Name Billing Class Employee No. Item Line Class Transaction Date Job No. Customer Service Item Notes Payroll Item Billable Employee Paid Day Rate Duration Days Remarks Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-03 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 2 0 Assisting platform with punch list. Holding morning meets to discuss daily and work going forward. Talking to Sawyer on delivery of spare HPU for NB crane Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-04 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting platform with punch list. Holding morning meets to discuss daily and work going forward. Talking to Sawyer on delivery of spare HPU for NB crane Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-05 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting platform with punch list. Holding morning meets to discuss daily and work going forward. Talking to Sawyer on delivery of spare HPU for NB crane Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-06 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting platform with punch list. Holding morning meets to discuss daily and work going forward. Talking to Sawyer on delivery of spare HPU for NB crane Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-07 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting platform with punch list. Holding morning meets to discuss daily and work going forward. Talking to Sawyer on delivery of spare HPU for NB crane Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-08 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting platform with punch list. Holding morning meets to discuss daily and work going forward. Talking to Sawyer on delivery of spare HPU for NB crane Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-09 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 2 0 Assisting platform with punch list. Holding morning meets to discuss daily and work going forward. Talking to Sawyer on delivery of spare HPU for NB crane Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-10 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 2 0 Assisting Holly Platform with punch list items. Holding morning conference call meetings. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-11 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting Holly Platform with punch list items. Holding morning conference call meetings. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-12 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting Holly Platform with punch list items. Holding morning conference call meetings. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-13 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting Holly Platform with punch list items. Holding morning conference call meetings. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-14 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting Holly Platform with punch list items. Holding morning conference call meetings. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-15 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting Holly Platform with punch list items. Holding morning conference call meetings. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-16 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 2 0 Assisting Holly Platform with punch list items. Holding morning conference call meetings. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-17 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 2 0 Assisting Holly Platform with punch list. Working with DPR on adding a Cmt tie-in line above isolation valve. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-18 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting Holly Platform with punch list. Working with DPR on adding a Cmt tie-in line above isolation valve. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-19 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting Holly Platform with punch list. Working with DPR on adding a Cmt tie-in line above isolation valve. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-20 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting Holly Platform with punch list. Working with DPR on adding a Cmt tie-in line above isolation valve. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-21 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting Holly Platform with punch list. Working with DPR on adding a Cmt tie-in line above isolation valve. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-22 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting Holly Platform with punch list. Working with DPR on adding a Cmt tie-in line above isolation valve. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-23 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 2 0 Assisting Holly Platform with punch list. Working with DPR on adding a Cmt tie-in line above isolation valve. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-24 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 2 0 Assisting Holly platform with punch list. Working with TS on eastside egress planning and cost estimate. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-25 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting Holly platform with punch list. Working with TS on eastside egress planning and cost estimate. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-26 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting Holly platform with punch list. Working with TS on eastside egress planning and cost estimate. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-27 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting Holly platform with punch list. Working with TS on eastside egress planning and cost estimate. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-28 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting Holly platform with punch list. Working with TS on eastside egress planning and cost estimate. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-29 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Assisting Holly platform with punch list. Working with TS on eastside egress planning and cost estimate. Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2020-05-30 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 2 0 Assisting Holly platform with punch list. Working with TS on eastside egress planning and cost estimate. Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-04 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 8 0 update presentation, refine, review, adjust, review again, give presentation, discuss path forward, work on equipment list, set up meetings, adjust functional spec, work on kpi table, work on questions list Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-04 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Ops call, TSR meeting, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-04 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.5 0 timesheet Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-05 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 7.75 0 update presentation, refine, review, adjust, review again, give presentation, discuss path forward, work on equipment list, set up meetings, adjust functional spec, work on kpi table, work on questions list Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-05 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.25 0 timesheet Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-06 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 1.25 0 update presentation, refine, review, adjust, review again, give presentation, discuss path forward, work on equipment list, set up meetings, adjust functional spec, work on kpi table, work on questions list Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-06 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.25 0 timesheet Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-06 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-04 Operations on Rails Detailed Design - OH Regular Pay N 6.5 0 work on sending documents, updating MDR, respond to cost questions, review drawing modifications, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-07 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 6 0 update presentation, refine, review, adjust, review again, give presentation, discuss path forward, work on equipment list, set up meetings, adjust functional spec, work on kpi table, work on questions list Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-07 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Ops call, TSR meeting, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-07 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-04 Operations on Rails Detailed Design - OH Regular Pay N 1.75 0 work on sending documents, updating MDR, respond to cost questions, review drawing modifications, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-08 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 6 0 update presentation, refine, review, adjust, review again, give presentation, discuss path forward, work on equipment list, set up meetings, adjust functional spec, work on kpi table, work on questions list Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-08 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.25 0 timesheet Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-08 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-04 Operations on Rails Detailed Design - OH Regular Pay N 2 0 work on sending documents, updating MDR, respond to cost questions, review drawing modifications, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-11 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 6 0 formatting equipment list, Drillmec call, call with Sheri, call with Greg, call with Entro, call with Greg and Kyle, update equipment list and other attachments, call with Greg, call with Shawn, zip files and send to Jack, meeting to review willow pathforward, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-11 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.75 0 Ops call, TSR meeting, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-11 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.5 0 timesheet Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-11 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-04 Operations on Rails Detailed Design - OH Regular Pay N 2.5 0 Discuss drawings with James, 270L Closeout report, doc review for Mio and Valery, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-12 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 6 0 formatting equipment list, Drillmec call, call with Sheri, call with Greg, call with Entro, call with Greg and Kyle, update equipment list and other attachments, call with Greg, call with Shawn, zip files and send to Jack, meeting to review willow pathforward, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-12 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.25 0 timesheet Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-12 OH-019 :OH-019 Overhead All Activities Regular Pay N 0.75 0 SAK meeting Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-12 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-04 Operations on Rails Detailed Design - OH Regular Pay N 1 0 Discuss drawings with James, 270L Closeout report, doc review for Mio and Valery, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-13 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 6 0 formatting equipment list, Drillmec call, call with Sheri, call with Greg, call with Entro, call with Greg and Kyle, update equipment list and other attachments, call with Greg, call with Shawn, zip files and send to Jack, meeting to review willow pathforward, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-13 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.5 0 timesheet Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-13 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-04 Operations on Rails Detailed Design - OH Regular Pay N 1.5 0 Discuss drawings with James, 270L Closeout report, doc review for Mio and Valery, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-13 Rig 273L-TSR :Rig 273L-TSR TSR-01758-AADU BOP Ram Installation & Removal Tool System Regular Pay N 1 0 Review concept with Tyler and Dan Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-14 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 4 0 formatting equipment list, Drillmec call, call with Sheri, call with Greg, call with Entro, call with Greg and Kyle, update equipment list and other attachments, call with Greg, call with Shawn, zip files and send to Jack, meeting to review willow pathforward, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-14 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.75 0 Ops call, TSR meeting, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-14 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 3 0 Review TSR material, create CTR, start creating model Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-14 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-04 Operations on Rails Detailed Design - OH Regular Pay N 1 0 Discuss drawings with James, 270L Closeout report, doc review for Mio and Valery, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-15 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 1 0 formatting equipment list, Drillmec call, call with Sheri, call with Greg, call with Entro, call with Greg and Kyle, update equipment list and other attachments, call with Greg, call with Shawn, zip files and send to Jack, meeting to review willow pathforward, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-15 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.5 0 timesheet Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-15 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 3.5 0 Review TSR material, create CTR, start creating model Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-15 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-04 Operations on Rails Detailed Design - OH Regular Pay N 1 0 Discuss drawings with James, 270L Closeout report, doc review for Mio and Valery, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-18 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 2 0 emails with rig builders, create meeting, meeting with huisman and drillmec, meeting with nov, entro and drillmec, call with Greg and Byers, bulletin, created project cost estimate outline Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-18 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.5 0 Ops call, TSR meeting Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-18 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.5 0 timesheet, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-18 OH-019 :OH-019 Overhead All Activities Regular Pay N 0.75 0 SAK call Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-18 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 3.25 0 model lifting tool, review design with Mio, make changes, start analysis, weight analysis, adjusted model, reran analysis, created TPP, researched material specs, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-18 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-04 Operations on Rails Detailed Design - OH Regular Pay N 2 0 documentation discussion with Mio, response to trucking fastening of accordion system, modify closeout report, contact Norm with EMI Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-19 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 4 0 emails with rig builders, create meeting, meeting with huisman and drillmec, meeting with nov, entro and drillmec, call with Greg and Byers, bulletin, created project cost estimate outline Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-19 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.25 0 timesheet, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-19 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 4.5 0 model lifting tool, review design with Mio, make changes, start analysis, weight analysis, adjusted model, reran analysis, created TPP, researched material specs, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-20 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 1.5 0 emails with rig builders, create meeting, meeting with huisman and drillmec, meeting with nov, entro and drillmec, call with Greg and Byers, bulletin, created project cost estimate outline Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-20 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 6.5 0 model lifting tool, review design with Mio, make changes, start analysis, weight analysis, adjusted model, reran analysis, created TPP, researched material specs, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-21 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 4.5 0 emails with rig builders, create meeting, meeting with huisman and drillmec, meeting with nov, entro and drillmec, call with Greg and Byers, bulletin, created project cost estimate outline Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-21 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.75 0 Ops call, TSR meeting Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-21 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.5 0 timesheet, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-21 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 3 0 model lifting tool, review design with Mio, make changes, start analysis, weight analysis, adjusted model, reran analysis, created TPP, researched material specs, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-22 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.25 0 timesheet, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-22 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 5.75 0 model lifting tool, review design with Mio, make changes, start analysis, weight analysis, adjusted model, reran analysis, created TPP, researched material specs, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-25 OH-008 :OH-008 Overhead All Activities Regular Pay N 8 0 Memorial Day Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-26 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 1 0 Send out bulletin, respond to Huisman questions, adjust project cost estimate, create list of equipment for supply chain to quote Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-26 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.25 0 timesheet Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-26 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 4.5 0 review and modify CTR, create TPP, call Kennedy Fab for questions, adjust design, create analysis report, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-26 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-04 Operations on Rails Detailed Design - OH Regular Pay N 3.25 0 Transfer all final documentation to Corporate Doc Control Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-27 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 4 0 Send out bulletin, respond to Huisman questions, adjust project cost estimate, create list of equipment for supply chain to quote Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-27 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.25 0 timesheet Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-27 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 3 0 review and modify CTR, create TPP, call Kennedy Fab for questions, adjust design, create analysis report, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-27 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-04 Operations on Rails Detailed Design - OH Regular Pay N 1.5 0 Transfer all final documentation to Corporate Doc Control Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-28 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 3 0 Send out bulletin, respond to Huisman questions, adjust project cost estimate, create list of equipment for supply chain to quote Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-28 OH-004 :OH-004 Overhead All Activities Regular Pay N 2.25 0 TSR meeting, safety meeting prep Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-28 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.25 0 timesheet Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-28 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 3 0 review and modify CTR, create TPP, call Kennedy Fab for questions, adjust design, create analysis report, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-29 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 1.75 0 Send out bulletin, respond to Huisman questions, adjust project cost estimate, create list of equipment for supply chain to quote Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-29 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.25 0 timesheet Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2020-05-29 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 4 0 review and modify CTR, create TPP, call Kennedy Fab for questions, adjust design, create analysis report, Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-04 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.5 0 (05/04/20) Weekly call with Sakhalin. (05/07/20) Weekly TSR call. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-04 OH-006 :OH-006 Overhead All Activities Regular Pay N 2 0 (05/04/20) Update call with Kyle. Reviewed new Orlan TSR scope. Update call with Tyler. Update call with Lam. Review and approve designers timesheets. Updated weekly timesheet and submitted for approval. (05/05/20) Update call with Kyle. Update call with Jorge. (05/06/20) Update call with Tyler. Update call with Kyle. (05/07/20) Pulled ref info for TSR call- safety moment. Update call with Kyle. Update call with Jorge. (05/08/20) Update call with kyle. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-04 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-01 Operations on Rails Detailed Design - DESIGN Regular Pay N 6 0 (05/04/20) Updated drawing list and sent to Sakhalin. Reviewed BOP/Diverter redlines from Sakhalin. Laid out stack with modified dims provided by Sakh. (05/05/20) Reviewed diverter comments from troy/Sakhalin. Started revisions to diverter drawing. (05/06/20) Finalized diverter drawing and sent to Sakh. for review. (05/07/20) Revised second diverter stack drawing. Compiled drawing files for signature and transmittal. (05/08/20) Finalized drawing check of stair drawing and send redlines to Lam. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-05 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.75 0 (05/04/20) Update call with Kyle. Reviewed new Orlan TSR scope. Update call with Tyler. Update call with Lam. Review and approve designers timesheets. Updated weekly timesheet and submitted for approval. (05/05/20) Update call with Kyle. Update call with Jorge. (05/06/20) Update call with Tyler. Update call with Kyle. (05/07/20) Pulled ref info for TSR call- safety moment. Update call with Kyle. Update call with Jorge. (05/08/20) Update call with kyle. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-05 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-01 Operations on Rails Detailed Design - DESIGN Regular Pay N 7.75 0 (05/04/20) Updated drawing list and sent to Sakhalin. Reviewed BOP/Diverter redlines from Sakhalin. Laid out stack with modified dims provided by Sakh. (05/05/20) Reviewed diverter comments from troy/Sakhalin. Started revisions to diverter drawing. (05/06/20) Finalized diverter drawing and sent to Sakh. for review. (05/07/20) Revised second diverter stack drawing. Compiled drawing files for signature and transmittal. (05/08/20) Finalized drawing check of stair drawing and send redlines to Lam. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-06 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 (05/04/20) Update call with Kyle. Reviewed new Orlan TSR scope. Update call with Tyler. Update call with Lam. Review and approve designers timesheets. Updated weekly timesheet and submitted for approval. (05/05/20) Update call with Kyle. Update call with Jorge. (05/06/20) Update call with Tyler. Update call with Kyle. (05/07/20) Pulled ref info for TSR call- safety moment. Update call with Kyle. Update call with Jorge. (05/08/20) Update call with kyle. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-06 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1.75 0 (05/06/20) Archived 209 HP spool drawing from Sakh. Printed 209l ATC stair/ladder drawing for review. (05/07/20) Started checking ATC stair/ladder drawings. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-06 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-01 Operations on Rails Detailed Design - DESIGN Regular Pay N 5.75 0 (05/04/20) Updated drawing list and sent to Sakhalin. Reviewed BOP/Diverter redlines from Sakhalin. Laid out stack with modified dims provided by Sakh. (05/05/20) Reviewed diverter comments from troy/Sakhalin. Started revisions to diverter drawing. (05/06/20) Finalized diverter drawing and sent to Sakh. for review. (05/07/20) Revised second diverter stack drawing. Compiled drawing files for signature and transmittal. (05/08/20) Finalized drawing check of stair drawing and send redlines to Lam. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-07 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 (05/04/20) Weekly call with Sakhalin. (05/07/20) Weekly TSR call. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-07 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.75 0 (05/04/20) Update call with Kyle. Reviewed new Orlan TSR scope. Update call with Tyler. Update call with Lam. Review and approve designers timesheets. Updated weekly timesheet and submitted for approval. (05/05/20) Update call with Kyle. Update call with Jorge. (05/06/20) Update call with Tyler. Update call with Kyle. (05/07/20) Pulled ref info for TSR call- safety moment. Update call with Kyle. Update call with Jorge. (05/08/20) Update call with kyle. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-07 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 3.75 0 (05/06/20) Archived 209 HP spool drawing from Sakh. Printed 209l ATC stair/ladder drawing for review. (05/07/20) Started checking ATC stair/ladder drawings. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-07 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-01 Operations on Rails Detailed Design - DESIGN Regular Pay N 3 0 (05/04/20) Updated drawing list and sent to Sakhalin. Reviewed BOP/Diverter redlines from Sakhalin. Laid out stack with modified dims provided by Sakh. (05/05/20) Reviewed diverter comments from troy/Sakhalin. Started revisions to diverter drawing. (05/06/20) Finalized diverter drawing and sent to Sakh. for review. (05/07/20) Revised second diverter stack drawing. Compiled drawing files for signature and transmittal. (05/08/20) Finalized drawing check of stair drawing and send redlines to Lam. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-08 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.25 0 (05/04/20) Update call with Kyle. Reviewed new Orlan TSR scope. Update call with Tyler. Update call with Lam. Review and approve designers timesheets. Updated weekly timesheet and submitted for approval. (05/05/20) Update call with Kyle. Update call with Jorge. (05/06/20) Update call with Tyler. Update call with Kyle. (05/07/20) Pulled ref info for TSR call- safety moment. Update call with Kyle. Update call with Jorge. (05/08/20) Update call with kyle. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-08 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-01 Operations on Rails Detailed Design - DESIGN Regular Pay N 5.75 0 (05/04/20) Updated drawing list and sent to Sakhalin. Reviewed BOP/Diverter redlines from Sakhalin. Laid out stack with modified dims provided by Sakh. (05/05/20) Reviewed diverter comments from troy/Sakhalin. Started revisions to diverter drawing. (05/06/20) Finalized diverter drawing and sent to Sakh. for review. (05/07/20) Revised second diverter stack drawing. Compiled drawing files for signature and transmittal. (05/08/20) Finalized drawing check of stair drawing and send redlines to Lam. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-11 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.25 0 (05/11/20) Weekly call with Sakhalin (rescheduled). (05/12/20) Sakhalin call. (05/13/20) Call with Lam/Kyle to review RUSA drafting standards. (05/14/20) Weekly TSR call. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-11 OH-005 :OH-005 Overhead All Activities Regular Pay N 0.25 0 (05/11/20) Pulled Bomco subbase dimensions and send pdf to Kyle. (05/12/20) Email request sent to Sakh - latest Odoptu South site plan drawing (searched current files). (05/13/20) Searched through archive for metric drawings as reference to future drafting standards. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-11 OH-006 :OH-006 Overhead All Activities Regular Pay N 3 0 (05/11/20) Update call with Tyler. Submitted IT ticket to restore PDf folder on Q. Assigned Jorge to Orlan lifting tool TSR and discussed. Fixed folders after IT restore. (05/12/20) Reviewed RUSA titleblock/info. Call with Kyle to review RUSA standards. Updated weekly timesheet and submitted for approval. Update call with Jorge. Update call with Lam. Reset printed/computer to resolve print issues. (05/13/20) Call with Kyle to discuss pump info. (05/14/20) Update call with Tyler. Call with Kyle-MP package call with Lam - RUSA standards. (05/15/20) Update call with Kyle. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-11 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-01 Operations on Rails Detailed Design - DESIGN Regular Pay N 5 0 (05/11/20) Organized drawing folders. Checked Loadmaster drawings against drawing list. Updated sheet and revision numbers as needed. Transmitted updated list to Sakh. Reviewed site plan received from Sakhalin. (05/13/20) reviewed site plan from Sakh. Started BOP stack sketch. (05/14/20) started site plan drawing. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-12 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.75 0 (05/11/20) Weekly call with Sakhalin (rescheduled). (05/12/20) Sakhalin call. (05/13/20) Call with Lam/Kyle to review RUSA drafting standards. (05/14/20) Weekly TSR call. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-12 OH-005 :OH-005 Overhead All Activities Regular Pay N 0.5 0 (05/11/20) Pulled Bomco subbase dimensions and send pdf to Kyle. (05/12/20) Email request sent to Sakh - latest Odoptu South site plan drawing (searched current files). (05/13/20) Searched through archive for metric drawings as reference to future drafting standards. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-12 OH-006 :OH-006 Overhead All Activities Regular Pay N 5.5 0 (05/11/20) Update call with Tyler. Submitted IT ticket to restore PDf folder on Q. Assigned Jorge to Orlan lifting tool TSR and discussed. Fixed folders after IT restore. (05/12/20) Reviewed RUSA titleblock/info. Call with Kyle to review RUSA standards. Updated weekly timesheet and submitted for approval. Update call with Jorge. Update call with Lam. Reset printed/computer to resolve print issues. (05/13/20) Call with Kyle to discuss pump info. (05/14/20) Update call with Tyler. Call with Kyle-MP package call with Lam - RUSA standards. (05/15/20) Update call with Kyle. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-12 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 1.5 0 (05/12/20) Printed drawings for review. (05/13/20) Drawing check. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-13 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 (05/11/20) Weekly call with Sakhalin (rescheduled). (05/12/20) Sakhalin call. (05/13/20) Call with Lam/Kyle to review RUSA drafting standards. (05/14/20) Weekly TSR call. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-13 OH-005 :OH-005 Overhead All Activities Regular Pay N 1 0 (05/11/20) Pulled Bomco subbase dimensions and send pdf to Kyle. (05/12/20) Email request sent to Sakh - latest Odoptu South site plan drawing (searched current files). (05/13/20) Searched through archive for metric drawings as reference to future drafting standards. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-13 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.25 0 (05/11/20) Update call with Tyler. Submitted IT ticket to restore PDf folder on Q. Assigned Jorge to Orlan lifting tool TSR and discussed. Fixed folders after IT restore. (05/12/20) Reviewed RUSA titleblock/info. Call with Kyle to review RUSA standards. Updated weekly timesheet and submitted for approval. Update call with Jorge. Update call with Lam. Reset printed/computer to resolve print issues. (05/13/20) Call with Kyle to discuss pump info. (05/14/20) Update call with Tyler. Call with Kyle-MP package call with Lam - RUSA standards. (05/15/20) Update call with Kyle. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-13 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 2.25 0 (05/13/20) Finalized Orlan casing jetting tool check and sent redlines to Jorge. Assigned drawing number for tool. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-13 OH-034 :OH-034 OH-034-008 Mexico Regular Pay N 1.5 0 (05/13/20) Researched mud pump info per request from Chuck. (05/14/20) Pulled pump info and sent to Chuck. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-13 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 0.5 0 (05/12/20) Printed drawings for review. (05/13/20) Drawing check. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-13 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-01 Operations on Rails Detailed Design - DESIGN Regular Pay N 2 0 (05/11/20) Organized drawing folders. Checked Loadmaster drawings against drawing list. Updated sheet and revision numbers as needed. Transmitted updated list to Sakh. Reviewed site plan received from Sakhalin. (05/13/20) reviewed site plan from Sakh. Started BOP stack sketch. (05/14/20) started site plan drawing. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-14 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 (05/11/20) Weekly call with Sakhalin (rescheduled). (05/12/20) Sakhalin call. (05/13/20) Call with Lam/Kyle to review RUSA drafting standards. (05/14/20) Weekly TSR call. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-14 OH-006 :OH-006 Overhead All Activities Regular Pay N 1.75 0 (05/11/20) Update call with Tyler. Submitted IT ticket to restore PDf folder on Q. Assigned Jorge to Orlan lifting tool TSR and discussed. Fixed folders after IT restore. (05/12/20) Reviewed RUSA titleblock/info. Call with Kyle to review RUSA standards. Updated weekly timesheet and submitted for approval. Update call with Jorge. Update call with Lam. Reset printed/computer to resolve print issues. (05/13/20) Call with Kyle to discuss pump info. (05/14/20) Update call with Tyler. Call with Kyle-MP package call with Lam - RUSA standards. (05/15/20) Update call with Kyle. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-14 OH-034 :OH-034 OH-034-004 Aksai Regular Pay N 4.25 0 (05/14/20) reviewed info from field and started table sketch for 249L. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-14 OH-034 :OH-034 OH-034-008 Mexico Regular Pay N 1.5 0 (05/13/20) Researched mud pump info per request from Chuck. (05/14/20) Pulled pump info and sent to Chuck. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-15 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.25 0 (05/11/20) Update call with Tyler. Submitted IT ticket to restore PDf folder on Q. Assigned Jorge to Orlan lifting tool TSR and discussed. Fixed folders after IT restore. (05/12/20) Reviewed RUSA titleblock/info. Call with Kyle to review RUSA standards. Updated weekly timesheet and submitted for approval. Update call with Jorge. Update call with Lam. Reset printed/computer to resolve print issues. (05/13/20) Call with Kyle to discuss pump info. (05/14/20) Update call with Tyler. Call with Kyle-MP package call with Lam - RUSA standards. (05/15/20) Update call with Kyle. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-15 OH-034 :OH-034 OH-034-004 Aksai Regular Pay N 6 0 (05/14/20) reviewed info from field and started table sketch for 249L. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-18 OH-006 :OH-006 Overhead All Activities Regular Pay N 2 0 (05/18/20) Update call with Kyle. Update call with Lam. Update call with Jorge. Review/approved designer's timesheets. (05/19/20) Updated weekly timesheet and submitted for approval. Update call with Tyler. Update call with Kyle. (05/20/20) Update call with Jorge. Update call with Tyler. (05/21/20) Update call with Jorge. Update call with Tyler. Update call with Kyle. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-18 OH-019 :OH-019 Overhead All Activities Regular Pay N 1 0 (05/18/20) Weekly call with Sakhalin. Call to discuss ATC concepts. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-18 OH-034 :OH-034 OH-034-004 Aksai Regular Pay N 5.5 0 (05/18/20) Continued on utility table design drawing. (05/19/20) Final drawing details. Checked drawing and made changes - sent to Tyler for review. (05/22/20) Discussed drawing with Tyler and started changes. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-19 OH-006 :OH-006 Overhead All Activities Regular Pay N 2 0 (05/18/20) Update call with Kyle. Update call with Lam. Update call with Jorge. Review/approved designer's timesheets. (05/19/20) Updated weekly timesheet and submitted for approval. Update call with Tyler. Update call with Kyle. (05/20/20) Update call with Jorge. Update call with Tyler. (05/21/20) Update call with Jorge. Update call with Tyler. Update call with Kyle. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-19 OH-034 :OH-034 OH-034-004 Aksai Regular Pay N 6.5 0 (05/18/20) Continued on utility table design drawing. (05/19/20) Final drawing details. Checked drawing and made changes - sent to Tyler for review. (05/22/20) Discussed drawing with Tyler and started changes. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-20 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 (05/18/20) Update call with Kyle. Update call with Lam. Update call with Jorge. Review/approved designer's timesheets. (05/19/20) Updated weekly timesheet and submitted for approval. Update call with Tyler. Update call with Kyle. (05/20/20) Update call with Jorge. Update call with Tyler. (05/21/20) Update call with Jorge. Update call with Tyler. Update call with Kyle. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-20 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-01 Operations on Rails Detailed Design - DESIGN Regular Pay N 7.5 0 (05/20/20) 270L site plan drawing updates (SWS). (05/21/20) Finalized site plan - sent for signature. (05/22/20) Transmitted site plan and updated both drawing list. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-21 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.75 0 (05/21/20) Weekly TSR call. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-21 OH-006 :OH-006 Overhead All Activities Regular Pay N 1.5 0 (05/18/20) Update call with Kyle. Update call with Lam. Update call with Jorge. Review/approved designer's timesheets. (05/19/20) Updated weekly timesheet and submitted for approval. Update call with Tyler. Update call with Kyle. (05/20/20) Update call with Jorge. Update call with Tyler. (05/21/20) Update call with Jorge. Update call with Tyler. Update call with Kyle. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-21 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-01 Operations on Rails Detailed Design - DESIGN Regular Pay N 6.25 0 (05/20/20) 270L site plan drawing updates (SWS). (05/21/20) Finalized site plan - sent for signature. (05/22/20) Transmitted site plan and updated both drawing list. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-22 OH-034 :OH-034 OH-034-004 Aksai Regular Pay N 5 0 (05/18/20) Continued on utility table design drawing. (05/19/20) Final drawing details. Checked drawing and made changes - sent to Tyler for review. (05/22/20) Discussed drawing with Tyler and started changes. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-22 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-01 Operations on Rails Detailed Design - DESIGN Regular Pay N 1 0 (05/20/20) 270L site plan drawing updates (SWS). (05/21/20) Finalized site plan - sent for signature. (05/22/20) Transmitted site plan and updated both drawing list. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-25 OH-008 :OH-008 Overhead All Activities Regular Pay N 8 0 Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-26 OH-004 :OH-004 Overhead All Activities Regular Pay N 1.25 0 (05/25/20) Call to discuss general arrangement drawings for Genesis. Call to discuss Holly egress options. (05/28/20) Call with Loadmaster to discuss genesis GA drawings. Weekly TSR call. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-26 OH-006 :OH-006 Overhead All Activities Regular Pay N 3.5 0 (05/25/20) Update call with Kyle. Update call with Tyler. Update call with Lam. researched issue with metric drawing. Update call with Jorge. (05/26/20) Update with Kyle. Call with Lam-CAD issue. Update call with Tyler. (05/28/20) Updated weekly timesheet and submitted for approval. Update call with Lam-Holly. Reviewed/approved designer timesheets. (05/29/20) Update with lam-209 ATC. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-26 OH-034 :OH-034 OH-034-004 Aksai Regular Pay N 3.75 0 (05/25/20) Redlines - 249L utility table. (05/29/20) Reviewed 249 chemical loading ramp drawing per question from field. Sent response. 249 table drawing- updates. Sent for signature. transmitted file and archived on the Q. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-27 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 (05/25/20) Update call with Kyle. Update call with Tyler. Update call with Lam. researched issue with metric drawing. Update call with Jorge. (05/26/20) Update with Kyle. Call with Lam-CAD issue. Update call with Tyler. (05/28/20) Updated weekly timesheet and submitted for approval. Update call with Lam-Holly. Reviewed/approved designer timesheets. (05/29/20) Update with lam-209 ATC. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-27 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-01 Operations on Rails Detailed Design - DESIGN Regular Pay N 7.5 0 (05/26/20) 270L BOP sketch. (05/28/20) Cont BOP layouts. (05/29/20) Finalized Bop layout and started diverter dwg. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-28 OH-004 :OH-004 Overhead All Activities Regular Pay N 1.5 0 (05/25/20) Call to discuss general arrangement drawings for Genesis. Call to discuss Holly egress options. (05/28/20) Call with Loadmaster to discuss genesis GA drawings. Weekly TSR call. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-28 OH-005 :OH-005 Overhead All Activities Regular Pay N 2.5 0 (05/28/20) No power down time. VPN connection issue. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-28 OH-006 :OH-006 Overhead All Activities Regular Pay N 2 0 (05/25/20) Update call with Kyle. Update call with Tyler. Update call with Lam. researched issue with metric drawing. Update call with Jorge. (05/26/20) Update with Kyle. Call with Lam-CAD issue. Update call with Tyler. (05/28/20) Updated weekly timesheet and submitted for approval. Update call with Lam-Holly. Reviewed/approved designer timesheets. (05/29/20) Update with lam-209 ATC. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-28 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-01 Operations on Rails Detailed Design - DESIGN Regular Pay N 2.5 0 (05/26/20) 270L BOP sketch. (05/28/20) Cont BOP layouts. (05/29/20) Finalized Bop layout and started diverter dwg. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-29 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.75 0 (05/25/20) Update call with Kyle. Update call with Tyler. Update call with Lam. researched issue with metric drawing. Update call with Jorge. (05/26/20) Update with Kyle. Call with Lam-CAD issue. Update call with Tyler. (05/28/20) Updated weekly timesheet and submitted for approval. Update call with Lam-Holly. Reviewed/approved designer timesheets. (05/29/20) Update with lam-209 ATC. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-29 OH-034 :OH-034 OH-034-004 Aksai Regular Pay N 3 0 (05/25/20) Redlines - 249L utility table. (05/29/20) Reviewed 249 chemical loading ramp drawing per question from field. Sent response. 249 table drawing- updates. Sent for signature. transmitted file and archived on the Q. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2020-05-29 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-01 Operations on Rails Detailed Design - DESIGN Regular Pay N 2.75 0 (05/26/20) 270L BOP sketch. (05/28/20) Cont BOP layouts. (05/29/20) Finalized Bop layout and started diverter dwg. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-04 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 2 0 Provide support as required. Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-04 OH-034 :OH-034 OH-034-005 Kazakhstan Regular Pay N 8 0 Attend Acceptance Testing for a generator set at J&R Engine Service in Oklahoma City for Mike Anatra. Developing test report result of the acceptance testing at J&R Engine Service. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-05 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 2 0 Provide support as required. Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-05 OH-034 :OH-034 OH-034-005 Kazakhstan Regular Pay N 8 0 Attend Acceptance Testing for a generator set at J&R Engine Service in Oklahoma City for Mike Anatra. Developing test report result of the acceptance testing at J&R Engine Service. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-06 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 8 0 Provide support as required. Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-07 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 8 0 Provide support as required. Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-08 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 4 0 Provide support as required. Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-11 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 3 0 Provide support as required. Contact NOV for drawings required for rig. Conference calls and reviewing the Parker Drilling Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-11 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 4 0 Provide support as required. Contact NOV for to obtain quote for an Independent Mud Pump Package to possibly install on rig 210 or possibly on rig 122.Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-11 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Answering company emails and taking phone calls. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-12 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 3 0 Provide support as required. Contact NOV for drawings required for rig. Conference calls and reviewing the Parker Drilling Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-12 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 4 0 Provide support as required. Contact NOV for to obtain quote for an Independent Mud Pump Package to possibly install on rig 210 or possibly on rig 122.Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-12 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Answering company emails and taking phone calls. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-13 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 3 0 Provide support as required. Contact NOV for drawings required for rig. Conference calls and reviewing the Parker Drilling Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-13 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 4 0 Provide support as required. Contact NOV for to obtain quote for an Independent Mud Pump Package to possibly install on rig 210 or possibly on rig 122.Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-13 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Answering company emails and taking phone calls. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-14 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 3 0 Provide support as required. Contact NOV for drawings required for rig. Conference calls and reviewing the Parker Drilling Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-14 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 4 0 Provide support as required. Contact NOV for to obtain quote for an Independent Mud Pump Package to possibly install on rig 210 or possibly on rig 122.Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-14 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Answering company emails and taking phone calls. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-15 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 3 0 Provide support as required. Contact NOV for drawings required for rig. Conference calls and reviewing the Parker Drilling Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-15 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 4 0 Provide support as required. Contact NOV for to obtain quote for an Independent Mud Pump Package to possibly install on rig 210 or possibly on rig 122.Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-15 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Answering company emails and taking phone calls. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-18 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 3 0 Provide support as required. Contact NOV for drawings required for rig. Conference calls and reviewing the Parker Drilling Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-18 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 4 0 Provide support as required. Contact NOV for to obtain quote for an Independent Mud Pump Package to possibly install on rig 210 or possibly on rig 122.Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-18 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Answering company emails and taking phone calls. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-19 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 3 0 Provide support as required. Contact NOV for drawings required for rig. Conference calls and reviewing the Parker Drilling Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-19 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 4 0 Provide support as required. Contact NOV for to obtain quote for an Independent Mud Pump Package to possibly install on rig 210 or possibly on rig 122.Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-19 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Answering company emails and taking phone calls. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-20 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 3 0 Provide support as required. Contact NOV for drawings required for rig. Conference calls and reviewing the Parker Drilling Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-20 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 4 0 Provide support as required. Contact NOV for to obtain quote for an Independent Mud Pump Package to possibly install on rig 210 or possibly on rig 122.Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-20 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Answering company emails and taking phone calls. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-21 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 3 0 Provide support as required. Contact NOV for drawings required for rig. Conference calls and reviewing the Parker Drilling Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-21 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 4 0 Provide support as required. Contact NOV for to obtain quote for an Independent Mud Pump Package to possibly install on rig 210 or possibly on rig 122.Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-21 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Answering company emails and taking phone calls. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-22 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 3 0 Provide support as required. Contact NOV for drawings required for rig. Conference calls and reviewing the Parker Drilling Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-22 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 4 0 Provide support as required. Contact NOV for to obtain quote for an Independent Mud Pump Package to possibly install on rig 210 or possibly on rig 122.Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-22 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Answering company emails and taking phone calls. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-25 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 3 0 Provide support as required. Contact NOV for drawings required for rig. Conference calls and reviewing the Parker Drilling Rig 212 Action Items List. Attending weekly update conference calls with Jaguar and Patterson. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-25 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 4 0 Provide support as required. Contact NOV for to obtain quote for an Independent Mud Pump Package to possibly install on rig 210 or possibly on rig 122.Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-25 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Answering company emails and taking phone calls providing support for miscellaneous projects for S. Carmichael and B. Collins. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-26 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 3 0 Provide support as required. Contact NOV for drawings required for rig. Conference calls and reviewing the Parker Drilling Rig 212 Action Items List. Attending weekly update conference calls with Jaguar and Patterson. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-26 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 4 0 Provide support as required. Contact NOV for to obtain quote for an Independent Mud Pump Package to possibly install on rig 210 or possibly on rig 122.Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-26 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Answering company emails and taking phone calls providing support for miscellaneous projects for S. Carmichael and B. Collins. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-27 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 3 0 Provide support as required. Contact NOV for drawings required for rig. Conference calls and reviewing the Parker Drilling Rig 212 Action Items List. Attending weekly update conference calls with Jaguar and Patterson. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-27 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 3 0 Provide support as required. Contact NOV for to obtain quote for an Independent Mud Pump Package to possibly install on rig 210 or possibly on rig 122.Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-27 OH-006 :OH-006 Overhead All Activities Regular Pay N 3 0 Answering company emails and taking phone calls providing support for miscellaneous projects for S. Carmichael and B. Collins. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-28 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 3 0 Provide support as required. Contact NOV for drawings required for rig. Conference calls and reviewing the Parker Drilling Rig 212 Action Items List. Attending weekly update conference calls with Jaguar and Patterson. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-28 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 4 0 Provide support as required. Contact NOV for to obtain quote for an Independent Mud Pump Package to possibly install on rig 210 or possibly on rig 122.Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-28 OH-006 :OH-006 Overhead All Activities Regular Pay N 2 0 Answering company emails and taking phone calls providing support for miscellaneous projects for S. Carmichael and B. Collins. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-29 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 3 0 Provide support as required. Contact NOV for drawings required for rig. Conference calls and reviewing the Parker Drilling Rig 212 Action Items List. Attending weekly update conference calls with Jaguar and Patterson. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-29 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 2 0 Provide support as required. Contact NOV for to obtain quote for an Independent Mud Pump Package to possibly install on rig 210 or possibly on rig 122.Conference calls and reviewing the Parker Drilling - Rig 210 Action Plan Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2020-05-29 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Answering company emails and taking phone calls providing support for miscellaneous projects for S. Carmichael and B. Collins. Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-04 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Weekly Operations Conference Call; Tech Services Weekly Call Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-04 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.5 0 MK Timesheet Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-04 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 5 0 Update Competitor Financial Analysis with Q1 data; Office Lease Project - Data for ELT Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-04 OH-009 :OH-009 OH-009-015 Alaska Regular Pay N 1.5 0 COPA Willow Project Conference Calls Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-05 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 4 0 Update Competitor Financial Analysis with Q1 data; Office Lease Project - Data for ELT Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-05 OH-009 :OH-009 OH-009-015 Alaska Regular Pay N 1.5 0 COPA Willow Project Conference Calls Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-05 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 2.5 0 NCOC Rig 401 Tender - Update Project Documents Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-06 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 8 0 NCOC Rig 401 Tender - Update Project Documents Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-07 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Weekly Operations Conference Call; Tech Services Weekly Call Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-07 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 4 0 Update Competitor Financial Analysis with Q1 data; Office Lease Project - Data for ELT Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-07 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 3 0 NCOC Rig 401 Tender - Update Project Documents Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-08 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 8 0 Update Competitor Financial Analysis with Q1 data; Office Lease Project - Data for ELT Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-11 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Weekly Operations Conference Call; Tech Services Weekly Meeting Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-11 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.5 0 MK Timesheet Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-11 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 1 0 Update Competitor Financial Analysis; Office Lease Project Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-11 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 6 0 NCOC Workover Rig Tender Review and Presentation; NCOC Revamp Tender Support Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-12 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 9 0 NCOC Workover Rig Tender Review and Presentation; NCOC Revamp Tender Support Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-13 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 9 0 NCOC Workover Rig Tender Review and Presentation; NCOC Revamp Tender Support Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-14 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Weekly Operations Conference Call; Tech Services Weekly Meeting Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-14 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 1 0 Update Competitor Financial Analysis; Office Lease Project Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-14 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 6 0 NCOC Workover Rig Tender Review and Presentation; NCOC Revamp Tender Support Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-15 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 1 0 Update Competitor Financial Analysis; Office Lease Project Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-15 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 7 0 NCOC Workover Rig Tender Review and Presentation; NCOC Revamp Tender Support Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-18 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Weekly Operations Conference Call; Tech Services Weekly Meeting Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-18 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.5 0 MK Timesheet Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-18 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 2 0 Update Competitor Financial Analysis; Edit D3O Whitepaper Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-18 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 4.5 0 NCOC Rig 401 Revamp Tender Support; NCOC Workover Rig Tender Project Planning Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-19 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 8 0 NCOC Rig 401 Revamp Tender Support; NCOC Workover Rig Tender Project Planning Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-20 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 8 0 NCOC Rig 401 Revamp Tender Support; NCOC Workover Rig Tender Project Planning Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-21 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Weekly Operations Conference Call; Tech Services Weekly Meeting Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-21 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 7 0 NCOC Rig 401 Revamp Tender Support; NCOC Workover Rig Tender Project Planning Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-22 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 3 0 Update Competitor Financial Analysis; Edit D3O Whitepaper Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-22 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 5 0 NCOC Rig 401 Revamp Tender Support; NCOC Workover Rig Tender Project Planning Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-25 OH-008 :OH-008 Overhead All Activities Regular Pay N 8 0 Memorial Day Holiday Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-26 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.5 0 MK Timesheet Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-26 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 3 0 D3O White Paper Review and Edit; Competitor Analysis Update with Carlos; Office Lease Calls and Emails with Jennifer Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-26 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 5.5 0 NCOC Workover Rig Tender Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-27 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 4 0 D3O White Paper Review and Edit; Competitor Analysis Update with Carlos; Office Lease Calls and Emails with Jennifer Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-27 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 5 0 NCOC Workover Rig Tender Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-28 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Technical Services Weekly Meeting Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-28 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 2 0 D3O White Paper Review and Edit; Competitor Analysis Update with Carlos; Office Lease Calls and Emails with Jennifer Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-28 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 5 0 NCOC Workover Rig Tender Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-29 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 3 0 D3O White Paper Review and Edit; Competitor Analysis Update with Carlos; Office Lease Calls and Emails with Jennifer Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2020-05-29 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 5 0 NCOC Workover Rig Tender Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-04 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 12 0 Travel to New Iberia, Work Order proposal, subcontracts, quotes Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-05 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 13 0 Travel to New Iberia, Work Order proposal, subcontracts, quotes Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-06 CVX Genesis :CVX Genesis TSR-1725-GENP-01 FEED Study/Detailed Design Regular Pay N 2 0 Monitor and control costs, technical clarifications, Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-06 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 12 0 Travel to New Iberia, Work Order proposal, subcontracts, quotes Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-07 CVX Genesis :CVX Genesis TSR-1725-GENP-01 FEED Study/Detailed Design Regular Pay N 2 0 Monitor and control costs, technical clarifications, Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-07 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 10 0 Travel to New Iberia, Work Order proposal, subcontracts, quotes Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-07 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 1 0 Monitor and control costs. submit timesheets Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-08 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 4 0 Travel to New Iberia, Work Order proposal, subcontracts, quotes Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-11 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 8 0 Commercial discussion with CVX on cost variance, installation procedure review requested by CVX, subcontracts, procurement technical evaluations, grasshopper layouts Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-11 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Sandy Esslemont 1x1 intro, weekly ops call Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-12 CVX Genesis :CVX Genesis TSR-1725-GENP-01 FEED Study/Detailed Design Regular Pay N 2 0 Technical clarifications, coordinate document control Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-12 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 7 0 Commercial discussion with CVX on cost variance, installation procedure review requested by CVX, subcontracts, procurement technical evaluations, grasshopper layouts Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-13 CVX Genesis :CVX Genesis TSR-1725-GENP-01 FEED Study/Detailed Design Regular Pay N 2 0 Technical clarifications, coordinate document control Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-13 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 7 0 Commercial discussion with CVX on cost variance, installation procedure review requested by CVX, subcontracts, procurement technical evaluations, grasshopper layouts Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-14 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 7 0 Commercial discussion with CVX on cost variance, installation procedure review requested by CVX, subcontracts, procurement technical evaluations, grasshopper layouts Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-14 OH-006 :OH-006 Overhead All Activities Regular Pay N 2 0 Sandy Esslemont 1x1 intro, weekly ops call Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-15 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 4 0 Commercial discussion with CVX on cost variance, installation procedure review requested by CVX, subcontracts, procurement technical evaluations, grasshopper layouts Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-18 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 8 0 Procurement, work orders, grasshopper and utilties interface, SIT procedure review, Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-18 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Weekly meetings Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-19 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 9 0 Procurement, work orders, grasshopper and utilties interface, SIT procedure review, Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-20 CVX Genesis :CVX Genesis TSR-1725-GENP-01 FEED Study/Detailed Design Regular Pay N 4 0 weekly report, weekly status meeting Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-20 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 5 0 Procurement, work orders, grasshopper and utilties interface, SIT procedure review, Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-21 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 8 0 Procurement, work orders, grasshopper and utilties interface, SIT procedure review, Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-21 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Weekly meetings Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-22 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 4 0 Procurement, work orders, grasshopper and utilties interface, SIT procedure review, Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-25 OH-008 :OH-008 Overhead All Activities Regular Pay N 8 0 Memo day Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-26 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 9 0 Procurement, work orders, grasshopper and utilities interface, Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-27 CVX Genesis :CVX Genesis TSR-1725-GENP-01 FEED Study/Detailed Design Regular Pay N 4 0 Technical review, documentation closeout Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-27 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 5 0 Procurement, work orders, grasshopper and utilities interface, Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-28 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 8 0 Procurement, work orders, grasshopper and utilities interface, Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-28 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Weekly meetings Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2020-05-29 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 5 0 Procurement, work orders, grasshopper and utilities interface, Little, Bryan Project Manager 31369 Little, Bryan:Project Manager 2020-05-04 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 4 0 Little, Bryan Project Manager 31369 Little, Bryan:Project Manager 2020-05-04 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 3 0 Little, Bryan Project Manager 31369 Little, Bryan:Project Manager 2020-05-05 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 5 0 Little, Bryan Project Manager 31369 Little, Bryan:Project Manager 2020-05-05 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 2 0 Little, Bryan Project Manager 31369 Little, Bryan:Project Manager 2020-05-06 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 3 0 Little, Bryan Project Manager 31369 Little, Bryan:Project Manager 2020-05-06 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 5 0 Little, Bryan Project Manager 31369 Little, Bryan:Project Manager 2020-05-07 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 4 0 Little, Bryan Project Manager 31369 Little, Bryan:Project Manager 2020-05-07 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 3 0 Little, Bryan Project Manager 31369 Little, Bryan:Project Manager 2020-05-08 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 1 0 Little, Bryan Project Manager 31369 Little, Bryan:Project Manager 2020-05-08 Latin America Region-TSR :Latin America Region-TSR TSR-01765-LABU Jaguar 2nd Rig - Mexico Regular Pay N 1 0 Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-04 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 5.5 0 Preparation for COPA presentation (numerous CC's, document review) Safety moment preparation for COPA presentation Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-04 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 0.5 0 212L Drawworks brake research / phone calls Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-04 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Weekly Operations CC Weekly HTSG Meeting CC with Steve C. and GO CC with intern CC with Lam N. (timesheets, SAK status, admin) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-04 OH-006 :OH-006 Overhead All Activities Regular Pay N 1.5 0 4-8 Forecast (multiple major changes) IHS Subscription administration Timesheet and approvals Reorganization of timekeeping system Sakhalin invoicing Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-04 OH-019 :OH-019 Overhead All Activities Regular Pay N 0.5 0 Weekly meeting and preparation Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-04 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 2 0 262L Reactivation Closeout review and approval 209L ATC Unit Roof Drawing review/redline Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-05 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 5 0 Preparation for COPA presentation (numerous CC's, document review) Safety moment preparation for COPA presentation Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-05 OH-006 :OH-006 Overhead All Activities Regular Pay N 2.5 0 4-8 Forecast (multiple major changes) IHS Subscription administration Timesheet and approvals Reorganization of timekeeping system Sakhalin invoicing Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-05 OH-009 :OH-009 OH-009-026 Kenya Regular Pay N 1 0 Super bundle email to Joe L. Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-05 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-04 Operations on Rails Detailed Design - OH Regular Pay N 0.75 0 Review / approve drawings (incl. safety plan) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-06 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 2.5 0 Preparation for COPA presentation (numerous CC's, document review) Safety moment preparation for COPA presentation Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-06 CVX Genesis :CVX Genesis TSR-1725-GENP-01 FEED Study/Detailed Design Regular Pay N 0.75 0 Load combination review / CC with LM Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-06 OH-004 :OH-004 Overhead All Activities Regular Pay N 1.75 0 Weekly Operations CC Weekly HTSG Meeting CC with Steve C. and GO CC with intern CC with Lam N. (timesheets, SAK status, admin) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-06 OH-006 :OH-006 Overhead All Activities Regular Pay N 2.75 0 4-8 Forecast (multiple major changes) IHS Subscription administration Timesheet and approvals Reorganization of timekeeping system Sakhalin invoicing Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-06 OH-013 :OH-013 Overhead All Activities Regular Pay N 0.75 0 Updating TSR tracker / preparation for meeting Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-06 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 0.75 0 262L Reactivation Closeout review and approval 209L ATC Unit Roof Drawing review/redline Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-07 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 2 0 Preparation for COPA presentation (numerous CC's, document review) Safety moment preparation for COPA presentation Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-07 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 0.75 0 Review of work orders Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-07 OH-004 :OH-004 Overhead All Activities Regular Pay N 1.5 0 Weekly Operations CC Weekly HTSG Meeting CC with Steve C. and GO CC with intern CC with Lam N. (timesheets, SAK status, admin) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-07 OH-006 :OH-006 Overhead All Activities Regular Pay N 3 0 4-8 Forecast (multiple major changes) IHS Subscription administration Timesheet and approvals Reorganization of timekeeping system Sakhalin invoicing Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-07 OH-013 :OH-013 Overhead All Activities Regular Pay N 0.75 0 Updating TSR tracker / preparation for meeting Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-07 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 0.5 0 262L Reactivation Closeout review and approval 209L ATC Unit Roof Drawing review/redline Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-07 OH-036 :OH-036 Overhead All Activities Regular Pay N 1 0 Conference Call with Clean Design (Canada) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-08 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 1.5 0 Preparation for COPA presentation (numerous CC's, document review) Safety moment preparation for COPA presentation Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-08 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 1 0 Review of work orders Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-08 OH-006 :OH-006 Overhead All Activities Regular Pay N 2.5 0 4-8 Forecast (multiple major changes) IHS Subscription administration Timesheet and approvals Reorganization of timekeeping system Sakhalin invoicing Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-08 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1.5 0 262L Reactivation Closeout review and approval 209L ATC Unit Roof Drawing review/redline Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-11 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 4 0 Transmittal organization Finalize review of rig-up procedure Chevron, LMI, PKD review of rig-up procedures (multi-day conference call) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-11 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Weekly operations conference call Weekly HTSG meeting Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-11 OH-006 :OH-006 Overhead All Activities Regular Pay N 2 0 Time sheet / approvals Finalizing forecast and answering inquiries Status updates from ENG/DES team CC with Steve Carmichael (x2) Tech Services update to Steve C. Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-11 OH-019 :OH-019 Overhead All Activities Regular Pay N 0.75 0 Weekly meeting Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-11 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1.25 0 Historical information sent to SAK ENG RE: Krechet rig move Finalizing 262L reactivation support closeout 209L Automation closeout review / revision / approval Sakhalin RUSA title block Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-11 OH-034 :OH-034 OH-034-006 Iraq Regular Pay N 1.5 0 Support Genel contract (email to Joe Lochridge) - cellar size(s) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-12 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 1 0 Meeting with Supply Chain Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-12 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 2.5 0 Transmittal organization Finalize review of rig-up procedure Chevron, LMI, PKD review of rig-up procedures (multi-day conference call) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-12 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 1 0 Review closeout document Independent mud pump skid Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-12 OH-006 :OH-006 Overhead All Activities Regular Pay N 1.5 0 Time sheet / approvals Finalizing forecast and answering inquiries Status updates from ENG/DES team CC with Steve Carmichael (x2) Tech Services update to Steve C. Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-12 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 2 0 Historical information sent to SAK ENG RE: Krechet rig move Finalizing 262L reactivation support closeout 209L Automation closeout review / revision / approval Sakhalin RUSA title block Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-12 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-04 Operations on Rails Detailed Design - OH Regular Pay N 1 0 Closeout review / redline Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-13 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 1 0 Meeting with Supply Chain Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-13 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 1 0 Transmittal organization Finalize review of rig-up procedure Chevron, LMI, PKD review of rig-up procedures (multi-day conference call) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-13 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 1 0 Review closeout document Independent mud pump skid Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-13 OH-006 :OH-006 Overhead All Activities Regular Pay N 2 0 Time sheet / approvals Finalizing forecast and answering inquiries Status updates from ENG/DES team CC with Steve Carmichael (x2) Tech Services update to Steve C. Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-13 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 2 0 NCOC Workover - meetings with MK, GO Reviewing tender documentation Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-13 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 2 0 Historical information sent to SAK ENG RE: Krechet rig move Finalizing 262L reactivation support closeout 209L Automation closeout review / revision / approval Sakhalin RUSA title block Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-14 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 1 0 Meeting with Supply Chain Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-14 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 1 0 Review closeout document Independent mud pump skid Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-14 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Weekly operations conference call Weekly HTSG meeting Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-14 OH-006 :OH-006 Overhead All Activities Regular Pay N 2 0 Time sheet / approvals Finalizing forecast and answering inquiries Status updates from ENG/DES team CC with Steve Carmichael (x2) Tech Services update to Steve C. Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-14 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 1 0 NCOC Workover - meetings with MK, GO Reviewing tender documentation Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-14 OH-013 :OH-013 Overhead All Activities Regular Pay N 1 0 Update TSR tracker Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-14 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1.5 0 Historical information sent to SAK ENG RE: Krechet rig move Finalizing 262L reactivation support closeout 209L Automation closeout review / revision / approval Sakhalin RUSA title block Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-15 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 1 0 Meeting with Supply Chain Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-15 OH-006 :OH-006 Overhead All Activities Regular Pay N 2 0 Time sheet / approvals Finalizing forecast and answering inquiries Status updates from ENG/DES team CC with Steve Carmichael (x2) Tech Services update to Steve C. Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-15 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 1 0 NCOC Workover - meetings with MK, GO Reviewing tender documentation Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-15 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1 0 Historical information sent to SAK ENG RE: Krechet rig move Finalizing 262L reactivation support closeout 209L Automation closeout review / revision / approval Sakhalin RUSA title block Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-15 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 0.75 0 Drawing review Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-15 Rig 270L-TSR :Rig 270L-TSR TSR-01743-270L-04 Operations on Rails Detailed Design - OH Regular Pay N 0.5 0 Closeout review / redline Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-18 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 1 0 Technical specification review (clarifications back to bidders) Bidder clarification meetings Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-18 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 0.5 0 Cost estimate review Document control administration SoW review Meeting with JL SIT procedure review (CC with Chevron) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-18 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Weekly Operations CC Weekly TSR Meeting CC with Matt Svoboda (Genesis Eng) CC with Karma (barge operating depths) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-18 OH-006 :OH-006 Overhead All Activities Regular Pay N 2.5 0 HTSG Marketing Material sent to SC HTSG hours summary CC's with all direct reports CC with Supply Chain (Loadmaster Universal Rig) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-18 OH-019 :OH-019 Overhead All Activities Regular Pay N 0.75 0 Weekly CC Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-18 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 4 0 Sakhalin invoicing clarifications Rig 209L rig-move meetings, CC, research Orlan bell nipple lifting tool (review) CTR revision; discuss with Mio and Mark Todd Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-19 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 2.5 0 Cost estimate review Document control administration SoW review Meeting with JL SIT procedure review (CC with Chevron) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-19 OH-006 :OH-006 Overhead All Activities Regular Pay N 3 0 HTSG Marketing Material sent to SC HTSG hours summary CC's with all direct reports CC with Supply Chain (Loadmaster Universal Rig) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-19 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 1 0 NCOC Workover Tender - CC's, peer review, support NCOC Rig 401 revamp Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-19 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 2 0 Sakhalin invoicing clarifications Rig 209L rig-move meetings, CC, research Orlan bell nipple lifting tool (review) CTR revision; discuss with Mio and Mark Todd Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-20 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 1 0 Technical specification review (clarifications back to bidders) Bidder clarification meetings Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-20 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 1.5 0 Cost estimate review Document control administration SoW review Meeting with JL SIT procedure review (CC with Chevron) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-20 OH-006 :OH-006 Overhead All Activities Regular Pay N 2.5 0 HTSG Marketing Material sent to SC HTSG hours summary CC's with all direct reports CC with Supply Chain (Loadmaster Universal Rig) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-20 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 4 0 NCOC Workover Tender - CC's, peer review, support NCOC Rig 401 revamp Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-21 Holly Platform :Holly Platform TSR-01665-HOLP-99 Project Management (OH) Regular Pay N 0.75 0 East side egress Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-21 OH-004 :OH-004 Overhead All Activities Regular Pay N 1.5 0 Weekly Operations CC Weekly TSR Meeting CC with Matt Svoboda (Genesis Eng) CC with Karma (barge operating depths) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-21 OH-006 :OH-006 Overhead All Activities Regular Pay N 2.5 0 HTSG Marketing Material sent to SC HTSG hours summary CC's with all direct reports CC with Supply Chain (Loadmaster Universal Rig) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-21 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 1 0 NCOC Workover Tender - CC's, peer review, support NCOC Rig 401 revamp Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-21 OH-019 :OH-019 Overhead All Activities Regular Pay N 0.75 0 Weekly CC Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-21 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 2 0 Sakhalin invoicing clarifications Rig 209L rig-move meetings, CC, research Orlan bell nipple lifting tool (review) CTR revision; discuss with Mio and Mark Todd Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-22 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 2 0 Cost estimate review Document control administration SoW review Meeting with JL SIT procedure review (CC with Chevron) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-22 Holly Platform :Holly Platform TSR-01665-HOLP-99 Project Management (OH) Regular Pay N 0.25 0 East side egress Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-22 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Weekly Operations CC Weekly TSR Meeting CC with Matt Svoboda (Genesis Eng) CC with Karma (barge operating depths) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-22 OH-006 :OH-006 Overhead All Activities Regular Pay N 1.5 0 HTSG Marketing Material sent to SC HTSG hours summary CC's with all direct reports CC with Supply Chain (Loadmaster Universal Rig) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-22 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1.5 0 Sakhalin invoicing clarifications Rig 209L rig-move meetings, CC, research Orlan bell nipple lifting tool (review) CTR revision; discuss with Mio and Mark Todd Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-25 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 (MON) timesheet administration Sakhalin invoicing TS hours summary Weekly CC's CC with Steve C. (x2) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-25 OH-008 :OH-008 Overhead All Activities Regular Pay N 8 0 Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-26 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 2 0 review WO redlines; CC to discuss WO SoW review / comments Meeting w/ LM top discuss drawings Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-26 Holly Platform :Holly Platform TSR-01665-HOLP-99 Project Management (OH) Regular Pay N 0.75 0 south side egress; preliminary design calcs; CTR development Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-26 OH-006 :OH-006 Overhead All Activities Regular Pay N 3 0 (MON) timesheet administration Sakhalin invoicing TS hours summary Weekly CC's CC with Steve C. (x2) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-26 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 0.5 0 NCOC WO Functional Specification review Send comments to MK Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-26 OH-019 :OH-019 Overhead All Activities Regular Pay N 0.5 0 CC's with Mio Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-26 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1 0 CC with ALE (Mammout) and Mio RE: 209L rig move Review Orlan mud repair tsr Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-26 OH-034 :OH-034 OH-034-005 Kazakhstan Regular Pay N 0.5 0 utility table review Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-26 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 0.75 0 MRS DOROTHY / MR SHELBY user fees; update action log; update status sheet Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-27 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 1 0 review WO redlines; CC to discuss WO SoW review / comments Meeting w/ LM top discuss drawings Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-27 Holly Platform :Holly Platform TSR-01665-HOLP-99 Project Management (OH) Regular Pay N 0.75 0 south side egress; preliminary design calcs; CTR development Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-27 OH-006 :OH-006 Overhead All Activities Regular Pay N 2 0 (MON) timesheet administration Sakhalin invoicing TS hours summary Weekly CC's CC with Steve C. (x2) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-27 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 2 0 NCOC WO Functional Specification review Send comments to MK Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-27 OH-013 :OH-013 Overhead All Activities Regular Pay N 0.5 0 Update TSR tracker spreadsheet Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-27 OH-019 :OH-019 Overhead All Activities Regular Pay N 0.5 0 CC's with Mio Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-27 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 0.75 0 CC with ALE (Mammout) and Mio RE: 209L rig move Review Orlan mud repair tsr Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-27 OH-034 :OH-034 OH-034-005 Kazakhstan Regular Pay N 0.5 0 utility table review Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-27 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 0.5 0 review design and TPP Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-28 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 1 0 internal meeting regarding NOV proposal meeting with NOV (FRI) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-28 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 0.75 0 review WO redlines; CC to discuss WO SoW review / comments Meeting w/ LM top discuss drawings Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-28 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 weekly Technical Services meeting Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-28 OH-006 :OH-006 Overhead All Activities Regular Pay N 2 0 (MON) timesheet administration Sakhalin invoicing TS hours summary Weekly CC's CC with Steve C. (x2) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-28 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 1.5 0 NCOC WO Functional Specification review Send comments to MK Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-28 OH-013 :OH-013 Overhead All Activities Regular Pay N 0.5 0 Update TSR tracker spreadsheet Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-28 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1.5 0 CC with ALE (Mammout) and Mio RE: 209L rig move Review Orlan mud repair tsr Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-28 OH-034 :OH-034 OH-034-006 Iraq Regular Pay N 0.5 0 REF 265L information sent to Jeff W. Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-28 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 0.5 0 review design and TPP Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-29 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 1 0 internal meeting regarding NOV proposal meeting with NOV (FRI) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-29 Holly Platform :Holly Platform TSR-01665-HOLP-99 Project Management (OH) Regular Pay N 1.25 0 south side egress; preliminary design calcs; CTR development Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-29 OH-006 :OH-006 Overhead All Activities Regular Pay N 2 0 (MON) timesheet administration Sakhalin invoicing TS hours summary Weekly CC's CC with Steve C. (x2) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-29 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 0.5 0 NCOC WO Functional Specification review Send comments to MK Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-29 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 0.75 0 CC with ALE (Mammout) and Mio RE: 209L rig move Review Orlan mud repair tsr Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2020-05-29 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 0.75 0 MRS DOROTHY / MR SHELBY user fees; update action log; update status sheet Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-04 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 3 0 05/04: compile updated PDF model of 3D drill floor with north wind wall removed for Robert 05/05: Fuze meeting with T&B to discuss findings on swarf cuttings bin load analysis Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-04 OH-005 :OH-005 Overhead All Activities Regular Pay N 1 0 05/04: time sheet to ProjXsense and payroll Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-04 OH-013 :OH-013 Overhead All Activities Regular Pay N 1.5 0 05/04: transmittal of TSR-01743-MDR and TSR-01677-CO 05/05: process incoming transmittals. 05/06: transmittal of TSR-01743-DBK; generate report of April accruals for Emanuel; transmit TSR-01743-DWG 05/07: transmit TSR-01743-DWG Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-04 OH-019 :OH-019 Overhead All Activities Regular Pay N 1 0 05/04: teleconference call with Sakhalin regarding 270 updates and Sakhalin TSRs Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-04 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1.5 0 05/04-07:begin drafting of insulation details and cladding of main ATC support structure. 05/08: model existing piping into compiled data model to check for clashes and piping modifications per TSR. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-05 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 1 0 05/04: compile updated PDF model of 3D drill floor with north wind wall removed for Robert 05/05: Fuze meeting with T&B to discuss findings on swarf cuttings bin load analysis Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-05 OH-006 :OH-006 Overhead All Activities Regular Pay N 2.25 0 05/05: look through emails and q: drive for Sakhalin title block Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-05 OH-013 :OH-013 Overhead All Activities Regular Pay N 1 0 05/04: transmittal of TSR-01743-MDR and TSR-01677-CO 05/05: process incoming transmittals. 05/06: transmittal of TSR-01743-DBK; generate report of April accruals for Emanuel; transmit TSR-01743-DWG 05/07: transmit TSR-01743-DWG Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-05 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 3.75 0 05/04-07:begin drafting of insulation details and cladding of main ATC support structure. 05/08: model existing piping into compiled data model to check for clashes and piping modifications per TSR. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-06 OH-013 :OH-013 Overhead All Activities Regular Pay N 2.5 0 05/04: transmittal of TSR-01743-MDR and TSR-01677-CO 05/05: process incoming transmittals. 05/06: transmittal of TSR-01743-DBK; generate report of April accruals for Emanuel; transmit TSR-01743-DWG 05/07: transmit TSR-01743-DWG Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-06 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 5.5 0 05/04-07:begin drafting of insulation details and cladding of main ATC support structure. 05/08: model existing piping into compiled data model to check for clashes and piping modifications per TSR. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-07 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 05/07: teleconference to discuss TSR updates and ongoing tasks 05/08: call with Kyle to discuss ATC redlines. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-07 OH-013 :OH-013 Overhead All Activities Regular Pay N 2 0 05/04: transmittal of TSR-01743-MDR and TSR-01677-CO 05/05: process incoming transmittals. 05/06: transmittal of TSR-01743-DBK; generate report of April accruals for Emanuel; transmit TSR-01743-DWG 05/07: transmit TSR-01743-DWG Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-07 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 3.5 0 05/04-07:begin drafting of insulation details and cladding of main ATC support structure. 05/08: model existing piping into compiled data model to check for clashes and piping modifications per TSR. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-07 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 1.5 0 05/07: discuss with Jorge and John regarding the updated views of the instrument arrangements Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-08 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 05/07: teleconference to discuss TSR updates and ongoing tasks 05/08: call with Kyle to discuss ATC redlines. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-08 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 7 0 05/04-07:begin drafting of insulation details and cladding of main ATC support structure. 05/08: model existing piping into compiled data model to check for clashes and piping modifications per TSR. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-11 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 05/11: online timesheets to ProjXsense 05/13: hightail 270L databook to Valery 05/15: find 3D pdf files and model files to upload to presentation folder (for Sandy). Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-11 OH-013 :OH-013 Overhead All Activities Regular Pay N 1 0 05/11: transmit TSR-01743-MDR 05/12: process incoming TSR transmittals; transmit TSR-01727-CTR-R2 05/15: transmit TSR-01752-CO Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-11 OH-019 :OH-019 Overhead All Activities Regular Pay N 0.5 0 05/10&05/11: teleconference call with Sakhalin regarding 270 updates and Sakhalin TSRs Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-11 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 5.5 0 05/11-05/14: model piping and outfitting items to check for clashes and design solutions to fit TSR requirements. 05/13: send Mio preliminary drawing set for comments; 05/14: begin transferring PKD drawing to RUSA title block. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-12 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 1 0 05/12: update Nabors drawing to reflect comments from Joshua and team. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-12 OH-013 :OH-013 Overhead All Activities Regular Pay N 1.25 0 05/11: transmit TSR-01743-MDR 05/12: process incoming TSR transmittals; transmit TSR-01727-CTR-R2 05/15: transmit TSR-01752-CO Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-12 OH-019 :OH-019 Overhead All Activities Regular Pay N 0.5 0 05/10&05/11: teleconference call with Sakhalin regarding 270 updates and Sakhalin TSRs Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-12 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 5.25 0 05/11-05/14: model piping and outfitting items to check for clashes and design solutions to fit TSR requirements. 05/13: send Mio preliminary drawing set for comments; 05/14: begin transferring PKD drawing to RUSA title block. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-13 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 1.25 0 05/12: update Nabors drawing to reflect comments from Joshua and team. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-13 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 05/13: conference call with James and Kyle to discuss RUSA title block standards 05/14: teleconference to discuss TSR updates and ongoing tasks Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-13 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.5 0 05/11: online timesheets to ProjXsense 05/13: hightail 270L databook to Valery 05/15: find 3D pdf files and model files to upload to presentation folder (for Sandy). Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-13 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 5.25 0 05/11-05/14: model piping and outfitting items to check for clashes and design solutions to fit TSR requirements. 05/13: send Mio preliminary drawing set for comments; 05/14: begin transferring PKD drawing to RUSA title block. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-14 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 05/13: conference call with James and Kyle to discuss RUSA title block standards 05/14: teleconference to discuss TSR updates and ongoing tasks Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-14 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 7 0 05/11-05/14: model piping and outfitting items to check for clashes and design solutions to fit TSR requirements. 05/13: send Mio preliminary drawing set for comments; 05/14: begin transferring PKD drawing to RUSA title block. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-15 OH-006 :OH-006 Overhead All Activities Regular Pay N 3 0 05/11: online timesheets to ProjXsense 05/13: hightail 270L databook to Valery 05/15: find 3D pdf files and model files to upload to presentation folder (for Sandy). Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-15 OH-013 :OH-013 Overhead All Activities Regular Pay N 1 0 05/11: transmit TSR-01743-MDR 05/12: process incoming TSR transmittals; transmit TSR-01727-CTR-R2 05/15: transmit TSR-01752-CO Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-15 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 4 0 05/11-05/14: model piping and outfitting items to check for clashes and design solutions to fit TSR requirements. 05/13: send Mio preliminary drawing set for comments; 05/14: begin transferring PKD drawing to RUSA title block. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-18 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 05/18: timesheets to ProjXsense and payroll. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-18 OH-013 :OH-013 Overhead All Activities Regular Pay N 2 0 05/18: process incoming transmittals; transmit TSR-01743-CO 05/19: transmit Genesis LM dwgs. 05/20: transmit Genesis LM dwgs and technical documents 05/21: transmit TSR-01743-DWG; TSR-01767-CTR; Genesis LM dwgs Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-18 OH-019 :OH-019 Overhead All Activities Regular Pay N 2 0 05/18: teleconference call with Sakhalin regarding 270 updates and Sakhalin TSRs; separate meeting with Mio and James regarding the overall installation of components for the ATC. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-18 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 3 0 05/19-05/22: piping modifications to clear potential interference of ATC egress; model piping of LP mud drains and TW connections Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-19 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 6 0 05/19: generate standpipe as-built PDF from photo, and label valves per email comments. 05/21: locate KBC backup HPU unit for plan view drawing Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-19 OH-013 :OH-013 Overhead All Activities Regular Pay N 2 0 05/18: process incoming transmittals; transmit TSR-01743-CO 05/19: transmit Genesis LM dwgs. 05/20: transmit Genesis LM dwgs and technical documents 05/21: transmit TSR-01743-DWG; TSR-01767-CTR; Genesis LM dwgs Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-20 OH-013 :OH-013 Overhead All Activities Regular Pay N 2 0 05/18: process incoming transmittals; transmit TSR-01743-CO 05/19: transmit Genesis LM dwgs. 05/20: transmit Genesis LM dwgs and technical documents 05/21: transmit TSR-01743-DWG; TSR-01767-CTR; Genesis LM dwgs Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-20 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 6 0 05/19-05/22: piping modifications to clear potential interference of ATC egress; model piping of LP mud drains and TW connections Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-21 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 2 0 05/19: generate standpipe as-built PDF from photo, and label valves per email comments. 05/21: locate KBC backup HPU unit for plan view drawing Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-21 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 05/21: teleconference to discuss TSR updates and ongoing tasks; IDR quarterly meeting. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-21 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 5 0 05/19-05/22: piping modifications to clear potential interference of ATC egress; model piping of LP mud drains and TW connections Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-22 OH-013 :OH-013 Overhead All Activities Regular Pay N 4 0 05/18: process incoming transmittals; transmit TSR-01743-CO 05/19: transmit Genesis LM dwgs. 05/20: transmit Genesis LM dwgs and technical documents 05/21: transmit TSR-01743-DWG; TSR-01767-CTR; Genesis LM dwgs Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-22 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 4 0 05/19-05/22: piping modifications to clear potential interference of ATC egress; model piping of LP mud drains and TW connections Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-25 OH-008 :OH-008 Overhead All Activities Regular Pay N 8 0 Memorial Day Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-26 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 05/26: update concept for south KBC egress, meeting with Kyle/James to discuss for analysis. 05/28: update concept per site/engineering comments. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-26 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 05/25: timesheets to ProjXsense. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-26 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 3 0 05/26-29: piping modifications to existing piping and new piping spools per TSR. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-27 OH-013 :OH-013 Overhead All Activities Regular Pay N 1 0 05/27: transmit TSR-01767-CTR 05/28: process incoming transmittal and drawing number request. 05/29: process incoming drawing request; transmit 249L drawing Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-27 OH-014 :OH-014 Overhead All Activities Regular Pay N 1 0 IDR quarterly training; create report for Emanuel for April accruals Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-27 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 6 0 05/26-29: piping modifications to existing piping and new piping spools per TSR. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-28 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 05/26: update concept for south KBC egress, meeting with Kyle/James to discuss for analysis. 05/28: update concept per site/engineering comments. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-28 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 05/28: teleconference to discuss TSR updates and ongoing tasks; Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-28 OH-013 :OH-013 Overhead All Activities Regular Pay N 1 0 05/27: transmit TSR-01767-CTR 05/28: process incoming transmittal and drawing number request. 05/29: process incoming drawing request; transmit 249L drawing Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-28 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 2 0 05/26-29: piping modifications to existing piping and new piping spools per TSR. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-29 OH-013 :OH-013 Overhead All Activities Regular Pay N 1.5 0 05/27: transmit TSR-01767-CTR 05/28: process incoming transmittal and drawing number request. 05/29: process incoming drawing request; transmit 249L drawing Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2020-05-29 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 6.5 0 05/26-29: piping modifications to existing piping and new piping spools per TSR. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-04 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 7 0 On 5/4-5/8, support COP Willow rig builder RFQ's. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-04 OH-004 :OH-004 Overhead All Activities Regular Pay N 2 0 On 5/4, weekly Ops mtg. On 5/7, weekly TS mtg. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-05 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 5 0 On 5/4-5/8, support COP Willow rig builder RFQ's. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-05 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 4 0 On 5/4-5/7, support Jaguar Rig 212 and 210 scope of work. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-06 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 5 0 On 5/4-5/8, support COP Willow rig builder RFQ's. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-06 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 4 0 On 5/4-5/7, support Jaguar Rig 212 and 210 scope of work. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-07 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 2 0 On 5/4-5/7, support Jaguar Rig 212 and 210 scope of work. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-07 OH-004 :OH-004 Overhead All Activities Regular Pay N 2 0 On 5/4, weekly Ops mtg. On 5/7, weekly TS mtg. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-07 OH-006 :OH-006 Overhead All Activities Regular Pay N 2 0 On 5/7, forecast update. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-07 OH-009 :OH-009 OH-009-016 Eastern Canada Regular Pay N 2 0 On 5/7, Husky WWRP update with Area Supt. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-07 OH-009 :OH-009 OH-009-023 Gulf of Mexico Regular Pay N 2 0 On 5/4-5/8, support GOM P&A opportunity. On 5/7, CVX Genesis Risk Register. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-08 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 3 0 On 5/4-5/8, support COP Willow rig builder RFQ's. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-08 OH-009 :OH-009 OH-009-023 Gulf of Mexico Regular Pay N 4 0 On 5/4-5/8, support GOM P&A opportunity. On 5/7, CVX Genesis Risk Register. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-11 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 5 0 On 5/11-5/14, support COP Willow RFQs for rig builders. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-11 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 2 0 On 5/11-5/14, support Jaguar Rig 212 closeout. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-11 OH-009 :OH-009 OH-009-023 Gulf of Mexico Regular Pay N 2 0 On 5/11-5/15, support P&A market entry. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-12 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 3 0 On 5/11-5/14, support COP Willow RFQs for rig builders. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-12 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 2 0 On 5/11-5/14, support Jaguar Rig 212 closeout. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-12 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 2 0 On 5/12 and 5/13, support NCOC newbuild workover tender. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-12 OH-009 :OH-009 OH-009-023 Gulf of Mexico Regular Pay N 2 0 On 5/11-5/15, support P&A market entry. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-13 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 4 0 On 5/11-5/14, support COP Willow RFQs for rig builders. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-13 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 1 0 On 5/11-5/14, support Jaguar Rig 212 closeout. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-13 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 2 0 On 5/12 and 5/13, support NCOC newbuild workover tender. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-13 OH-009 :OH-009 OH-009-023 Gulf of Mexico Regular Pay N 2 0 On 5/11-5/15, support P&A market entry. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-14 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 6 0 On 5/11-5/14, support COP Willow RFQs for rig builders. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-14 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 1 0 On 5/11-5/14, support Jaguar Rig 212 closeout. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-14 OH-009 :OH-009 OH-009-023 Gulf of Mexico Regular Pay N 2 0 On 5/11-5/15, support P&A market entry. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-15 OH-009 :OH-009 OH-009-023 Gulf of Mexico Regular Pay N 6 0 On 5/11-5/15, support P&A market entry. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-18 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 5 0 On 5/18-5/20, support COP Willow RFQ 's for rig builders. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-18 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 1 0 On 5/18, support Rig 212 closeout and action tracker. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-18 OH-009 :OH-009 OH-009-023 Gulf of Mexico Regular Pay N 3 0 On 5/18-5/20, P&A market entry mtgs, market research and powerpoint. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-19 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 4 0 On 5/18-5/20, support COP Willow RFQ 's for rig builders. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-19 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 1 0 On 5/18, support Rig 212 closeout and action tracker. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-19 OH-009 :OH-009 OH-009-023 Gulf of Mexico Regular Pay N 4 0 On 5/18-5/20, P&A market entry mtgs, market research and powerpoint. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-20 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 4 0 On 5/18-5/20, support COP Willow RFQ 's for rig builders. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-20 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 1 0 On 5/18, support Rig 212 closeout and action tracker. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-20 OH-009 :OH-009 OH-009-023 Gulf of Mexico Regular Pay N 4 0 On 5/18-5/20, P&A market entry mtgs, market research and powerpoint. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-21 OH-001 :OH-001 Overhead All Activities Regular Pay N 8 0 On 5/21 & 5/22, PTO. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-22 OH-001 :OH-001 Overhead All Activities Regular Pay N 8 0 On 5/21 & 5/22, PTO. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-25 OH-008 :OH-008 Overhead All Activities Regular Pay N 8 0 On 5/25, Memorial Day Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-26 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 1 0 On 5/26-5/29, support COP Willow RFQs. Conf call with NOV and Drillmec. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-26 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 2 0 On 5/25-5/29, Jaguar updates, closeout. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-26 OH-009 :OH-009 OH-009-023 Gulf of Mexico Regular Pay N 6 0 On 5/24-5/29, support P&A market entry analysis. Meet with P&A team to evaluate P&A equipment. Support CVX work order review. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-27 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 3 0 On 5/25-5/29, Jaguar updates, closeout. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-27 OH-009 :OH-009 OH-009-023 Gulf of Mexico Regular Pay N 6 0 On 5/24-5/29, support P&A market entry analysis. Meet with P&A team to evaluate P&A equipment. Support CVX work order review. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-28 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 3 0 On 5/26-5/29, support COP Willow RFQs. Conf call with NOV and Drillmec. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-28 OH-009 :OH-009 OH-009-023 Gulf of Mexico Regular Pay N 6 0 On 5/24-5/29, support P&A market entry analysis. Meet with P&A team to evaluate P&A equipment. Support CVX work order review. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-29 ARBU-TSRs :ARBU-TSRs TSR-01766-P01419 COPA Willow Proposal Regular Pay N 3 0 On 5/26-5/29, support COP Willow RFQs. Conf call with NOV and Drillmec. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-29 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 1 0 On 5/25-5/29, Jaguar updates, closeout. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2020-05-29 OH-009 :OH-009 OH-009-023 Gulf of Mexico Regular Pay N 4 0 On 5/24-5/29, support P&A market entry analysis. Meet with P&A team to evaluate P&A equipment. Support CVX work order review. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-04 HTSG-TSR :HTSG-TSR HTSG-2020 SMART-Developmental Goals Regular Pay N 1 0 Clean Design Meeting to give update . Send 272/273 Project oneline to Clean Design. Create Action item list. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-04 OH-019 :OH-019 Overhead All Activities Regular Pay N 2 0 270 and SAK ENG Weekly meeting Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-04 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 4 0 262 Fire and Gas drawing review done. Sent email back with comments. 209 Close out report done and send to Kyle for review. Send 209 lighting panel drawing to SAK ENG as per request Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-04 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 1 0 General GENESIS Spar support. Talk to Rexel to add Lights to Pony Sub and Super Structure. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-05 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 6 0 262 Fire and Gas drawing review done. Sent email back with comments. 209 Close out report done and send to Kyle for review. Send 209 lighting panel drawing to SAK ENG as per request Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-05 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 2 0 General GENESIS Spar support. Talk to Rexel to add Lights to Pony Sub and Super Structure. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-06 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 7 0 262 Fire and Gas drawing review done. Sent email back with comments. 209 Close out report done and send to Kyle for review. Send 209 lighting panel drawing to SAK ENG as per request Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-06 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 1 0 General GENESIS Spar support. Talk to Rexel to add Lights to Pony Sub and Super Structure. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-07 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 1 0 Adding Sub Structure Lighting Load to Oneline Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-07 HTSG-TSR :HTSG-TSR HTSG-2020 SMART-Developmental Goals Regular Pay N 2 0 Clean Design Meeting to give update . Send 272/273 Project oneline to Clean Design. Create Action item list. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-07 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 TS Weekly meeting Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-07 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 3 0 262 Fire and Gas drawing review done. Sent email back with comments. 209 Close out report done and send to Kyle for review. Send 209 lighting panel drawing to SAK ENG as per request Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-07 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 1 0 General GENESIS Spar support. Talk to Rexel to add Lights to Pony Sub and Super Structure. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-08 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 1 0 Adding Sub Structure Lighting Load to Oneline Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-08 HTSG-TSR :HTSG-TSR HTSG-2020 SMART-Developmental Goals Regular Pay N 2 0 Clean Design Meeting to give update . Send 272/273 Project oneline to Clean Design. Create Action item list. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-08 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 4 0 262 Fire and Gas drawing review done. Sent email back with comments. 209 Close out report done and send to Kyle for review. Send 209 lighting panel drawing to SAK ENG as per request Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-08 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 1 0 General GENESIS Spar support. Talk to Rexel to add Lights to Pony Sub and Super Structure. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-11 HTSG-TSR :HTSG-TSR HTSG-2020 SMART-Developmental Goals Regular Pay N 4 0 Meeting with Tyler to come up with fuel usages for Rig 272/273. Explain power requirement from Clean Design to Tyler to get Rig Power Data Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-11 OH-019 :OH-019 Overhead All Activities Regular Pay N 1 0 SAK Weekly meeting. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-11 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1 0 review 209 close out report and send to kyle to transmit to SAK. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-11 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 2 0 Genesis Spar project weekly Call Cable requirement for grasshopper and drag chain . review LED light data sheet provided by Gulf Coast. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-12 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 1 0 Working on System oneline . Working with Gulf Coast for LED lights for super structure. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-12 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1 0 review 209 close out report and send to kyle to transmit to SAK. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-12 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 6 0 Genesis Spar project weekly Call Cable requirement for grasshopper and drag chain . review LED light data sheet provided by Gulf Coast. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-13 HTSG-TSR :HTSG-TSR HTSG-2020 SMART-Developmental Goals Regular Pay N 4 0 Meeting with Tyler to come up with fuel usages for Rig 272/273. Explain power requirement from Clean Design to Tyler to get Rig Power Data Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-13 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 4 0 Genesis Spar project weekly Call Cable requirement for grasshopper and drag chain . review LED light data sheet provided by Gulf Coast. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-14 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 2 0 Working on System oneline . Working with Gulf Coast for LED lights for super structure. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-14 HTSG-TSR :HTSG-TSR HTSG-2020 SMART-Developmental Goals Regular Pay N 2 0 Meeting with Tyler to come up with fuel usages for Rig 272/273. Explain power requirement from Clean Design to Tyler to get Rig Power Data Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-14 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 TS Weekly Meeting Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-14 OH-019 :OH-019 Overhead All Activities Regular Pay N 1 0 SAK Weekly meeting. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-14 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1 0 review 209 close out report and send to kyle to transmit to SAK. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-14 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 1 0 Genesis Spar project weekly Call Cable requirement for grasshopper and drag chain . review LED light data sheet provided by Gulf Coast. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-15 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 2 0 Working on System oneline . Working with Gulf Coast for LED lights for super structure. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-15 HTSG-TSR :HTSG-TSR HTSG-2020 SMART-Developmental Goals Regular Pay N 4 0 Meeting with Tyler to come up with fuel usages for Rig 272/273. Explain power requirement from Clean Design to Tyler to get Rig Power Data Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-15 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 2 0 Genesis Spar project weekly Call Cable requirement for grasshopper and drag chain . review LED light data sheet provided by Gulf Coast. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-18 HTSG-TSR :HTSG-TSR HTSG-2020 SMART-Developmental Goals Regular Pay N 4 0 GEN Data Provided to Clean Design . Set up Conference call to discuss data provided. Fuel Cost provided Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-18 OH-019 :OH-019 Overhead All Activities Regular Pay N 1 0 Weekly SAK Meeting Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-18 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 3 0 Super Structure dimension provided to Gulf Coast for light study. Finish Oneline to show new transformer and lighting panel for super structure waiting for light study report from Gulf Coast Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-19 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 2 0 New 75KVA Transformer and lighting panel data sheet request to ACS. Conference call set up to finalize old and new Quote Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-19 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 6 0 Super Structure dimension provided to Gulf Coast for light study. Finish Oneline to show new transformer and lighting panel for super structure waiting for light study report from Gulf Coast Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-20 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 1 0 New 75KVA Transformer and lighting panel data sheet request to ACS. Conference call set up to finalize old and new Quote Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-20 HTSG-TSR :HTSG-TSR HTSG-2020 SMART-Developmental Goals Regular Pay N 4 0 GEN Data Provided to Clean Design . Set up Conference call to discuss data provided. Fuel Cost provided Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-20 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 3 0 Super Structure dimension provided to Gulf Coast for light study. Finish Oneline to show new transformer and lighting panel for super structure waiting for light study report from Gulf Coast Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-21 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 1 0 New 75KVA Transformer and lighting panel data sheet request to ACS. Conference call set up to finalize old and new Quote Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-21 HTSG-TSR :HTSG-TSR HTSG-2020 SMART-Developmental Goals Regular Pay N 3 0 GEN Data Provided to Clean Design . Set up Conference call to discuss data provided. Fuel Cost provided Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-21 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Weekly TSR Meeting Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-21 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 3 0 Super Structure dimension provided to Gulf Coast for light study. Finish Oneline to show new transformer and lighting panel for super structure waiting for light study report from Gulf Coast Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-22 HTSG-TSR :HTSG-TSR HTSG-2020 SMART-Developmental Goals Regular Pay N 3 0 GEN Data Provided to Clean Design . Set up Conference call to discuss data provided. Fuel Cost provided Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-22 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 5 0 Super Structure dimension provided to Gulf Coast for light study. Finish Oneline to show new transformer and lighting panel for super structure waiting for light study report from Gulf Coast Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-25 OH-008 :OH-008 Overhead All Activities Regular Pay N 8 0 Holiday Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-26 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 3 0 Review Gulf Coast Super Structure LED light study report. Reviewing Transformer and Lighting panel data sheet sent by ACS . Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-26 HTSG-TSR :HTSG-TSR HTSG-2020 SMART-Developmental Goals Regular Pay N 4 0 GEN Data provided by Rig 272. Review Data and sent to Clean Design. Waiting for feedback from Clean Design. Additional info requested by Clean Design to provide Hi-Line cost. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-26 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 1 0 Genesis Weekly meeting. Conference call with ACS. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-27 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 5 0 Review Gulf Coast Super Structure LED light study report. Reviewing Transformer and Lighting panel data sheet sent by ACS . Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-27 HTSG-TSR :HTSG-TSR HTSG-2020 SMART-Developmental Goals Regular Pay N 2 0 GEN Data provided by Rig 272. Review Data and sent to Clean Design. Waiting for feedback from Clean Design. Additional info requested by Clean Design to provide Hi-Line cost. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-27 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 1 0 Genesis Weekly meeting. Conference call with ACS. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-28 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 2 0 Review Gulf Coast Super Structure LED light study report. Reviewing Transformer and Lighting panel data sheet sent by ACS . Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-28 HTSG-TSR :HTSG-TSR HTSG-2020 SMART-Developmental Goals Regular Pay N 4 0 GEN Data provided by Rig 272. Review Data and sent to Clean Design. Waiting for feedback from Clean Design. Additional info requested by Clean Design to provide Hi-Line cost. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-28 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 TS Weekly meeting Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-28 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 1 0 Genesis Weekly meeting. Conference call with ACS. Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-29 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 4 0 Review Gulf Coast Super Structure LED light study report. Reviewing Transformer and Lighting panel data sheet sent by ACS . Patel, Ripal Engineer II Patel, Ripal:Engineer II 2020-05-29 HTSG-TSR :HTSG-TSR HTSG-2020 SMART-Developmental Goals Regular Pay N 4 0 GEN Data provided by Rig 272. Review Data and sent to Clean Design. Waiting for feedback from Clean Design. Additional info requested by Clean Design to provide Hi-Line cost. Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-04 OH-005 :OH-005 Overhead All Activities Regular Pay N 2.5 0 Call from J.G. (Status/Progress review) 5/4/20 I.T. for Fuze request & inst. 5/4-5/20 Call from J.G. (Status/Progress review) 5/7/20 Emails Timesheet Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-04 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 6 0 ORLP-01-03-xxx-1-R0 5/4/20 ORLP-01-03-xxx-2-R0-5/5-7/20 ORLP-01-03-xxx-3-R0-5/7-8/20 Review comments w/ J.R. 5/7/20 Request 3D support from L.N. 5/7-8/20 Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-05 OH-005 :OH-005 Overhead All Activities Regular Pay N 2.5 0 Call from J.G. (Status/Progress review) 5/4/20 I.T. for Fuze request & inst. 5/4-5/20 Call from J.G. (Status/Progress review) 5/7/20 Emails Timesheet Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-05 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 6 0 ORLP-01-03-xxx-1-R0 5/4/20 ORLP-01-03-xxx-2-R0-5/5-7/20 ORLP-01-03-xxx-3-R0-5/7-8/20 Review comments w/ J.R. 5/7/20 Request 3D support from L.N. 5/7-8/20 Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-06 OH-005 :OH-005 Overhead All Activities Regular Pay N 2 0 Call from J.G. (Status/Progress review) 5/4/20 I.T. for Fuze request & inst. 5/4-5/20 Call from J.G. (Status/Progress review) 5/7/20 Emails Timesheet Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-06 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 6.5 0 ORLP-01-03-xxx-1-R0 5/4/20 ORLP-01-03-xxx-2-R0-5/5-7/20 ORLP-01-03-xxx-3-R0-5/7-8/20 Review comments w/ J.R. 5/7/20 Request 3D support from L.N. 5/7-8/20 Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-07 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Weekly meeting 5/7/20 Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-07 OH-005 :OH-005 Overhead All Activities Regular Pay N 2 0 Call from J.G. (Status/Progress review) 5/4/20 I.T. for Fuze request & inst. 5/4-5/20 Call from J.G. (Status/Progress review) 5/7/20 Emails Timesheet Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-07 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 5.5 0 ORLP-01-03-xxx-1-R0 5/4/20 ORLP-01-03-xxx-2-R0-5/5-7/20 ORLP-01-03-xxx-3-R0-5/7-8/20 Review comments w/ J.R. 5/7/20 Request 3D support from L.N. 5/7-8/20 Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-08 OH-005 :OH-005 Overhead All Activities Regular Pay N 1 0 Call from J.G. (Status/Progress review) 5/4/20 I.T. for Fuze request & inst. 5/4-5/20 Call from J.G. (Status/Progress review) 5/7/20 Emails Timesheet Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-08 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 5 0 ORLP-01-03-xxx-1-R0 5/4/20 ORLP-01-03-xxx-2-R0-5/5-7/20 ORLP-01-03-xxx-3-R0-5/7-8/20 Review comments w/ J.R. 5/7/20 Request 3D support from L.N. 5/7-8/20 Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-11 OH-005 :OH-005 Overhead All Activities Regular Pay N 1.5 0 Timesheet Emails Review work w/ J.G. (5/11/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-11 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 2 0 TSR-01759 ORLP-01-03-011-(1-3) Comments (5/11/20) Review w/ J.R.(5/11/20) Additional comments per J.R. (5/15/20) TSR-01767 Layout for Bell nipple modifications sketch. 5/13-15/20 Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-11 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 1.5 0 Review TSR-01767 (drawings, PDF's, docs.) (5/11-12) Compare drawing dimensions to PDF inspection dimensions and model drawings. Review Lift tool drawings and Pics w/ T.E.(5/12/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-11 Rig 273L-TSR :Rig 273L-TSR TSR-01757-AADU Surface 21-1/4in. Annualar Lift Ring Modifications Regular Pay N 3.5 0 273L-01-03-xxx- (1-3) R0 Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-12 OH-005 :OH-005 Overhead All Activities Regular Pay N 0.75 0 Timesheet Emails Review work w/ J.G. (5/11/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-12 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 1.5 0 Review TSR-01767 (drawings, PDF's, docs.) (5/11-12) Compare drawing dimensions to PDF inspection dimensions and model drawings. Review Lift tool drawings and Pics w/ T.E.(5/12/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-12 Rig 273L-TSR :Rig 273L-TSR TSR-01757-AADU Surface 21-1/4in. Annualar Lift Ring Modifications Regular Pay N 6.25 0 273L-01-03-xxx- (1-3) R0 Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-13 OH-005 :OH-005 Overhead All Activities Regular Pay N 0.75 0 Timesheet Emails Review work w/ J.G. (5/11/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-13 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 6.75 0 TSR-01759 ORLP-01-03-011-(1-3) Comments (5/11/20) Review w/ J.R.(5/11/20) Additional comments per J.R. (5/15/20) TSR-01767 Layout for Bell nipple modifications sketch. 5/13-15/20 Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-13 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 1 0 Review TSR-01767 (drawings, PDF's, docs.) (5/11-12) Compare drawing dimensions to PDF inspection dimensions and model drawings. Review Lift tool drawings and Pics w/ T.E.(5/12/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-14 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Weekly meeting w/ FUZE (5/14/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-14 OH-005 :OH-005 Overhead All Activities Regular Pay N 0.75 0 Timesheet Emails Review work w/ J.G. (5/11/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-14 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 5.75 0 TSR-01759 ORLP-01-03-011-(1-3) Comments (5/11/20) Review w/ J.R.(5/11/20) Additional comments per J.R. (5/15/20) TSR-01767 Layout for Bell nipple modifications sketch. 5/13-15/20 Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-14 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 1 0 Review TSR-01767 (drawings, PDF's, docs.) (5/11-12) Compare drawing dimensions to PDF inspection dimensions and model drawings. Review Lift tool drawings and Pics w/ T.E.(5/12/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-15 OH-005 :OH-005 Overhead All Activities Regular Pay N 0.5 0 Timesheet Emails Review work w/ J.G. (5/11/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-15 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 4.5 0 TSR-01759 ORLP-01-03-011-(1-3) Comments (5/11/20) Review w/ J.R.(5/11/20) Additional comments per J.R. (5/15/20) TSR-01767 Layout for Bell nipple modifications sketch. 5/13-15/20 Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-15 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 1 0 Review TSR-01767 (drawings, PDF's, docs.) (5/11-12) Compare drawing dimensions to PDF inspection dimensions and model drawings. Review Lift tool drawings and Pics w/ T.E.(5/12/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-18 OH-005 :OH-005 Overhead All Activities Regular Pay N 1 0 Emails Back to work Questioniore/call Timesheet Call J.G. Update status/progress (5/18-21/20) Solidworks (research/training for modeling to 2d views + convert CAD files/dwgs. (5/20-21/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-18 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 2.5 0 TSR-01759 ORLP-01-03-011-(1-3) Comments per emails (5/18-20/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-18 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 5 0 Layout for Bell nipple modifications & Lift tool sketch. (5/18-19/20) FUZE meeting w/ Mio (info for building,assembling, and standards (5/18/20) Update Hooks & lift tool per T.E. changes to his model (5/20-22/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-19 OH-005 :OH-005 Overhead All Activities Regular Pay N 1.5 0 Emails Back to work Questioniore/call Timesheet Call J.G. Update status/progress (5/18-21/20) Solidworks (research/training for modeling to 2d views + convert CAD files/dwgs. (5/20-21/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-19 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 0.5 0 TSR-01759 ORLP-01-03-011-(1-3) Comments per emails (5/18-20/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-19 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 6.5 0 Layout for Bell nipple modifications & Lift tool sketch. (5/18-19/20) FUZE meeting w/ Mio (info for building,assembling, and standards (5/18/20) Update Hooks & lift tool per T.E. changes to his model (5/20-22/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-20 OH-005 :OH-005 Overhead All Activities Regular Pay N 6 0 Emails Back to work Questioniore/call Timesheet Call J.G. Update status/progress (5/18-21/20) Solidworks (research/training for modeling to 2d views + convert CAD files/dwgs. (5/20-21/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-20 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 0.5 0 TSR-01759 ORLP-01-03-011-(1-3) Comments per emails (5/18-20/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-20 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 2 0 Layout for Bell nipple modifications & Lift tool sketch. (5/18-19/20) FUZE meeting w/ Mio (info for building,assembling, and standards (5/18/20) Update Hooks & lift tool per T.E. changes to his model (5/20-22/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-21 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Weekly meeting (FUZE) (5/21/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-21 OH-005 :OH-005 Overhead All Activities Regular Pay N 6 0 Emails Back to work Questioniore/call Timesheet Call J.G. Update status/progress (5/18-21/20) Solidworks (research/training for modeling to 2d views + convert CAD files/dwgs. (5/20-21/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-21 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 1.5 0 Layout for Bell nipple modifications & Lift tool sketch. (5/18-19/20) FUZE meeting w/ Mio (info for building,assembling, and standards (5/18/20) Update Hooks & lift tool per T.E. changes to his model (5/20-22/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-22 OH-005 :OH-005 Overhead All Activities Regular Pay N 1 0 Emails Back to work Questioniore/call Timesheet Call J.G. Update status/progress (5/18-21/20) Solidworks (research/training for modeling to 2d views + convert CAD files/dwgs. (5/20-21/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-22 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 5 0 Layout for Bell nipple modifications & Lift tool sketch. (5/18-19/20) FUZE meeting w/ Mio (info for building,assembling, and standards (5/18/20) Update Hooks & lift tool per T.E. changes to his model (5/20-22/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-25 OH-008 :OH-008 Overhead All Activities Regular Pay N 8 0 Memorial Day Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-26 OH-005 :OH-005 Overhead All Activities Regular Pay N 1.5 0 Emails Timesheet Call J.G. RUSA dwg (Units & metric settings review) (5/26/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-26 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1 0 TSR-01759 Casing jetting tool comment updates (5/26/20) TSR-01759 Review comments per emails (5/26-27/20; w/J.R. 5/29/20) ORLP-01-03-011-(1-4)-R0-Update per comments & add sht.;final details pending (5/29/20). Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-26 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 6 0 TSR-01767 Bell nipple dwg (RUSA number pending) (5/26/20) Send to T.E. (5/27/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-27 OH-005 :OH-005 Overhead All Activities Regular Pay N 1.5 0 Emails Timesheet Call J.G. RUSA dwg (Units & metric settings review) (5/26/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-27 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 2 0 TSR-01759 Casing jetting tool comment updates (5/26/20) TSR-01759 Review comments per emails (5/26-27/20; w/J.R. 5/29/20) ORLP-01-03-011-(1-4)-R0-Update per comments & add sht.;final details pending (5/29/20). Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-27 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 5 0 TSR-01767 Bell nipple dwg (RUSA number pending) (5/26/20) Send to T.E. (5/27/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-28 OH-001 :OH-001 Overhead All Activities Regular Pay N 6 0 Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-28 OH-005 :OH-005 Overhead All Activities Regular Pay N 1 0 Emails Timesheet Call J.G. RUSA dwg (Units & metric settings review) (5/26/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-28 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1 0 TSR-01759 Casing jetting tool comment updates (5/26/20) TSR-01759 Review comments per emails (5/26-27/20; w/J.R. 5/29/20) ORLP-01-03-011-(1-4)-R0-Update per comments & add sht.;final details pending (5/29/20). Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-29 OH-005 :OH-005 Overhead All Activities Regular Pay N 1 0 Emails Timesheet Call J.G. RUSA dwg (Units & metric settings review) (5/26/20) Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-29 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 5 0 TSR-01759 Casing jetting tool comment updates (5/26/20) TSR-01759 Review comments per emails (5/26-27/20; w/J.R. 5/29/20) ORLP-01-03-011-(1-4)-R0-Update per comments & add sht.;final details pending (5/29/20). Perez, Jorge Senior Designer 29841 Perez, Jorge:Senior Designer 2020-05-29 ORLAN-TSR :ORLAN-TSR TSR-01767-ORLP Bell Nipple Lifting Tool Regular Pay N 1 0 TSR-01767 Bell nipple dwg (RUSA number pending) (5/26/20) Send to T.E. (5/27/20) Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-04 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 2 0 C32 exhaust requirements, grasshopper utility gap analysis and cost revision, piping material spec clarifications, BOD load table comparison, cost estimate assistance, status report meetings, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-04 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 2 0 Drawworks torque performance testing Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-04 OH-019 :OH-019 Overhead All Activities Regular Pay N 1 0 Weekly meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-04 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 2 0 choke line MTO research, assistance with kepple fabrication records Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-04 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 1.5 0 Concept development and meeting, drawing review, documentation requirements Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-05 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 6.5 0 C32 exhaust requirements, grasshopper utility gap analysis and cost revision, piping material spec clarifications, BOD load table comparison, cost estimate assistance, status report meetings, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-05 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 2 0 Holly north analysis, swarf removal analysis Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-06 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 7.5 0 C32 exhaust requirements, grasshopper utility gap analysis and cost revision, piping material spec clarifications, BOD load table comparison, cost estimate assistance, status report meetings, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-06 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 1 0 Concept development and meeting, drawing review, documentation requirements Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-07 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 5.5 0 C32 exhaust requirements, grasshopper utility gap analysis and cost revision, piping material spec clarifications, BOD load table comparison, cost estimate assistance, status report meetings, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-07 Latin America Region-TSR :Latin America Region-TSR TSR-01753-LABU Jaguar Exploration - Mexico Regular Pay N 2 0 Drawworks torque performance testing Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-07 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 TS meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-08 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 1.5 0 C32 exhaust requirements, grasshopper utility gap analysis and cost revision, piping material spec clarifications, BOD load table comparison, cost estimate assistance, status report meetings, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-08 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 2 0 choke line MTO research, assistance with kepple fabrication records Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-08 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 2.5 0 Concept development and meeting, drawing review, documentation requirements Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-11 CVX Genesis :CVX Genesis TSR-1725-GENP-01 FEED Study/Detailed Design Regular Pay N 2 0 installation procedure review and meetings, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-11 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 3.5 0 fire water specification, grasshopper/dragchain design, suitcase alternative research and concept, HPU sound study review, revised HPU air flow calculation, piping material specification clarifications Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-11 OH-019 :OH-019 Overhead All Activities Regular Pay N 1 0 weekly meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-11 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 2 0 drawing review, casing data sheet review, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-12 CVX Genesis :CVX Genesis TSR-1725-GENP-01 FEED Study/Detailed Design Regular Pay N 2 0 installation procedure review and meetings, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-12 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 5.5 0 fire water specification, grasshopper/dragchain design, suitcase alternative research and concept, HPU sound study review, revised HPU air flow calculation, piping material specification clarifications Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-12 OH-019 :OH-019 Overhead All Activities Regular Pay N 1 0 weekly meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-13 CVX Genesis :CVX Genesis TSR-1725-GENP-01 FEED Study/Detailed Design Regular Pay N 2 0 installation procedure review and meetings, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-13 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 5.5 0 fire water specification, grasshopper/dragchain design, suitcase alternative research and concept, HPU sound study review, revised HPU air flow calculation, piping material specification clarifications Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-13 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 1 0 drawing review, casing data sheet review, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-14 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 4.5 0 fire water specification, grasshopper/dragchain design, suitcase alternative research and concept, HPU sound study review, revised HPU air flow calculation, piping material specification clarifications Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-14 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 TS meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-14 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1 0 Choke line recertification assistance, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-14 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 2 0 drawing review, casing data sheet review, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-15 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 3 0 fire water specification, grasshopper/dragchain design, suitcase alternative research and concept, HPU sound study review, revised HPU air flow calculation, piping material specification clarifications Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-15 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1 0 Choke line recertification assistance, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-15 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 2 0 drawing review, casing data sheet review, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-18 CVX Genesis :CVX Genesis TSR-1725-GENP-01 FEED Study/Detailed Design Regular Pay N 1 0 status update meeting, substructure lighting design assistance, SIT procedure review and meetings, non slip coating review, deck drain interface Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-18 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 2.5 0 grasshopper/dragchain clarification meetings and detailed design, fire water piping spec, HPU exhaust routing, Power swivel interface and electrical cable requirements Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-18 OH-019 :OH-019 Overhead All Activities Regular Pay N 1 0 weekly meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-18 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1 0 Kretchet choke line recertification assistance, Berkut mud standpipe support bolt torque assistance, kretchet rig move to south well site research Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-18 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 3 0 drawing review, created sketch of lifting tool & C-plate- and 4m spool shoulder, piping material spec clarifications, regulatory assistance on 3 items, correspondence with vendor Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-19 CVX Genesis :CVX Genesis TSR-1725-GENP-01 FEED Study/Detailed Design Regular Pay N 1 0 status update meeting, substructure lighting design assistance, SIT procedure review and meetings, non slip coating review, deck drain interface Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-19 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 3 0 grasshopper/dragchain clarification meetings and detailed design, fire water piping spec, HPU exhaust routing, Power swivel interface and electrical cable requirements Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-19 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 2 0 Kretchet choke line recertification assistance, Berkut mud standpipe support bolt torque assistance, kretchet rig move to south well site research Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-19 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 2.5 0 drawing review, created sketch of lifting tool & C-plate- and 4m spool shoulder, piping material spec clarifications, regulatory assistance on 3 items, correspondence with vendor Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-20 CVX Genesis :CVX Genesis TSR-1725-GENP-01 FEED Study/Detailed Design Regular Pay N 2.5 0 status update meeting, substructure lighting design assistance, SIT procedure review and meetings, non slip coating review, deck drain interface Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-20 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 4 0 grasshopper/dragchain clarification meetings and detailed design, fire water piping spec, HPU exhaust routing, Power swivel interface and electrical cable requirements Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-20 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 2 0 drawing review, created sketch of lifting tool & C-plate- and 4m spool shoulder, piping material spec clarifications, regulatory assistance on 3 items, correspondence with vendor Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-21 CVX Genesis :CVX Genesis TSR-1725-GENP-01 FEED Study/Detailed Design Regular Pay N 1 0 status update meeting, substructure lighting design assistance, SIT procedure review and meetings, non slip coating review, deck drain interface Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-21 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 4 0 grasshopper/dragchain clarification meetings and detailed design, fire water piping spec, HPU exhaust routing, Power swivel interface and electrical cable requirements Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-21 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 TS meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-21 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 2 0 Kretchet choke line recertification assistance, Berkut mud standpipe support bolt torque assistance, kretchet rig move to south well site research Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-21 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 0.5 0 drawing review, created sketch of lifting tool & C-plate- and 4m spool shoulder, piping material spec clarifications, regulatory assistance on 3 items, correspondence with vendor Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-22 CVX Genesis :CVX Genesis TSR-1725-GENP-01 FEED Study/Detailed Design Regular Pay N 2.5 0 status update meeting, substructure lighting design assistance, SIT procedure review and meetings, non slip coating review, deck drain interface Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-22 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 2.5 0 grasshopper/dragchain clarification meetings and detailed design, fire water piping spec, HPU exhaust routing, Power swivel interface and electrical cable requirements Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-22 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 1 0 drawing review, created sketch of lifting tool & C-plate- and 4m spool shoulder, piping material spec clarifications, regulatory assistance on 3 items, correspondence with vendor Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-25 OH-008 :OH-008 Overhead All Activities Regular Pay N 8 0 Memorial Day Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-26 CVX Genesis :CVX Genesis TSR-1725-GENP-01 FEED Study/Detailed Design Regular Pay N 2 0 status meetings, basis of design revision, master equipment list revision, superstructure lighting design assistance, air receiver sizing clarifications, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-26 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 3.5 0 grasshopper/dragchain clarifications, manrider air hoist clarifications, venturetech hydraulic interfaces, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-26 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1 0 Berkut u-bolt torque recommendation, Kretchet choke spool coorespondance, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-26 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 2 0 drawing review, material spec clarifications, C-plate closing mechanism concept, TPP meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-27 CVX Genesis :CVX Genesis TSR-1725-GENP-01 FEED Study/Detailed Design Regular Pay N 2 0 status meetings, basis of design revision, master equipment list revision, superstructure lighting design assistance, air receiver sizing clarifications, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-27 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 4 0 grasshopper/dragchain clarifications, manrider air hoist clarifications, venturetech hydraulic interfaces, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-27 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 3 0 holly east egress loads on festoon Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-28 CVX Genesis :CVX Genesis TSR-1725-GENP-01 FEED Study/Detailed Design Regular Pay N 3.5 0 status meetings, basis of design revision, master equipment list revision, superstructure lighting design assistance, air receiver sizing clarifications, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-28 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 3.5 0 grasshopper/dragchain clarifications, manrider air hoist clarifications, venturetech hydraulic interfaces, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-28 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 TS meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-28 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 0.5 0 drawing review, material spec clarifications, C-plate closing mechanism concept, TPP meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-29 CVX Genesis :CVX Genesis TSR-1725-GENP-01 FEED Study/Detailed Design Regular Pay N 1.5 0 status meetings, basis of design revision, master equipment list revision, superstructure lighting design assistance, air receiver sizing clarifications, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-29 CVX Genesis :CVX Genesis TSR-1725-GENP-02 Initiation and Procurement Regular Pay N 1 0 grasshopper/dragchain clarifications, manrider air hoist clarifications, venturetech hydraulic interfaces, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-29 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1 0 Berkut u-bolt torque recommendation, Kretchet choke spool coorespondance, Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-29 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 1.5 0 holly east egress loads on festoon Reck, John Engineer I 29656 Reck, John:Engineer I 2020-05-29 ORLAN-TSR :ORLAN-TSR TSR-01759-ORLP Casing Jetting Tool (9.625 in.) Regular Pay N 1 0 drawing review, material spec clarifications, C-plate closing mechanism concept, TPP meeting