Name Billing Class Employee No. Item Line Class Transaction Date Job No. Customer Service Item Notes Payroll Item Billable Employee Paid Day Rate Duration Days Remarks Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2017-11-05 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 Travel to St. johns, on Sunday, Meet with Ron Taffee and Steve Sharpe on Monday to discuss project overview, Prepared slides and information on Tuesday. Meet with HMDC on Wednesday and Thursday, debrief on Thursday with PDC, travel back to Houston on Friday Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2017-11-06 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 Travel to St. johns, on Sunday, Meet with Ron Taffee and Steve Sharpe on Monday to discuss project overview, Prepared slides and information on Tuesday. Meet with HMDC on Wednesday and Thursday, debrief on Thursday with PDC, travel back to Houston on Friday Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2017-11-07 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 Travel to St. johns, on Sunday, Meet with Ron Taffee and Steve Sharpe on Monday to discuss project overview, Prepared slides and information on Tuesday. Meet with HMDC on Wednesday and Thursday, debrief on Thursday with PDC, travel back to Houston on Friday Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2017-11-08 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 Travel to St. johns, on Sunday, Meet with Ron Taffee and Steve Sharpe on Monday to discuss project overview, Prepared slides and information on Tuesday. Meet with HMDC on Wednesday and Thursday, debrief on Thursday with PDC, travel back to Houston on Friday Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2017-11-09 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 Travel to St. johns, on Sunday, Meet with Ron Taffee and Steve Sharpe on Monday to discuss project overview, Prepared slides and information on Tuesday. Meet with HMDC on Wednesday and Thursday, debrief on Thursday with PDC, travel back to Houston on Friday Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2017-11-10 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 Travel to St. johns, on Sunday, Meet with Ron Taffee and Steve Sharpe on Monday to discuss project overview, Prepared slides and information on Tuesday. Meet with HMDC on Wednesday and Thursday, debrief on Thursday with PDC, travel back to Houston on Friday Carmichael, Steve Manager/Staff Consultant Carmichael, Steve:Manager/Staff Consultant 2017-11-07 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 11/7- Travel to St. Johns 11/8 - 11/ 9 workshop 11/10 - Travel Home Carmichael, Steve Manager/Staff Consultant Carmichael, Steve:Manager/Staff Consultant 2017-11-08 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 11/7- Travel to St. Johns 11/8 - 11/ 9 workshop 11/10 - Travel Home Carmichael, Steve Manager/Staff Consultant Carmichael, Steve:Manager/Staff Consultant 2017-11-09 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 11/7- Travel to St. Johns 11/8 - 11/ 9 workshop 11/10 - Travel Home Carmichael, Steve Manager/Staff Consultant Carmichael, Steve:Manager/Staff Consultant 2017-11-10 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 11/7- Travel to St. Johns 11/8 - 11/ 9 workshop 11/10 - Travel Home Corse, Ian Sr. Electrical Engineer Corse, Ian:Sr. Electrical Engineer 2017-11-06 OH-005 :OH-005 Overhead All Activities Regular Pay N 8 0 Corse, Ian Sr. Electrical Engineer Corse, Ian:Sr. Electrical Engineer 2017-11-07 OH-005 :OH-005 Overhead All Activities Regular Pay N 8 0 Corse, Ian Sr. Electrical Engineer Corse, Ian:Sr. Electrical Engineer 2017-11-08 OH-002 :OH-002 Overhead All Activities Regular Pay N 8 0 Father in law funeral Corse, Ian Sr. Electrical Engineer Corse, Ian:Sr. Electrical Engineer 2017-11-09 OH-005 :OH-005 Overhead All Activities Regular Pay N 8 0 Corse, Ian Sr. Electrical Engineer Corse, Ian:Sr. Electrical Engineer 2017-11-10 OH-005 :OH-005 Overhead All Activities Regular Pay N 8 0 Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2017-11-06 EHBU-TSRs :EHBU-TSRs TSR-01521-EHBU Total Uganda Support Regular Pay N 9.5 0 Histogram learning and revising, Peer review meeting, modify histogram again, update cost estimate, send info to HH, talk with Lizzy, peer review, cost estimate, review sound study, update action item list with HH comments, review cashflow schedule with Rob, email HH about questions, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2017-11-07 EHBU-TSRs :EHBU-TSRs TSR-01521-EHBU Total Uganda Support Regular Pay N 8 0 Histogram learning and revising, Peer review meeting, modify histogram again, update cost estimate, send info to HH, talk with Lizzy, peer review, cost estimate, review sound study, update action item list with HH comments, review cashflow schedule with Rob, email HH about questions, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2017-11-08 EHBU-TSRs :EHBU-TSRs TSR-01521-EHBU Total Uganda Support Regular Pay N 7.5 0 Histogram learning and revising, Peer review meeting, modify histogram again, update cost estimate, send info to HH, talk with Lizzy, peer review, cost estimate, review sound study, update action item list with HH comments, review cashflow schedule with Rob, email HH about questions, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2017-11-08 Rig 270L-TSR :Rig 270L-TSR TSR-01595-270L Skidding Pony Sub Regular Pay N 1 0 update assumptions, update formatting, submit detailed cost estimate to Dean Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2017-11-09 EHBU-TSRs :EHBU-TSRs TSR-01521-EHBU Total Uganda Support Regular Pay N 7.5 0 Histogram learning and revising, Peer review meeting, modify histogram again, update cost estimate, send info to HH, talk with Lizzy, peer review, cost estimate, review sound study, update action item list with HH comments, review cashflow schedule with Rob, email HH about questions, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2017-11-09 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.5 0 TSR meeting Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2017-11-09 Rig 270L-TSR :Rig 270L-TSR TSR-01595-270L Skidding Pony Sub Regular Pay N 2 0 update assumptions, update formatting, submit detailed cost estimate to Dean Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2017-11-10 EHBU-TSRs :EHBU-TSRs TSR-01521-EHBU Total Uganda Support Regular Pay N 1 0 Histogram learning and revising, Peer review meeting, modify histogram again, update cost estimate, send info to HH, talk with Lizzy, peer review, cost estimate, review sound study, update action item list with HH comments, review cashflow schedule with Rob, email HH about questions, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2017-11-10 Rig 077B-TSR :Rig 077B-TSR TSR-01603-077B SEMS Package Regular Pay N 4 0 copy over calculations, call Leroy and prep for trip, change hotels, review drawings Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2017-11-06 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 (11/06/17) Updated weekly timesheet and submitted for approval. (11/08/17) General TSR update with designers. (11/10/17) Updated timesheet. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2017-11-06 OH-009 :OH-009 OH-009-017 Aksai Regular Pay N 2 0 (11/06/17) Discussed 216 HP piping with Kyle. Pulled drawings and reviewed scope with Lam. (11/07/17) Reviewed drawings/sketch with Lam. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2017-11-06 OH-009 :OH-009 OH-009-023 Gulf of Mexico Regular Pay N 6 0 (11/06/17) 77B ballast P&ID/PFD changes. (11/07/17) Cont drawing updates. (11/08/17) Started new PFD drawings. (11/10/17) Printed drawing package for 77B rig visit. discussed scope with Tyler/Kyle. Called Leroy to confirm travel plans. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2017-11-07 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.25 0 (11/07/17) Team meeting. (11/09/17) Weekly TSR meeting. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2017-11-07 OH-009 :OH-009 OH-009-017 Aksai Regular Pay N 1 0 (11/06/17) Discussed 216 HP piping with Kyle. Pulled drawings and reviewed scope with Lam. (11/07/17) Reviewed drawings/sketch with Lam. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2017-11-07 OH-009 :OH-009 OH-009-023 Gulf of Mexico Regular Pay N 5.75 0 (11/06/17) 77B ballast P&ID/PFD changes. (11/07/17) Cont drawing updates. (11/08/17) Started new PFD drawings. (11/10/17) Printed drawing package for 77B rig visit. discussed scope with Tyler/Kyle. Called Leroy to confirm travel plans. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2017-11-07 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1 0 (11/07/17) discussed new Berkut TRS with Kyle. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2017-11-07 Rig 272L-TSR :Rig 272L-TSR TSR-01609-272L-273L Rig GA & BOP Stack Updates Regular Pay N 1 0 (11/07/17) Sent drawings to lam for transmittal. Archived files on the Q. (11/10/17) revised closeout and sent for approval. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2017-11-08 Berkut-TSR :Berkut-TSR TSR-01614-BERP Cement Unit Jib Lifting Tool Regular Pay N 6.5 0 (11/08/17) Worked on new jib base sketch - discussed with Kyle. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2017-11-08 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.5 0 (11/06/17) Updated weekly timesheet and submitted for approval. (11/08/17) General TSR update with designers. (11/10/17) Updated timesheet. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2017-11-08 OH-009 :OH-009 OH-009-023 Gulf of Mexico Regular Pay N 2 0 (11/06/17) 77B ballast P&ID/PFD changes. (11/07/17) Cont drawing updates. (11/08/17) Started new PFD drawings. (11/10/17) Printed drawing package for 77B rig visit. discussed scope with Tyler/Kyle. Called Leroy to confirm travel plans. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2017-11-09 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.5 0 (11/07/17) Team meeting. (11/09/17) Weekly TSR meeting. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2017-11-09 OH-009 :OH-009 OH-009-020 Indonesia Regular Pay N 6 0 (11/09/17) Pulled new proposal number for Star energy proposal. Scaled site plans and started rig layouts. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2017-11-09 Rig 209L-TSR :Rig 209L-TSR TSR-01593-209L Suitcase Platform & DSM-DM Walkway Regular Pay N 2.5 0 (11/09/17) Checked DSM platform drawing. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2017-11-10 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 (11/06/17) Updated weekly timesheet and submitted for approval. (11/08/17) General TSR update with designers. (11/10/17) Updated timesheet. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2017-11-10 OH-009 :OH-009 OH-009-023 Gulf of Mexico Regular Pay N 4.5 0 (11/06/17) 77B ballast P&ID/PFD changes. (11/07/17) Cont drawing updates. (11/08/17) Started new PFD drawings. (11/10/17) Printed drawing package for 77B rig visit. discussed scope with Tyler/Kyle. Called Leroy to confirm travel plans. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2017-11-10 Rig 272L-TSR :Rig 272L-TSR TSR-01609-272L-273L Rig GA & BOP Stack Updates Regular Pay N 0.5 0 (11/07/17) Sent drawings to lam for transmittal. Archived files on the Q. (11/10/17) revised closeout and sent for approval. Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2017-11-06 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Kanban meeting , TSR weekly meeting Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2017-11-06 OH-019 :OH-019 Overhead All Activities Regular Pay N 1 0 Weekly Sakhalin meeting Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2017-11-06 ORLAN-TSR :ORLAN-TSR TSR-01582-ORLP Poorboy Degasser (electrical) Regular Pay N 7 0 TSR review and closeout Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2017-11-07 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 5 0 1. Review NOV quote 2. Review wood group quote 3. Create clarifications form on quote 4 Scope of work for DDAS system. Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2017-11-07 ORLAN-TSR :ORLAN-TSR TSR-01582-ORLP Poorboy Degasser (electrical) Regular Pay N 3 0 TSR review and closeout Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2017-11-08 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 8 0 1. Review NOV quote 2. Review wood group quote 3. Create clarifications form on quote 4 Scope of work for DDAS system. Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2017-11-08 OH-013 :OH-013 Overhead All Activities Regular Pay N 1 0 TSR worksheet Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2017-11-09 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 8 0 1. Review NOV quote 2. Review wood group quote 3. Create clarifications form on quote 4 Scope of work for DDAS system. Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2017-11-09 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Kanban meeting , TSR weekly meeting Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2017-11-10 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 5 0 1. Review NOV quote 2. Review wood group quote 3. Create clarifications form on quote 4 Scope of work for DDAS system. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-11-06 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 6 0 Continue to attend Conference Calls Meetings. Reviewing NOV proposed Top Drive single line power/control drawings as well as VFD building drawings presented by NOV. Reviewing the Set Point proposal SOW for engineering services. Continue the review DDAS for potential upgrade that will be required when entire systems upgrade. Review the Wood Group proposal for the work to be done for the Top Drive upgrade. Conference call with Joshua and Sachin to discuss the Wood Group SOW/Cost Proposal. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-11-06 OH-009 :OH-009 OH-009-003 Husky Energy WREP Regular Pay N 2 0 Review presentation details for preparation for the Thursday meeting with Wood Group for the Husky Project. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-11-06 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 4 0 Reviewing PM procedures for AC/DC motors and systems. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-11-07 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 Travel to St. John's NF on Tuesday for PM review on the Hibernia Project. Attend PM workshop for Hibernia full day on Wednesday and half a day on Thursday to review "Action Item List that created in Wednesday Work Shop. Return travel on Friday from St. John's. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-11-08 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 Travel to St. John's NF on Tuesday for PM review on the Hibernia Project. Attend PM workshop for Hibernia full day on Wednesday and half a day on Thursday to review "Action Item List that created in Wednesday Work Shop. Return travel on Friday from St. John's. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-11-08 OH-009 :OH-009 OH-009-003 Husky Energy WREP Regular Pay N 2 0 Review presentation details for preparation for the Thursday meeting with Wood Group for the Husky Project. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-11-09 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 3 0 Continue to attend Conference Calls Meetings. Reviewing NOV proposed Top Drive single line power/control drawings as well as VFD building drawings presented by NOV. Reviewing the Set Point proposal SOW for engineering services. Continue the review DDAS for potential upgrade that will be required when entire systems upgrade. Review the Wood Group proposal for the work to be done for the Top Drive upgrade. Conference call with Joshua and Sachin to discuss the Wood Group SOW/Cost Proposal. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-11-09 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 5 0 Travel to St. John's NF on Tuesday for PM review on the Hibernia Project. Attend PM workshop for Hibernia full day on Wednesday and half a day on Thursday to review "Action Item List that created in Wednesday Work Shop. Return travel on Friday from St. John's. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-11-09 OH-009 :OH-009 OH-009-003 Husky Energy WREP Regular Pay N 4 0 Review presentation details for preparation for the Thursday meeting with Wood Group for the Husky Project. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-11-10 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 Travel to St. John's NF on Tuesday for PM review on the Hibernia Project. Attend PM workshop for Hibernia full day on Wednesday and half a day on Thursday to review "Action Item List that created in Wednesday Work Shop. Return travel on Friday from St. John's. Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2017-11-06 OH-001 :OH-001 Overhead All Activities Regular Pay N 8 0 PTO Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2017-11-06 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 11/06/2017 - Weekly Operations Conference Call; 11/09/2017 - Technical Services Weekly Meeting Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2017-11-06 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.5 0 MK Timesheet; Continue on MK Continuing Education Audit Documents Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2017-11-07 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 9 0 Continue working on Uganda Closeout Report; Due Diligence Weekly Meeting; Internal Corporate Project Activities Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2017-11-08 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 MK Timesheet; Continue on MK Continuing Education Audit Documents Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2017-11-08 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 8 0 Continue working on Uganda Closeout Report; Due Diligence Weekly Meeting; Internal Corporate Project Activities Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2017-11-09 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 11/06/2017 - Weekly Operations Conference Call; 11/09/2017 - Technical Services Weekly Meeting Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2017-11-09 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 7 0 Continue working on Uganda Closeout Report; Due Diligence Weekly Meeting; Internal Corporate Project Activities Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2017-11-09 OH-014 :OH-014 Overhead All Activities Regular Pay N 1 0 Business Development Program - Training Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2017-11-10 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 6 0 Continue working on Uganda Closeout Report; Due Diligence Weekly Meeting; Internal Corporate Project Activities Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2017-11-06 EHBU-TSRs :EHBU-TSRs TSR-01521-EHBU Total Uganda Support Regular Pay N 4 0 Histogram review, Scopr of work document Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2017-11-06 EHBU-TSRs :EHBU-TSRs TSR-01559-EHBU KOC Tender- New Rig Build Regular Pay N 1 0 Closeout Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2017-11-06 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 4 0 Schedule, Cost estimate, Weekly meeting, minutes of meeting, technical clarifications, DDAS SetPoint, FoxDrill engagement for competitive quote, Quote clarifications Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2017-11-07 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 9 0 Schedule, Cost estimate, Weekly meeting, minutes of meeting, technical clarifications, DDAS SetPoint, FoxDrill engagement for competitive quote, Quote clarifications Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2017-11-08 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 9 0 Schedule, Cost estimate, Weekly meeting, minutes of meeting, technical clarifications, DDAS SetPoint, FoxDrill engagement for competitive quote, Quote clarifications Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2017-11-09 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 8 0 Schedule, Cost estimate, Weekly meeting, minutes of meeting, technical clarifications, DDAS SetPoint, FoxDrill engagement for competitive quote, Quote clarifications Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2017-11-09 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Timesheet, Weekly TS meeting, Internal coordination for acceptable payment terms Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2017-11-10 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 2 0 Schedule, Cost estimate, Weekly meeting, minutes of meeting, technical clarifications, DDAS SetPoint, FoxDrill engagement for competitive quote, Quote clarifications Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2017-11-10 OH-006 :OH-006 Overhead All Activities Regular Pay N 2 0 Timesheet, Weekly TS meeting, Internal coordination for acceptable payment terms Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-06 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 0.75 0 Cost Estimate Review Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-06 OH-004 :OH-004 Overhead All Activities Regular Pay N 2.5 0 Weekly Ops Phone Call Weekly TS Mgmt Meeting TSR Board Mtgs Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-06 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Time sheet and timesheet review PEGNL License Renewal CE credits Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-06 OH-034 :OH-034 OH-034-003 Eastern Canada Regular Pay N 1 0 A0 Bulkhead Discussion with Joshua Non-billable top drive upgrade discussion with JL Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-06 Rig 209L-TSR :Rig 209L-TSR TSR-01501-209L BOP Hoist Test Beam Regular Pay N 1.25 0 Monday afternoon/Monday night - issue was cleared / no testing required Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-06 Rig 209L-TSR :Rig 209L-TSR TSR-01562-209L Completion Spooler Window on DM Regular Pay N 2 0 New pad eye placement for tie-down of spoolers; platform drawing review; analysis Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-06 Rig 216L-TSR :Rig 216L-TSR TSR-01613-216L 7500 PSI Mud Upgrade Regular Pay N 1 0 drawing review; field verification; scope review Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-07 Berkut-TSR :Berkut-TSR TSR-01614-BERP Cement Unit Jib Lifting Tool Regular Pay N 2 0 Drawing review; MTO review; analysis; closeout Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-07 EHBU-TSRs :EHBU-TSRs TSR-01521-EHBU Total Uganda Support Regular Pay N 1.5 0 Histogram / scope verification with HH Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-07 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Time sheet and timesheet review PEGNL License Renewal CE credits Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-07 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 3.5 0 PLUSPETROL - histogram review, revenue/expense layout for 2018/19 Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-07 OH-016 :OH-016 Overhead All Activities Regular Pay N 1 0 Review suspension of ABS class for 257 Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-07 Rig 216L-TSR :Rig 216L-TSR TSR-01613-216L 7500 PSI Mud Upgrade Regular Pay N 0.5 0 drawing review; field verification; scope review Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-08 Berkut-TSR :Berkut-TSR TSR-01605-BERP Snubbing Post Regular Pay N 1 0 closeout / and attachments Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-08 Berkut-TSR :Berkut-TSR TSR-01614-BERP Cement Unit Jib Lifting Tool Regular Pay N 1 0 Drawing review; MTO review; analysis; closeout Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-08 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.5 0 Weekly Ops Phone Call Weekly TS Mgmt Meeting TSR Board Mtgs Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-08 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Time sheet and timesheet review PEGNL License Renewal CE credits Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-08 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 1 0 PLUSPETROL - histogram review, revenue/expense layout for 2018/19 Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-08 OH-016 :OH-016 Overhead All Activities Regular Pay N 0.5 0 Review suspension of ABS class for 257 Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-08 OH-034 :OH-034 OH-034-003 Eastern Canada Regular Pay N 0.5 0 A0 Bulkhead Discussion with Joshua Non-billable top drive upgrade discussion with JL Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-08 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 1 0 platform weights for RS Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-08 Rig 209L-TSR :Rig 209L-TSR TSR-01562-209L Completion Spooler Window on DM Regular Pay N 0.25 0 New pad eye placement for tie-down of spoolers; platform drawing review; analysis Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-08 Rig 216L-TSR :Rig 216L-TSR TSR-01613-216L 7500 PSI Mud Upgrade Regular Pay N 2 0 drawing review; field verification; scope review Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-08 Rig 270L-TSR :Rig 270L-TSR TSR-01595-270L Skidding Pony Sub Regular Pay N 0.5 0 ROM cost estimate and assumptions to Exxon Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-09 Berkut-TSR :Berkut-TSR TSR-01605-BERP Snubbing Post Regular Pay N 2 0 closeout / and attachments Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-09 Berkut-TSR :Berkut-TSR TSR-01614-BERP Cement Unit Jib Lifting Tool Regular Pay N 1 0 Drawing review; MTO review; analysis; closeout Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-09 EHBU-TSRs :EHBU-TSRs TSR-01521-EHBU Total Uganda Support Regular Pay N 0.5 0 Histogram / scope verification with HH Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-09 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Weekly Ops Phone Call Weekly TS Mgmt Meeting TSR Board Mtgs Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-09 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Time sheet and timesheet review PEGNL License Renewal CE credits Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-09 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 2 0 PLUSPETROL - histogram review, revenue/expense layout for 2018/19 Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-09 Rig 209L-TSR :Rig 209L-TSR TSR-01562-209L Completion Spooler Window on DM Regular Pay N 0.25 0 New pad eye placement for tie-down of spoolers; platform drawing review; analysis Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-09 Rig 216L-TSR :Rig 216L-TSR TSR-01613-216L 7500 PSI Mud Upgrade Regular Pay N 1 0 drawing review; field verification; scope review Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-09 Rig 270L-TSR :Rig 270L-TSR TSR-01595-270L Skidding Pony Sub Regular Pay N 0.5 0 ROM cost estimate and assumptions to Exxon Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-10 Berkut-TSR :Berkut-TSR TSR-01605-BERP Snubbing Post Regular Pay N 1.5 0 closeout / and attachments Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-10 Berkut-TSR :Berkut-TSR TSR-01614-BERP Cement Unit Jib Lifting Tool Regular Pay N 0.5 0 Drawing review; MTO review; analysis; closeout Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-10 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.5 0 Weekly Ops Phone Call Weekly TS Mgmt Meeting TSR Board Mtgs Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-10 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Time sheet and timesheet review PEGNL License Renewal CE credits Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-10 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 1 0 PLUSPETROL - histogram review, revenue/expense layout for 2018/19 Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-10 Rig 216L-TSR :Rig 216L-TSR TSR-01613-216L 7500 PSI Mud Upgrade Regular Pay N 1.5 0 drawing review; field verification; scope review Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-11-10 Rig 270L-TSR :Rig 270L-TSR TSR-01595-270L Skidding Pony Sub Regular Pay N 0.5 0 ROM cost estimate and assumptions to Exxon Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2017-11-06 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.25 0 daily: TSR board meeting update (15 mins) 11/09: weekly TSR meeting Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2017-11-06 OH-019 :OH-019 Overhead All Activities Regular Pay N 1 0 weekly Sakhalin TSR update conference call. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2017-11-06 ORLAN-TSR :ORLAN-TSR TSR-01572-ORLP Choke Manifold Replacement Regular Pay N 6.75 0 PLACEHOLDER: 216 HP piping upgrade Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2017-11-07 OH-013 :OH-013 Overhead All Activities Regular Pay N 2.5 0 11/07: transmit TSR-01609-DWG; TSR-01582-CO 11/10: transmit TSR-01614-CTR&CO; TSR-01609-CO Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2017-11-07 ORLAN-TSR :ORLAN-TSR TSR-01572-ORLP Choke Manifold Replacement Regular Pay N 3.5 0 PLACEHOLDER: 216 HP piping upgrade Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2017-11-07 Rig 209L-TSR :Rig 209L-TSR TSR-01562-209L Completion Spooler Window on DM Regular Pay N 2 0 11/07-11/08: 6.5mT pad eye detail drawing, with updated model Preliminary work: updated CAD for HPPS TSR to George Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2017-11-08 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.25 0 daily: TSR board meeting update (15 mins) 11/09: weekly TSR meeting Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2017-11-08 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.75 0 11/08: meeting with Kyle and Rob to discuss SolidWorks license renewals 11/09: updated 209L model data Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2017-11-08 Rig 209L-TSR :Rig 209L-TSR TSR-01562-209L Completion Spooler Window on DM Regular Pay N 2 0 11/07-11/08: 6.5mT pad eye detail drawing, with updated model Preliminary work: updated CAD for HPPS TSR to George Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2017-11-09 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 daily: TSR board meeting update (15 mins) 11/09: weekly TSR meeting Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2017-11-09 OH-013 :OH-013 Overhead All Activities Regular Pay N 3.5 0 11/07: transmit TSR-01609-DWG; TSR-01582-CO 11/10: transmit TSR-01614-CTR&CO; TSR-01609-CO Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2017-11-10 OH-013 :OH-013 Overhead All Activities Regular Pay N 2 0 11/07: transmit TSR-01609-DWG; TSR-01582-CO 11/10: transmit TSR-01614-CTR&CO; TSR-01609-CO Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2017-11-10 Rig 209L-TSR :Rig 209L-TSR TSR-01562-209L Completion Spooler Window on DM Regular Pay N 4.5 0 11/07-11/08: 6.5mT pad eye detail drawing, with updated model Preliminary work: updated CAD for HPPS TSR to George Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2017-11-10 Rig 272L-TSR :Rig 272L-TSR TSR-01597-272L Mudmaster Installation Study Regular Pay N 1.5 0 Closeout Documentation preparation for 216L Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2017-11-06 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 On 11/6 and 11/10, travel from Houston to St. John's and St. John's to Houston. On 11/7, prepare slides and agenda material for PM refresh kickoff workshop in St. John's. On 11/8 and 11/9, PM refresh kickoff workshop in St. John's. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2017-11-06 OH-010 :OH-010 Overhead All Activities Regular Pay N 4 0 On 11/6 and 11/10, additional hours of travel from Houston to St. John's and St. John's to Houston. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2017-11-07 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 1 0 On 11/7 and 11/8, support review and optimization of Wood Top drive estimate to reduce power cables. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2017-11-07 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 On 11/6 and 11/10, travel from Houston to St. John's and St. John's to Houston. On 11/7, prepare slides and agenda material for PM refresh kickoff workshop in St. John's. On 11/8 and 11/9, PM refresh kickoff workshop in St. John's. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2017-11-07 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 On 11/7 and 11/8, timesheets and general opportunity support. Rate sheet. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2017-11-08 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 1 0 On 11/7 and 11/8, support review and optimization of Wood Top drive estimate to reduce power cables. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2017-11-08 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 On 11/6 and 11/10, travel from Houston to St. John's and St. John's to Houston. On 11/7, prepare slides and agenda material for PM refresh kickoff workshop in St. John's. On 11/8 and 11/9, PM refresh kickoff workshop in St. John's. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2017-11-08 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 On 11/7 and 11/8, timesheets and general opportunity support. Rate sheet. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2017-11-09 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 4 0 On 11/6 and 11/10, travel from Houston to St. John's and St. John's to Houston. On 11/7, prepare slides and agenda material for PM refresh kickoff workshop in St. John's. On 11/8 and 11/9, PM refresh kickoff workshop in St. John's. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2017-11-09 OH-009 :OH-009 OH-009-003 Husky Energy WREP Regular Pay N 6 0 On 11/9, Wood meeting in St. John's for Husky WRE. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2017-11-10 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 On 11/6 and 11/10, travel from Houston to St. John's and St. John's to Houston. On 11/7, prepare slides and agenda material for PM refresh kickoff workshop in St. John's. On 11/8 and 11/9, PM refresh kickoff workshop in St. John's. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2017-11-10 OH-010 :OH-010 Overhead All Activities Regular Pay N 4 0 On 11/6 and 11/10, additional hours of travel from Houston to St. John's and St. John's to Houston. Reck, John Engineer I 29656 Reck, John:Engineer I 2017-11-06 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 TS meeting and daily meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2017-11-06 OH-019 :OH-019 Overhead All Activities Regular Pay N 1 0 weekly meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2017-11-06 ORLAN-TSR :ORLAN-TSR TSR-01582-ORLP Poorboy Degasser (electrical) Regular Pay N 1.5 0 Closeout assistance Reck, John Engineer I 29656 Reck, John:Engineer I 2017-11-06 Rig 216L-TSR :Rig 216L-TSR TSR-01613-216L 7500 PSI Mud Upgrade Regular Pay N 5 0 Gap analysis, Southwest review, drawing review, valve dimensions, vendor meeting, drawing redlines Reck, John Engineer I 29656 Reck, John:Engineer I 2017-11-07 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.5 0 TS meeting and daily meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2017-11-07 ORLAN-TSR :ORLAN-TSR TSR-01601-ORLP Nitrogen Pre-Charge Valve Wrench Regular Pay N 2 0 Closeout, material documentation Reck, John Engineer I 29656 Reck, John:Engineer I 2017-11-07 Rig 209L-TSR :Rig 209L-TSR TSR-01560-209L Rig Skidding Claw(s) Regular Pay N 6 0 Analysis report, Closeout Reck, John Engineer I 29656 Reck, John:Engineer I 2017-11-08 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.5 0 TS meeting and daily meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2017-11-08 Rig 209L-TSR :Rig 209L-TSR TSR-01560-209L Rig Skidding Claw(s) Regular Pay N 0.5 0 Analysis report, Closeout Reck, John Engineer I 29656 Reck, John:Engineer I 2017-11-08 Rig 209L-TSR :Rig 209L-TSR TSR-01612-209L Mud Pump Gooseneck Regular Pay N 7.5 0 Drawing review, vendor quote, vendor clarifications, clamp clarifications, dimensions Reck, John Engineer I 29656 Reck, John:Engineer I 2017-11-09 Berkut-TSR :Berkut-TSR TSR-01614-BERP Cement Unit Jib Lifting Tool Regular Pay N 3.5 0 FEA analysis, Closeout review Reck, John Engineer I 29656 Reck, John:Engineer I 2017-11-09 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 TS meeting and daily meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2017-11-09 Rig 216L-TSR :Rig 216L-TSR TSR-01613-216L 7500 PSI Mud Upgrade Regular Pay N 4 0 Gap analysis, Southwest review, drawing review, valve dimensions, vendor meeting, drawing redlines Reck, John Engineer I 29656 Reck, John:Engineer I 2017-11-10 Berkut-TSR :Berkut-TSR TSR-01605-BERP Snubbing Post Regular Pay N 2 0 Padeye calc, closeout Reck, John Engineer I 29656 Reck, John:Engineer I 2017-11-10 Berkut-TSR :Berkut-TSR TSR-01614-BERP Cement Unit Jib Lifting Tool Regular Pay N 0.5 0 FEA analysis, Closeout review Reck, John Engineer I 29656 Reck, John:Engineer I 2017-11-10 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.5 0 TS meeting and daily meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2017-11-10 Rig 216L-TSR :Rig 216L-TSR TSR-01613-216L 7500 PSI Mud Upgrade Regular Pay N 3 0 Gap analysis, Southwest review, drawing review, valve dimensions, vendor meeting, drawing redlines Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2017-11-05 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 11/05 :Depart LFT @ 0945 & Arrive YYT 0120 11/06: Review maintenance task issues in SAP & how the system is being used; with Ron Taaffe, Steve Sharpe, & Jeffery Weitzel 11/07: Continue to study maintenance task update issues with Parker personnel & prepare to discuss with Exxon Mobil 11/08: Discuss options for updating SAP maintenance tasks, asset criticality, failures and counters for the Hibernia and explore unused functionality in SAP with Parker and Exxon Mobil personnel 11/09: Plan forward approach to SAP maintenance tasks updates, assignment for asset criticality, and exploration of unused SAP functionality 11/10: Depart YYT @ 1330 & Arrive LFT @ 2200 Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2017-11-06 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 7.5 0 11/05 :Depart LFT @ 0945 & Arrive YYT 0120 11/06: Review maintenance task issues in SAP & how the system is being used; with Ron Taaffe, Steve Sharpe, & Jeffery Weitzel 11/07: Continue to study maintenance task update issues with Parker personnel & prepare to discuss with Exxon Mobil 11/08: Discuss options for updating SAP maintenance tasks, asset criticality, failures and counters for the Hibernia and explore unused functionality in SAP with Parker and Exxon Mobil personnel 11/09: Plan forward approach to SAP maintenance tasks updates, assignment for asset criticality, and exploration of unused SAP functionality 11/10: Depart YYT @ 1330 & Arrive LFT @ 2200 Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2017-11-07 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 11/05 :Depart LFT @ 0945 & Arrive YYT 0120 11/06: Review maintenance task issues in SAP & how the system is being used; with Ron Taaffe, Steve Sharpe, & Jeffery Weitzel 11/07: Continue to study maintenance task update issues with Parker personnel & prepare to discuss with Exxon Mobil 11/08: Discuss options for updating SAP maintenance tasks, asset criticality, failures and counters for the Hibernia and explore unused functionality in SAP with Parker and Exxon Mobil personnel 11/09: Plan forward approach to SAP maintenance tasks updates, assignment for asset criticality, and exploration of unused SAP functionality 11/10: Depart YYT @ 1330 & Arrive LFT @ 2200 Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2017-11-08 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 11/05 :Depart LFT @ 0945 & Arrive YYT 0120 11/06: Review maintenance task issues in SAP & how the system is being used; with Ron Taaffe, Steve Sharpe, & Jeffery Weitzel 11/07: Continue to study maintenance task update issues with Parker personnel & prepare to discuss with Exxon Mobil 11/08: Discuss options for updating SAP maintenance tasks, asset criticality, failures and counters for the Hibernia and explore unused functionality in SAP with Parker and Exxon Mobil personnel 11/09: Plan forward approach to SAP maintenance tasks updates, assignment for asset criticality, and exploration of unused SAP functionality 11/10: Depart YYT @ 1330 & Arrive LFT @ 2200 Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2017-11-09 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 11/05 :Depart LFT @ 0945 & Arrive YYT 0120 11/06: Review maintenance task issues in SAP & how the system is being used; with Ron Taaffe, Steve Sharpe, & Jeffery Weitzel 11/07: Continue to study maintenance task update issues with Parker personnel & prepare to discuss with Exxon Mobil 11/08: Discuss options for updating SAP maintenance tasks, asset criticality, failures and counters for the Hibernia and explore unused functionality in SAP with Parker and Exxon Mobil personnel 11/09: Plan forward approach to SAP maintenance tasks updates, assignment for asset criticality, and exploration of unused SAP functionality 11/10: Depart YYT @ 1330 & Arrive LFT @ 2200 Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2017-11-10 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 11/05 :Depart LFT @ 0945 & Arrive YYT 0120 11/06: Review maintenance task issues in SAP & how the system is being used; with Ron Taaffe, Steve Sharpe, & Jeffery Weitzel 11/07: Continue to study maintenance task update issues with Parker personnel & prepare to discuss with Exxon Mobil 11/08: Discuss options for updating SAP maintenance tasks, asset criticality, failures and counters for the Hibernia and explore unused functionality in SAP with Parker and Exxon Mobil personnel 11/09: Plan forward approach to SAP maintenance tasks updates, assignment for asset criticality, and exploration of unused SAP functionality 11/10: Depart YYT @ 1330 & Arrive LFT @ 2200 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2017-11-06 OH-004 :OH-004 Overhead All Activities Regular Pay N 5 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2017-11-06 OH-006 :OH-006 Overhead All Activities Regular Pay N 2.5 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2017-11-06 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 2 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2017-11-07 OH-004 :OH-004 Overhead All Activities Regular Pay N 2 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2017-11-07 OH-006 :OH-006 Overhead All Activities Regular Pay N 5 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2017-11-07 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 2 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2017-11-08 OH-004 :OH-004 Overhead All Activities Regular Pay N 2 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2017-11-08 OH-006 :OH-006 Overhead All Activities Regular Pay N 5.5 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2017-11-08 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 1.5 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2017-11-09 OH-004 :OH-004 Overhead All Activities Regular Pay N 1.5 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2017-11-09 OH-006 :OH-006 Overhead All Activities Regular Pay N 1.5 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2017-11-09 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 5 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2017-11-10 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2017-11-10 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 4 0 Slack, Dan Senior Designer 30809 Slack, Dan:Senior Designer 2017-11-06 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Daily Team Meeting, Monday area meeting with Sakhlin. Weekly TSR Meeting. Slack, Dan Senior Designer 30809 Slack, Dan:Senior Designer 2017-11-06 OH-005 :OH-005 Overhead All Activities Regular Pay N 0.5 0 Timesheets Slack, Dan Senior Designer 30809 Slack, Dan:Senior Designer 2017-11-06 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 6.5 0 Created 209L-01-03-629-6_RA-suitcase-access-platform-handrail-details & 209L-01-03-629-7_RA-suitcase-access-platform-handrail-details. Revise drawings to rotate beams and finish details for moving connection to top beam. Overflow hours for TSR 1593 for drafting. Slack, Dan Senior Designer 30809 Slack, Dan:Senior Designer 2017-11-07 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 8 0 Created 209L-01-03-629-6_RA-suitcase-access-platform-handrail-details & 209L-01-03-629-7_RA-suitcase-access-platform-handrail-details. Revise drawings to rotate beams and finish details for moving connection to top beam. Overflow hours for TSR 1593 for drafting. Slack, Dan Senior Designer 30809 Slack, Dan:Senior Designer 2017-11-08 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 8 0 Created 209L-01-03-629-6_RA-suitcase-access-platform-handrail-details & 209L-01-03-629-7_RA-suitcase-access-platform-handrail-details. Revise drawings to rotate beams and finish details for moving connection to top beam. Overflow hours for TSR 1593 for drafting. Slack, Dan Senior Designer 30809 Slack, Dan:Senior Designer 2017-11-09 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.5 0 Daily Team Meeting, Monday area meeting with Sakhlin. Weekly TSR Meeting. Slack, Dan Senior Designer 30809 Slack, Dan:Senior Designer 2017-11-09 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 7.5 0 Created 209L-01-03-629-6_RA-suitcase-access-platform-handrail-details & 209L-01-03-629-7_RA-suitcase-access-platform-handrail-details. Revise drawings to rotate beams and finish details for moving connection to top beam. Overflow hours for TSR 1593 for drafting. Slack, Dan Senior Designer 30809 Slack, Dan:Senior Designer 2017-11-10 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 8 0 Created 209L-01-03-629-6_RA-suitcase-access-platform-handrail-details & 209L-01-03-629-7_RA-suitcase-access-platform-handrail-details. Revise drawings to rotate beams and finish details for moving connection to top beam. Overflow hours for TSR 1593 for drafting.