Name Billing Class Employee No. Item Line Class Transaction Date Job No. Customer Service Item Notes Payroll Item Billable Employee Paid Day Rate Duration Days Remarks Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2019-09-22 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 Prepared pipe deck for utility piping, installed east side stations. Laid out routing for Bop closing lines. Prep and paint all raw iron on rig floor and sub base Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2019-09-23 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 Prepared pipe deck for utility piping, installed east side stations. Laid out routing for Bop closing lines. Prep and paint all raw iron on rig floor and sub base Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2019-09-24 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 Prepared pipe deck for utility piping, installed east side stations. Laid out routing for Bop closing lines. Prep and paint all raw iron on rig floor and sub base Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2019-09-25 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 Prepared pipe deck for utility piping, installed east side stations. Laid out routing for Bop closing lines. Prep and paint all raw iron on rig floor and sub base Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2019-09-26 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 Prepared pipe deck for utility piping, installed east side stations. Laid out routing for Bop closing lines. Prep and paint all raw iron on rig floor and sub base Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2019-09-27 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 Prepared pipe deck for utility piping, installed east side stations. Laid out routing for Bop closing lines. Prep and paint all raw iron on rig floor and sub base Broussard, Leroy Operations Supervisor Broussard, Leroy:Operations Supervisor 2019-09-28 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 Prepared pipe deck for utility piping, installed east side stations. Laid out routing for Bop closing lines. Prep and paint all raw iron on rig floor and sub base Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-01 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 7 0 Working with California Team to progress rig repairs, tracking equipment and materials.Reviewing and ordering spare parts packages, handling tools, equipment quotes, specifications, MTO's, & MR's for procurement. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-01 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 7 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station, Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-02 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 7 0 Working with California Team to progress rig repairs, tracking equipment and materials.Reviewing and ordering spare parts packages, handling tools, equipment quotes, specifications, MTO's, & MR's for procurement. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-02 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 7 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station, Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-03 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 7 0 Working with California Team to progress rig repairs, tracking equipment and materials.Reviewing and ordering spare parts packages, handling tools, equipment quotes, specifications, MTO's, & MR's for procurement. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-03 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 7 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station, Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-04 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 7 0 Working with California Team to progress rig repairs, tracking equipment and materials.Reviewing and ordering spare parts packages, handling tools, equipment quotes, specifications, MTO's, & MR's for procurement. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-04 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 7 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station, Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-05 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 7 0 Working with California Team to progress rig repairs, tracking equipment and materials.Reviewing and ordering spare parts packages, handling tools, equipment quotes, specifications, MTO's, & MR's for procurement. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-05 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 7 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station, Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-06 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 7 0 Working with California Team to progress rig repairs, tracking equipment and materials.Reviewing and ordering spare parts packages, handling tools, equipment quotes, specifications, MTO's, & MR's for procurement. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-06 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 7 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station, Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-07 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 7 0 Working with California Team to progress rig repairs, tracking equipment and materials.Reviewing and ordering spare parts packages, handling tools, equipment quotes, specifications, MTO's, & MR's for procurement. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-07 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 7 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station, Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-08 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 7 0 Working with California Team to progress rig repairs, tracking equipment and materials.Reviewing and ordering spare parts packages, handling tools, equipment quotes, specifications, MTO's, & MR's for procurement. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-08 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 7 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station, Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-09 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 7 0 Working with California Team to progress rig repairs, tracking equipment and materials.Reviewing and ordering spare parts packages, handling tools, equipment quotes, specifications, MTO's, & MR's for procurement. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-09 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 7 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station, Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-10 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 7 0 Working with California Team to progress rig repairs, tracking equipment and materials.Reviewing and ordering spare parts packages, handling tools, equipment quotes, specifications, MTO's, & MR's for procurement. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-10 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 7 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station, Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-11 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 7 0 Working with California Team to progress rig repairs, tracking equipment and materials.Reviewing and ordering spare parts packages, handling tools, equipment quotes, specifications, MTO's, & MR's for procurement. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-11 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 7 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station, Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-12 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 7 0 Working with California Team to progress rig repairs, tracking equipment and materials.Reviewing and ordering spare parts packages, handling tools, equipment quotes, specifications, MTO's, & MR's for procurement. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-12 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 7 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station, Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-13 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 7 0 Working with California Team to progress rig repairs, tracking equipment and materials.Reviewing and ordering spare parts packages, handling tools, equipment quotes, specifications, MTO's, & MR's for procurement. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-13 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 7 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station, Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-14 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 7 0 Working with California Team to progress rig repairs, tracking equipment and materials.Reviewing and ordering spare parts packages, handling tools, equipment quotes, specifications, MTO's, & MR's for procurement. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-14 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 7 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station, Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-15 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-16 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-17 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-18 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-19 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-20 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-21 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-22 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-23 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-24 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-25 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-26 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 Working with XOM & T&B on the Sea Water Lift Pumps, 3rd Party Utilities Power & Services, Auger System for Shaker, and Bunkering Station Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2019-09-27 Holly Platform :Holly Platform TSR-01665-HOLP-97 Travel (OH) Regular Pay N 8 0 Travel from Santa Barbara to Oklahoma City Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-01 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 8 0 Travel to and from CA for presentation to BW and CSLC, Create PPT and present Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-02 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 8 0 Travel to and from CA for presentation to BW and CSLC, Create PPT and present Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-03 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 5.5 0 procurement, change management, weekly report, cost tracking, schedule updates, technical clarifications, Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-03 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Travel to and from CA for presentation to BW and CSLC, Create PPT and present Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-04 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 8 0 Travel to and from CA for presentation to BW and CSLC, Create PPT and present Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-05 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 9.5 0 procurement, change management, weekly report, cost tracking, schedule updates, technical clarifications, Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-06 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 6 0 procurement, change management, weekly report, cost tracking, schedule updates, technical clarifications, Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-09 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 7.5 0 procurement, change management, weekly report, cost tracking, schedule updates, technical clarifications, supplier coordination Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-09 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 2 0 Coordinate and expedite procurement for bunkering structural and mechanical systems, seawater pump spools, and engineering for MGS integration Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-10 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 8.5 0 procurement, change management, weekly report, cost tracking, schedule updates, technical clarifications, supplier coordination Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-10 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 1 0 Coordinate and expedite procurement for bunkering structural and mechanical systems, seawater pump spools, and engineering for MGS integration Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-11 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 4.5 0 procurement, change management, weekly report, cost tracking, schedule updates, technical clarifications, supplier coordination Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-11 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 1 0 Coordinate and expedite procurement for bunkering structural and mechanical systems, seawater pump spools, and engineering for MGS integration Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-12 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 8.5 0 procurement, change management, weekly report, cost tracking, schedule updates, technical clarifications, supplier coordination Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-12 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 1 0 Coordinate and expedite procurement for bunkering structural and mechanical systems, seawater pump spools, and engineering for MGS integration Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-13 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 5 0 procurement, change management, weekly report, cost tracking, schedule updates, technical clarifications, supplier coordination Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-16 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 3.5 0 Closeout, cost tracking Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-16 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 3 0 Coordinate engineering and procurement for bunkering, Drillwater piping, mud gas separator piping, bunkering structural, auger system, LP flare tie-in, monitor costs Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-17 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 3.5 0 Closeout, cost tracking Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-17 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 3 0 Coordinate engineering and procurement for bunkering, Drillwater piping, mud gas separator piping, bunkering structural, auger system, LP flare tie-in, monitor costs Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-18 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 3 0 Closeout, cost tracking Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-18 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 2.5 0 Coordinate engineering and procurement for bunkering, Drillwater piping, mud gas separator piping, bunkering structural, auger system, LP flare tie-in, monitor costs Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-19 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 4.5 0 Closeout, cost tracking Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-19 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 3 0 Coordinate engineering and procurement for bunkering, Drillwater piping, mud gas separator piping, bunkering structural, auger system, LP flare tie-in, monitor costs Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-20 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 2 0 Closeout, cost tracking Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-20 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 1 0 Coordinate engineering and procurement for bunkering, Drillwater piping, mud gas separator piping, bunkering structural, auger system, LP flare tie-in, monitor costs Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-24 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Coordinate engineering and procurement for bunkering, Drillwater piping, mud gas separator piping, bunkering structural, auger system, LP flare tie-in, monitor costs Lambert, Joshua Project Manager JOSHLAMBERT Lambert, Joshua:Project Manager 2019-09-25 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Coordinate engineering and procurement for bunkering, Drillwater piping, mud gas separator piping, bunkering structural, auger system, LP flare tie-in, monitor costs Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2019-09-04 Holly Platform :Holly Platform TSR-01665-HOLP-99 Project Management (OH) Regular Pay N 2 0 Design review Additional scope review Personnel administration Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2019-09-20 Holly Platform :Holly Platform TSR-01665-HOLP-99 Project Management (OH) Regular Pay N 1.25 0 drawing review general administration Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-01 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 6 0 09/01: HP mud line P&ID PFD schematic; DF GA updates 09/04: walk down LP mud P&ID 09/05: continue tracing/walk down LP mud lines; generate as-built P&ID 09/06: update model of LP piping from schematic drawing 09/07: photograph as-builts; rename/organize photos; as-builts of LP piping and mousehole assembly Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-01 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 8 0 09/01: bunkering station model updates; P&ID schematic updates 09/02&09/03: bunkering station model updates, concept development, and image exports. 09/04: bunkering station P&ID updates; auger system concept development; 09/05: update final drill water piping model per schematic sketch; Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-02 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 12 0 09/01: bunkering station model updates; P&ID schematic updates 09/02&09/03: bunkering station model updates, concept development, and image exports. 09/04: bunkering station P&ID updates; auger system concept development; 09/05: update final drill water piping model per schematic sketch; Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-03 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 12 0 09/01: bunkering station model updates; P&ID schematic updates 09/02&09/03: bunkering station model updates, concept development, and image exports. 09/04: bunkering station P&ID updates; auger system concept development; 09/05: update final drill water piping model per schematic sketch; Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-04 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 6 0 09/01: HP mud line P&ID PFD schematic; DF GA updates 09/04: walk down LP mud P&ID 09/05: continue tracing/walk down LP mud lines; generate as-built P&ID 09/06: update model of LP piping from schematic drawing 09/07: photograph as-builts; rename/organize photos; as-builts of LP piping and mousehole assembly Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-04 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 8 0 09/01: bunkering station model updates; P&ID schematic updates 09/02&09/03: bunkering station model updates, concept development, and image exports. 09/04: bunkering station P&ID updates; auger system concept development; 09/05: update final drill water piping model per schematic sketch; Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-05 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 14 0 09/01: HP mud line P&ID PFD schematic; DF GA updates 09/04: walk down LP mud P&ID 09/05: continue tracing/walk down LP mud lines; generate as-built P&ID 09/06: update model of LP piping from schematic drawing 09/07: photograph as-builts; rename/organize photos; as-builts of LP piping and mousehole assembly Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-06 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 12 0 09/01: HP mud line P&ID PFD schematic; DF GA updates 09/04: walk down LP mud P&ID 09/05: continue tracing/walk down LP mud lines; generate as-built P&ID 09/06: update model of LP piping from schematic drawing 09/07: photograph as-builts; rename/organize photos; as-builts of LP piping and mousehole assembly Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-07 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 14 0 09/01: HP mud line P&ID PFD schematic; DF GA updates 09/04: walk down LP mud P&ID 09/05: continue tracing/walk down LP mud lines; generate as-built P&ID 09/06: update model of LP piping from schematic drawing 09/07: photograph as-builts; rename/organize photos; as-builts of LP piping and mousehole assembly Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-08 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 09/08: MSG skid modification as-built and modeling on DF 09/09: auger concept installation and motor access platform. 09/11-12: model cantilever structure for Halliburton's explosive container with jettison 09/14: bell nipple housing CAD drawings; DF egress concept model Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-09 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 09/08: MSG skid modification as-built and modeling on DF 09/09: auger concept installation and motor access platform. 09/11-12: model cantilever structure for Halliburton's explosive container with jettison 09/14: bell nipple housing CAD drawings; DF egress concept model Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-10 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 14 0 09/10-11: LP piping as-built; HP P&ID walk-down for as-built. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-11 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 7 0 09/10-11: LP piping as-built; HP P&ID walk-down for as-built. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-11 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 7 0 09/08: MSG skid modification as-built and modeling on DF 09/09: auger concept installation and motor access platform. 09/11-12: model cantilever structure for Halliburton's explosive container with jettison 09/14: bell nipple housing CAD drawings; DF egress concept model Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-12 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 09/08: MSG skid modification as-built and modeling on DF 09/09: auger concept installation and motor access platform. 09/11-12: model cantilever structure for Halliburton's explosive container with jettison 09/14: bell nipple housing CAD drawings; DF egress concept model Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-14 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 09/08: MSG skid modification as-built and modeling on DF 09/09: auger concept installation and motor access platform. 09/11-12: model cantilever structure for Halliburton's explosive container with jettison 09/14: bell nipple housing CAD drawings; DF egress concept model Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-15 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 09/15: east DF egress concept model; KBC/DF access walkway concept model; bell nipple drawings 09/16-17: update model of bunkering station water supply (with stanchions); generate concept model of supply line (from bunkering station) 09/18: generate rig plan GA's of pipe deck level; CTU clash check; 09/19: generate rig GA's and section view for Jelec. 09/20: travel from SBA to IAH 09/21: generate active tank views for Jelec (south and west elevations) Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-16 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 09/15: east DF egress concept model; KBC/DF access walkway concept model; bell nipple drawings 09/16-17: update model of bunkering station water supply (with stanchions); generate concept model of supply line (from bunkering station) 09/18: generate rig plan GA's of pipe deck level; CTU clash check; 09/19: generate rig GA's and section view for Jelec. 09/20: travel from SBA to IAH 09/21: generate active tank views for Jelec (south and west elevations) Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-17 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 09/15: east DF egress concept model; KBC/DF access walkway concept model; bell nipple drawings 09/16-17: update model of bunkering station water supply (with stanchions); generate concept model of supply line (from bunkering station) 09/18: generate rig plan GA's of pipe deck level; CTU clash check; 09/19: generate rig GA's and section view for Jelec. 09/20: travel from SBA to IAH 09/21: generate active tank views for Jelec (south and west elevations) Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-18 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 09/15: east DF egress concept model; KBC/DF access walkway concept model; bell nipple drawings 09/16-17: update model of bunkering station water supply (with stanchions); generate concept model of supply line (from bunkering station) 09/18: generate rig plan GA's of pipe deck level; CTU clash check; 09/19: generate rig GA's and section view for Jelec. 09/20: travel from SBA to IAH 09/21: generate active tank views for Jelec (south and west elevations) Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-19 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 14 0 09/15: east DF egress concept model; KBC/DF access walkway concept model; bell nipple drawings 09/16-17: update model of bunkering station water supply (with stanchions); generate concept model of supply line (from bunkering station) 09/18: generate rig plan GA's of pipe deck level; CTU clash check; 09/19: generate rig GA's and section view for Jelec. 09/20: travel from SBA to IAH 09/21: generate active tank views for Jelec (south and west elevations) Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-20 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 8 0 09/15: east DF egress concept model; KBC/DF access walkway concept model; bell nipple drawings 09/16-17: update model of bunkering station water supply (with stanchions); generate concept model of supply line (from bunkering station) 09/18: generate rig plan GA's of pipe deck level; CTU clash check; 09/19: generate rig GA's and section view for Jelec. 09/20: travel from SBA to IAH 09/21: generate active tank views for Jelec (south and west elevations) Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-21 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 6 0 09/15: east DF egress concept model; KBC/DF access walkway concept model; bell nipple drawings 09/16-17: update model of bunkering station water supply (with stanchions); generate concept model of supply line (from bunkering station) 09/18: generate rig plan GA's of pipe deck level; CTU clash check; 09/19: generate rig GA's and section view for Jelec. 09/20: travel from SBA to IAH 09/21: generate active tank views for Jelec (south and west elevations) Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2019-09-26 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 7 0 begin preliminary piping model for MSG Patel, Ripal Engineer II Patel, Ripal:Engineer II 2019-09-09 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 8 0 Power Load Analysis Done for Holly Patel, Ripal Engineer II Patel, Ripal:Engineer II 2019-09-10 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 8 0 Power Load Analysis Done for Holly Patel, Ripal Engineer II Patel, Ripal:Engineer II 2019-09-11 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 4 0 Power Load Analysis Done for Holly Patel, Ripal Engineer II Patel, Ripal:Engineer II 2019-09-16 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 Standby GEN Load Analysis Done Patel, Ripal Engineer II Patel, Ripal:Engineer II 2019-09-20 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 8 0 Standby GEN Load Analysis Done Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-03 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 4 0 started holly rig equipment inventory, LP mud P&ID review, valve and line registry for LP mud, choke hose adapter spool, mud standpipe replacement sensor tree Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-03 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 3 0 sea water pump cable and turnbuckle, bunkering station MTO, bunkering station piping drawing review and redline, created sea water pipe spool drawing Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-04 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 1.5 0 started holly rig equipment inventory, LP mud P&ID review, valve and line registry for LP mud, choke hose adapter spool, mud standpipe replacement sensor tree Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-04 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 5 0 sea water pump cable and turnbuckle, bunkering station MTO, bunkering station piping drawing review and redline, created sea water pipe spool drawing Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-05 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 2.5 0 started holly rig equipment inventory, LP mud P&ID review, valve and line registry for LP mud, choke hose adapter spool, mud standpipe replacement sensor tree Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-05 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 sea water pump cable and turnbuckle, bunkering station MTO, bunkering station piping drawing review and redline, created sea water pipe spool drawing Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-06 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 3 0 started holly rig equipment inventory, LP mud P&ID review, valve and line registry for LP mud, choke hose adapter spool, mud standpipe replacement sensor tree Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-06 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 2 0 sea water pump cable and turnbuckle, bunkering station MTO, bunkering station piping drawing review and redline, created sea water pipe spool drawing Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-10 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 3 0 redlined lp mud drawing for valve and line numbers, equipment tag info for P&IDs, speced out HP adapter spools and reviewed quotes, valve registry and naming convention Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-10 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 3 0 finalized bunkering station MTO, seawater MTO, MGS vent line routing and MTO, natural gas line into MGS piping spec and material, MGS vent line MTO creation, Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-11 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 2.5 0 redlined lp mud drawing for valve and line numbers, equipment tag info for P&IDs, speced out HP adapter spools and reviewed quotes, valve registry and naming convention Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-11 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 4 0 finalized bunkering station MTO, seawater MTO, MGS vent line routing and MTO, natural gas line into MGS piping spec and material, MGS vent line MTO creation, Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-12 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 2 0 redlined lp mud drawing for valve and line numbers, equipment tag info for P&IDs, speced out HP adapter spools and reviewed quotes, valve registry and naming convention Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-12 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 5.5 0 finalized bunkering station MTO, seawater MTO, MGS vent line routing and MTO, natural gas line into MGS piping spec and material, MGS vent line MTO creation, Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-13 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 1.5 0 redlined lp mud drawing for valve and line numbers, equipment tag info for P&IDs, speced out HP adapter spools and reviewed quotes, valve registry and naming convention Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-13 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 3 0 finalized bunkering station MTO, seawater MTO, MGS vent line routing and MTO, natural gas line into MGS piping spec and material, MGS vent line MTO creation, Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-16 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 3 0 kbc lowering apparatus, rig inventory list,equipment tag info for P&IDs, speced out HP adapter spools and reviewed quotes, valve registry and naming convention, new choke line modification, Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-16 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 2 0 MGS vent line routing and MTO, natural gas line into MGS piping spec and material, MGS vent line MTO creation, Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-17 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 2.5 0 kbc lowering apparatus, rig inventory list,equipment tag info for P&IDs, speced out HP adapter spools and reviewed quotes, valve registry and naming convention, new choke line modification, Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-17 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 1.5 0 MGS vent line routing and MTO, natural gas line into MGS piping spec and material, MGS vent line MTO creation, Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-18 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 4.5 0 kbc lowering apparatus, rig inventory list,equipment tag info for P&IDs, speced out HP adapter spools and reviewed quotes, valve registry and naming convention, new choke line modification, Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-18 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 2.5 0 MGS vent line routing and MTO, natural gas line into MGS piping spec and material, MGS vent line MTO creation, Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-19 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 3.5 0 kbc lowering apparatus, rig inventory list,equipment tag info for P&IDs, speced out HP adapter spools and reviewed quotes, valve registry and naming convention, new choke line modification, Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-19 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 2 0 MGS vent line routing and MTO, natural gas line into MGS piping spec and material, MGS vent line MTO creation, Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-20 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 1.5 0 kbc lowering apparatus, rig inventory list,equipment tag info for P&IDs, speced out HP adapter spools and reviewed quotes, valve registry and naming convention, new choke line modification, Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-20 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 2 0 MGS vent line routing and MTO, natural gas line into MGS piping spec and material, MGS vent line MTO creation, Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-23 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 1.5 0 rig inventory list,equipment tag info for P&IDs, speced out HP adapter spools and reviewed quotes, valve registry and naming convention, new choke line modification, Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-23 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 1 0 gas line and vent line material spec and clarifications Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-24 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 2.5 0 rig inventory list,equipment tag info for P&IDs, speced out HP adapter spools and reviewed quotes, valve registry and naming convention, new choke line modification, Reck, John Engineer I 29656 Reck, John:Engineer I 2019-09-24 Holly Platform :Holly Platform TSR-01665-HOLP-21 Reimbursable Rig Repairs Regular Pay N 1 0 gas line and vent line material spec and clarifications WILSON, SVETLANA Administrative Services I 33746 WILSON, SVETLANA:Administrative Services I 2019-09-02 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 2 0 EM timesheet, monthly invoice, NTT MSA, MRs, cost tracker update, labor variance update WILSON, SVETLANA Administrative Services I 33746 WILSON, SVETLANA:Administrative Services I 2019-09-03 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 1 0 EM timesheet, monthly invoice, NTT MSA, MRs, cost tracker update, labor variance update WILSON, SVETLANA Administrative Services I 33746 WILSON, SVETLANA:Administrative Services I 2019-09-04 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 3 0 EM timesheet, monthly invoice, NTT MSA, MRs, cost tracker update, labor variance update WILSON, SVETLANA Administrative Services I 33746 WILSON, SVETLANA:Administrative Services I 2019-09-05 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 1 0 EM timesheet, monthly invoice, NTT MSA, MRs, cost tracker update, labor variance update WILSON, SVETLANA Administrative Services I 33746 WILSON, SVETLANA:Administrative Services I 2019-09-11 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 2 0 Cost tracker update, labor variance update, EM timesheet , WILSON, SVETLANA Administrative Services I 33746 WILSON, SVETLANA:Administrative Services I 2019-09-12 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 2 0 Cost tracker update, labor variance update, EM timesheet , WILSON, SVETLANA Administrative Services I 33746 WILSON, SVETLANA:Administrative Services I 2019-09-16 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 2 0 CD Lyon timesheets receipt, EM timesheet, cost tracker, labor variance tracker update WILSON, SVETLANA Administrative Services I 33746 WILSON, SVETLANA:Administrative Services I 2019-09-17 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 3 0 CD Lyon timesheets receipt, EM timesheet, cost tracker, labor variance tracker update WILSON, SVETLANA Administrative Services I 33746 WILSON, SVETLANA:Administrative Services I 2019-09-23 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 1 0 CD Lyon receipts, cost tracker update, labor variance, timesheets, invoice payment WILSON, SVETLANA Administrative Services I 33746 WILSON, SVETLANA:Administrative Services I 2019-09-24 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 4 0 CD Lyon receipts, cost tracker update, labor variance, timesheets, invoice payment WILSON, SVETLANA Administrative Services I 33746 WILSON, SVETLANA:Administrative Services I 2019-09-25 Holly Platform :Holly Platform TSR-01665-HOLP-20 Rig Upgrades Regular Pay N 4 0 CD Lyon receipts, cost tracker update, labor variance, timesheets, invoice payment