Name Billing Class Employee No. Item Line Class Transaction Date Job No. Customer Service Item Notes Payroll Item Billable Employee Paid Day Rate Duration Days Remarks Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2017-12-04 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 2 0 Worked on various aspects of the top drive maintenance plan, as well as help the other in the revision and draft of new procedures. Completed both heat exchangers, the top drive lube pump, the PS-21 and the PS-16 Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2017-12-05 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 4 0 Worked on various aspects of the top drive maintenance plan, as well as help the other in the revision and draft of new procedures. Completed both heat exchangers, the top drive lube pump, the PS-21 and the PS-16 Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2017-12-06 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 4 0 Worked on various aspects of the top drive maintenance plan, as well as help the other in the revision and draft of new procedures. Completed both heat exchangers, the top drive lube pump, the PS-21 and the PS-16 Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2017-12-07 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 3 0 Worked on various aspects of the top drive maintenance plan, as well as help the other in the revision and draft of new procedures. Completed both heat exchangers, the top drive lube pump, the PS-21 and the PS-16 Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2017-12-08 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 1 0 Worked on various aspects of the top drive maintenance plan, as well as help the other in the revision and draft of new procedures. Completed both heat exchangers, the top drive lube pump, the PS-21 and the PS-16 Carmichael, Steve Manager/Staff Consultant Carmichael, Steve:Manager/Staff Consultant 2017-12-05 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 1 0 Meetings PM review Carmichael, Steve Manager/Staff Consultant Carmichael, Steve:Manager/Staff Consultant 2017-12-06 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 1 0 Meetings PM review Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2017-12-07 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 8 0 study of Hibernia survey SoW and travel arrangement. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-12-05 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 1 0 Revising the PM documentation on SharePoint for the Hibernia Platform. Working the 10 items that are due for the TD Package to be presented Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-12-06 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 8 0 Revising the PM documentation on SharePoint for the Hibernia Platform. Working the 10 items that are due for the TD Package to be presented Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-12-07 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 6 0 Revising the PM documentation on SharePoint for the Hibernia Platform. Working the 10 items that are due for the TD Package to be presented Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-12-07 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 6 0 Attended conference calls regarding plans forward and protocols in making the recommended changes for existing procedures to the PKD recommended. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-12-08 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 3 0 Revising the PM documentation on SharePoint for the Hibernia Platform. Working the 10 items that are due for the TD Package to be presented Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-12-08 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 3 0 Attended conference calls regarding plans forward and protocols in making the recommended changes for existing procedures to the PKD recommended. Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2017-12-05 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 3 0 Created Life Extension and TD Upgrade Project Overview Slide Pack, Revised cost estimate and schedule per HMDC Comments, Coordinated NOV survey, Provide initial comments to MHWirth DC TD option, Coordinate RFI to Bardex, Research Heritage and Harmony information Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2017-12-06 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 1 0 Led NOV survey scope review meeting Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2017-12-06 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 4 0 Created Life Extension and TD Upgrade Project Overview Slide Pack, Revised cost estimate and schedule per HMDC Comments, Coordinated NOV survey, Provide initial comments to MHWirth DC TD option, Coordinate RFI to Bardex, Research Heritage and Harmony information Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2017-12-07 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 4 0 Created Life Extension and TD Upgrade Project Overview Slide Pack, Revised cost estimate and schedule per HMDC Comments, Coordinated NOV survey, Provide initial comments to MHWirth DC TD option, Coordinate RFI to Bardex, Research Heritage and Harmony information Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2017-12-08 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 5 0 Created Life Extension and TD Upgrade Project Overview Slide Pack, Revised cost estimate and schedule per HMDC Comments, Coordinated NOV survey, Provide initial comments to MHWirth DC TD option, Coordinate RFI to Bardex, Research Heritage and Harmony information Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2017-12-07 Hibernia Platform :Hibernia Platform TSR-01577-HIBP Monkey Board Handrail Assembly Regular Pay N 3 0 rev'd drawing up per site comments; closeout documentation created. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2017-12-04 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 5 0 On 12/5, PM review internal weekly meeting with Asset mgt. On 12/4, separated Rotary table OEM manual into 22 separate pdf files for ease of locating maintenance procedures, drawings and technical data. On 12/4, 12/5, and 12/7 separated Drawworks OEM manual into 21 separate pdf files for ease of locating maintenance procedures, drawings and technical data. On 12/4, separated Brake cooling unit OEM manual into 9 separate pdf files for ease of locating maintenance procedures, drawings and technical data. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2017-12-05 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 1 0 On 12/5, PM review internal weekly meeting with Asset mgt. On 12/4, separated Rotary table OEM manual into 22 separate pdf files for ease of locating maintenance procedures, drawings and technical data. On 12/4, 12/5, and 12/7 separated Drawworks OEM manual into 21 separate pdf files for ease of locating maintenance procedures, drawings and technical data. On 12/4, separated Brake cooling unit OEM manual into 9 separate pdf files for ease of locating maintenance procedures, drawings and technical data. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2017-12-06 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 3 0 On 12/6, provide preliminary review of DDM DC Top drive and gaps/technical clarifications for MHWirth to address. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2017-12-07 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 1 0 On 12/5, PM review internal weekly meeting with Asset mgt. On 12/4, separated Rotary table OEM manual into 22 separate pdf files for ease of locating maintenance procedures, drawings and technical data. On 12/4, 12/5, and 12/7 separated Drawworks OEM manual into 21 separate pdf files for ease of locating maintenance procedures, drawings and technical data. On 12/4, separated Brake cooling unit OEM manual into 9 separate pdf files for ease of locating maintenance procedures, drawings and technical data. Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2017-12-04 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 1 0 Reviewing and updating maintenance plans 10080753, 10080756, 10080763, 10080806, & 101126262. Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2017-12-05 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 2 0 Reviewing and updating maintenance plans 10080753, 10080756, 10080763, 10080806, & 101126262. Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2017-12-05 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 1 0 12/5/17 Project meeting. 1 Hour 12/6/17 & 12/7/17 Reviewing TDS-6S OEM manual for mechanical maintenance & PKD TDS-4S mechanical maintenance. Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2017-12-06 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 2 0 Reviewing and updating maintenance plans 10080753, 10080756, 10080763, 10080806, & 101126262. Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2017-12-06 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 2 0 12/5/17 Project meeting. 1 Hour 12/6/17 & 12/7/17 Reviewing TDS-6S OEM manual for mechanical maintenance & PKD TDS-4S mechanical maintenance. Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2017-12-07 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 2 0 Reviewing and updating maintenance plans 10080753, 10080756, 10080763, 10080806, & 101126262. Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2017-12-07 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 4 0 12/5/17 Project meeting. 1 Hour 12/6/17 & 12/7/17 Reviewing TDS-6S OEM manual for mechanical maintenance & PKD TDS-4S mechanical maintenance. Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2017-12-08 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 2 0 Reviewing and updating maintenance plans 10080753, 10080756, 10080763, 10080806, & 101126262.