Name Billing Class Employee No. Item Line Class Transaction Date Job No. Customer Service Item Notes Payroll Item Billable Employee Paid Day Rate Duration Days Remarks Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2017-12-11 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 2 0 Various meetings, and vendor communications to secure adequate TDS6 top drive service information. Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2017-12-12 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 1 0 Various meetings, and vendor communications to secure adequate TDS6 top drive service information. Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2017-12-13 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 2 0 Various meetings, and vendor communications to secure adequate TDS6 top drive service information. Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2017-12-14 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 1 0 Various meetings, and vendor communications to secure adequate TDS6 top drive service information. Carmichael, Steve Manager/Staff Consultant Carmichael, Steve:Manager/Staff Consultant 2017-12-10 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 0.5 0 Meetings on PM review Carmichael, Steve Manager/Staff Consultant Carmichael, Steve:Manager/Staff Consultant 2017-12-13 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 1 0 Meetings on PM review Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2017-12-11 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 8 0 1. Standby for NOV personnel to do NOV survey 2. NOV Survey for top drive and Driller's cabin Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2017-12-12 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 8 0 1. Standby for NOV personnel to do NOV survey 2. NOV Survey for top drive and Driller's cabin Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2017-12-13 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 8 0 1. Standby for NOV personnel to do NOV survey 2. NOV Survey for top drive and Driller's cabin Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2017-12-14 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 8 0 1. Standby for NOV personnel to do NOV survey 2. NOV Survey for top drive and Driller's cabin Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2017-12-15 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 8 0 1. Standby for NOV personnel to do NOV survey 2. NOV Survey for top drive and Driller's cabin Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2017-12-16 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 8 0 1. Standby for NOV personnel to do NOV survey 2. NOV Survey for top drive and Driller's cabin Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-12-11 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 2 0 Revising the PM documentation on SharePoint for the Hibernia Platform. Completed working the 10 items that were due for the TD Package to be presented to XOM. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-12-11 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 2 0 Attended conference calls regarding plans forward and protocols in making the recommended changes for existing procedures to the PKD recommended. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-12-12 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 2 0 Attend conference call with NOV Engineers regarding how to accomplish the required temperature rating of T3 for the Chopper Resistor. Research documentation regarding required temperature ratings of equipment in the CEC. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-12-12 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 2 0 Revising the PM documentation on SharePoint for the Hibernia Platform. Completed working the 10 items that were due for the TD Package to be presented to XOM. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-12-12 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 3 0 Attended conference calls regarding plans forward and protocols in making the recommended changes for existing procedures to the PKD recommended. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-12-13 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 2 0 Attend conference call with NOV Engineers regarding how to accomplish the required temperature rating of T3 for the Chopper Resistor. Research documentation regarding required temperature ratings of equipment in the CEC. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-12-13 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 2 0 Revising the PM documentation on SharePoint for the Hibernia Platform. Completed working the 10 items that were due for the TD Package to be presented to XOM. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-12-13 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 2.5 0 Attended conference calls regarding plans forward and protocols in making the recommended changes for existing procedures to the PKD recommended. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-12-14 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 2 0 Attend conference call with NOV Engineers regarding how to accomplish the required temperature rating of T3 for the Chopper Resistor. Research documentation regarding required temperature ratings of equipment in the CEC. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-12-14 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 1 0 Revising the PM documentation on SharePoint for the Hibernia Platform. Completed working the 10 items that were due for the TD Package to be presented to XOM. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2017-12-15 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 1.5 0 Revising the PM documentation on SharePoint for the Hibernia Platform. Completed working the 10 items that were due for the TD Package to be presented to XOM. Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2017-12-11 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 5 0 Attend weekly meeting with NOV, NOV quote clarifications, Discussion on chopper design for VFD house, Comparison of DDM1000 to TDS6S, Split out scope of work document for PLC life extension, Update cost estimate to split Life Extension Project and TD Upgrade Project, Coordinate NOV survey Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2017-12-12 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 6.5 0 Attend weekly meeting with NOV, NOV quote clarifications, Discussion on chopper design for VFD house, Comparison of DDM1000 to TDS6S, Split out scope of work document for PLC life extension, Update cost estimate to split Life Extension Project and TD Upgrade Project, Coordinate NOV survey Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2017-12-13 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 5 0 Attend weekly meeting with NOV, NOV quote clarifications, Discussion on chopper design for VFD house, Comparison of DDM1000 to TDS6S, Split out scope of work document for PLC life extension, Update cost estimate to split Life Extension Project and TD Upgrade Project, Coordinate NOV survey Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2017-12-13 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 1 0 Biweekly meeting Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2017-12-14 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 4 0 Attend weekly meeting with NOV, NOV quote clarifications, Discussion on chopper design for VFD house, Comparison of DDM1000 to TDS6S, Split out scope of work document for PLC life extension, Update cost estimate to split Life Extension Project and TD Upgrade Project, Coordinate NOV survey Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-12-12 Hibernia Platform :Hibernia Platform TSR-01576-HIBP Top Drive Maintenance Platform Regular Pay N 1 0 revise drawings revise calculations Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2017-12-13 Hibernia Platform :Hibernia Platform TSR-01576-HIBP Top Drive Maintenance Platform Regular Pay N 0.5 0 revise drawings revise calculations Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2017-12-11 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 4 0 On 12/13, bi-weekly conf call. On 12/11 and 12/13, review TDS6 pm plan revisions. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2017-12-12 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 4 0 On 12/12, review revised estimate, MH TD specs, Hibernia electrical system capacity. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2017-12-13 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 5 0 On 12/13, bi-weekly conf call. On 12/11 and 12/13, review TDS6 pm plan revisions. Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2017-12-11 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 1 0 Review and identify duplicates in TDS-6S mechanical tasks and standardizing those operations. Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2017-12-12 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 1 0 Meetings each day for Hibernia PM review status. Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2017-12-13 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 1 0 Meetings each day for Hibernia PM review status. Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2017-12-14 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 0.5 0 Meetings each day for Hibernia PM review status.