Name	Billing Class	Employee No.	Item Line Class	Transaction Date	Job No.	Customer	Service Item	Notes	Payroll Item	Billable	Employee Paid Day Rate	Duration	Days	Remarks
Anatra, Mike	Site Manager	MIKEANATRA	Anatra, Mike:Site Manager	2017-12-11	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP.	(Non-Billable): PM Review Change Order 5	Regular Pay	N		2	0	Various meetings, and vendor communications to secure adequate TDS6 top drive service information. 
Anatra, Mike	Site Manager	MIKEANATRA	Anatra, Mike:Site Manager	2017-12-12	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP.	(Non-Billable): PM Review Change Order 5	Regular Pay	N		1	0	Various meetings, and vendor communications to secure adequate TDS6 top drive service information. 
Anatra, Mike	Site Manager	MIKEANATRA	Anatra, Mike:Site Manager	2017-12-13	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP.	(Non-Billable): PM Review Change Order 5	Regular Pay	N		2	0	Various meetings, and vendor communications to secure adequate TDS6 top drive service information. 
Anatra, Mike	Site Manager	MIKEANATRA	Anatra, Mike:Site Manager	2017-12-14	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP.	(Non-Billable): PM Review Change Order 5	Regular Pay	N		1	0	Various meetings, and vendor communications to secure adequate TDS6 top drive service information. 
Carmichael, Steve	Manager/Staff Consultant		Carmichael, Steve:Manager/Staff Consultant	2017-12-10	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP.	(Non-Billable): PM Review Change Order 5	Regular Pay	N		0.5	0	Meetings on PM review
Carmichael, Steve	Manager/Staff Consultant		Carmichael, Steve:Manager/Staff Consultant	2017-12-13	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP.	(Non-Billable): PM Review Change Order 5	Regular Pay	N		1	0	Meetings on PM review
Ghadge, Sachin	Senior Engineer	34418	Ghadge, Sachin:Senior Engineer	2017-12-11	Hibernia Platform	:Hibernia Platform	TSR-01583-HIBP	Top Drive & Control System Upgrade	Regular Pay	N		8	0	1. Standby  for  NOV personnel  to do NOV survey 2. NOV Survey for top drive and Driller's cabin
Ghadge, Sachin	Senior Engineer	34418	Ghadge, Sachin:Senior Engineer	2017-12-12	Hibernia Platform	:Hibernia Platform	TSR-01583-HIBP	Top Drive & Control System Upgrade	Regular Pay	N		8	0	1. Standby  for  NOV personnel  to do NOV survey 2. NOV Survey for top drive and Driller's cabin
Ghadge, Sachin	Senior Engineer	34418	Ghadge, Sachin:Senior Engineer	2017-12-13	Hibernia Platform	:Hibernia Platform	TSR-01583-HIBP	Top Drive & Control System Upgrade	Regular Pay	N		8	0	1. Standby  for  NOV personnel  to do NOV survey 2. NOV Survey for top drive and Driller's cabin
Ghadge, Sachin	Senior Engineer	34418	Ghadge, Sachin:Senior Engineer	2017-12-14	Hibernia Platform	:Hibernia Platform	TSR-01583-HIBP	Top Drive & Control System Upgrade	Regular Pay	N		8	0	1. Standby  for  NOV personnel  to do NOV survey 2. NOV Survey for top drive and Driller's cabin
Ghadge, Sachin	Senior Engineer	34418	Ghadge, Sachin:Senior Engineer	2017-12-15	Hibernia Platform	:Hibernia Platform	TSR-01583-HIBP	Top Drive & Control System Upgrade	Regular Pay	N		8	0	1. Standby  for  NOV personnel  to do NOV survey 2. NOV Survey for top drive and Driller's cabin
Ghadge, Sachin	Senior Engineer	34418	Ghadge, Sachin:Senior Engineer	2017-12-16	Hibernia Platform	:Hibernia Platform	TSR-01583-HIBP	Top Drive & Control System Upgrade	Regular Pay	N		8	0	1. Standby  for  NOV personnel  to do NOV survey 2. NOV Survey for top drive and Driller's cabin
Gorrell, Chuck	Sr Site Mgr	10154	Gorrell, Chuck:Sr Site Mgr	2017-12-11	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP	PM Review Change Order 5	Regular Pay	N		2	0	Revising the PM documentation on SharePoint for the Hibernia Platform. Completed working the 10 items that were due for the TD Package to be presented to XOM.
Gorrell, Chuck	Sr Site Mgr	10154	Gorrell, Chuck:Sr Site Mgr	2017-12-11	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP.	(Non-Billable): PM Review Change Order 5	Regular Pay	N		2	0	Attended conference calls regarding plans forward and protocols in making the recommended changes for existing procedures to the PKD recommended. 
Gorrell, Chuck	Sr Site Mgr	10154	Gorrell, Chuck:Sr Site Mgr	2017-12-12	Hibernia Platform	:Hibernia Platform	TSR-01583-HIBP.	(Non-Billable): Top Drive & Control System Upgrade	Regular Pay	N		2	0	Attend conference call with NOV Engineers regarding how to accomplish the required temperature rating of T3 for the Chopper Resistor. Research documentation regarding required temperature ratings of equipment in the CEC.
Gorrell, Chuck	Sr Site Mgr	10154	Gorrell, Chuck:Sr Site Mgr	2017-12-12	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP	PM Review Change Order 5	Regular Pay	N		2	0	Revising the PM documentation on SharePoint for the Hibernia Platform. Completed working the 10 items that were due for the TD Package to be presented to XOM.
Gorrell, Chuck	Sr Site Mgr	10154	Gorrell, Chuck:Sr Site Mgr	2017-12-12	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP.	(Non-Billable): PM Review Change Order 5	Regular Pay	N		3	0	Attended conference calls regarding plans forward and protocols in making the recommended changes for existing procedures to the PKD recommended. 
Gorrell, Chuck	Sr Site Mgr	10154	Gorrell, Chuck:Sr Site Mgr	2017-12-13	Hibernia Platform	:Hibernia Platform	TSR-01583-HIBP.	(Non-Billable): Top Drive & Control System Upgrade	Regular Pay	N		2	0	Attend conference call with NOV Engineers regarding how to accomplish the required temperature rating of T3 for the Chopper Resistor. Research documentation regarding required temperature ratings of equipment in the CEC.
Gorrell, Chuck	Sr Site Mgr	10154	Gorrell, Chuck:Sr Site Mgr	2017-12-13	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP	PM Review Change Order 5	Regular Pay	N		2	0	Revising the PM documentation on SharePoint for the Hibernia Platform. Completed working the 10 items that were due for the TD Package to be presented to XOM.
Gorrell, Chuck	Sr Site Mgr	10154	Gorrell, Chuck:Sr Site Mgr	2017-12-13	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP.	(Non-Billable): PM Review Change Order 5	Regular Pay	N		2.5	0	Attended conference calls regarding plans forward and protocols in making the recommended changes for existing procedures to the PKD recommended. 
Gorrell, Chuck	Sr Site Mgr	10154	Gorrell, Chuck:Sr Site Mgr	2017-12-14	Hibernia Platform	:Hibernia Platform	TSR-01583-HIBP.	(Non-Billable): Top Drive & Control System Upgrade	Regular Pay	N		2	0	Attend conference call with NOV Engineers regarding how to accomplish the required temperature rating of T3 for the Chopper Resistor. Research documentation regarding required temperature ratings of equipment in the CEC.
Gorrell, Chuck	Sr Site Mgr	10154	Gorrell, Chuck:Sr Site Mgr	2017-12-14	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP	PM Review Change Order 5	Regular Pay	N		1	0	Revising the PM documentation on SharePoint for the Hibernia Platform. Completed working the 10 items that were due for the TD Package to be presented to XOM.
Gorrell, Chuck	Sr Site Mgr	10154	Gorrell, Chuck:Sr Site Mgr	2017-12-15	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP	PM Review Change Order 5	Regular Pay	N		1.5	0	Revising the PM documentation on SharePoint for the Hibernia Platform. Completed working the 10 items that were due for the TD Package to be presented to XOM.
Lambert, Joshua	Asst PM	JOSHLAMBERT	Lambert, Joshua:Asst PM	2017-12-11	Hibernia Platform	:Hibernia Platform	TSR-01583-HIBP.	(Non-Billable): Top Drive & Control System Upgrade	Regular Pay	N		5	0	Attend weekly meeting with NOV, NOV quote clarifications, Discussion on chopper design for VFD house, Comparison of DDM1000 to TDS6S, Split out scope of work document for PLC life extension, Update cost estimate to split Life Extension Project and TD Upgrade Project, Coordinate NOV survey
Lambert, Joshua	Asst PM	JOSHLAMBERT	Lambert, Joshua:Asst PM	2017-12-12	Hibernia Platform	:Hibernia Platform	TSR-01583-HIBP.	(Non-Billable): Top Drive & Control System Upgrade	Regular Pay	N		6.5	0	Attend weekly meeting with NOV, NOV quote clarifications, Discussion on chopper design for VFD house, Comparison of DDM1000 to TDS6S, Split out scope of work document for PLC life extension, Update cost estimate to split Life Extension Project and TD Upgrade Project, Coordinate NOV survey
Lambert, Joshua	Asst PM	JOSHLAMBERT	Lambert, Joshua:Asst PM	2017-12-13	Hibernia Platform	:Hibernia Platform	TSR-01583-HIBP.	(Non-Billable): Top Drive & Control System Upgrade	Regular Pay	N		5	0	Attend weekly meeting with NOV, NOV quote clarifications, Discussion on chopper design for VFD house, Comparison of DDM1000 to TDS6S, Split out scope of work document for PLC life extension, Update cost estimate to split Life Extension Project and TD Upgrade Project, Coordinate NOV survey
Lambert, Joshua	Asst PM	JOSHLAMBERT	Lambert, Joshua:Asst PM	2017-12-13	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP.	(Non-Billable): PM Review Change Order 5	Regular Pay	N		1	0	Biweekly meeting
Lambert, Joshua	Asst PM	JOSHLAMBERT	Lambert, Joshua:Asst PM	2017-12-14	Hibernia Platform	:Hibernia Platform	TSR-01583-HIBP.	(Non-Billable): Top Drive & Control System Upgrade	Regular Pay	N		4	0	Attend weekly meeting with NOV, NOV quote clarifications, Discussion on chopper design for VFD house, Comparison of DDM1000 to TDS6S, Split out scope of work document for PLC life extension, Update cost estimate to split Life Extension Project and TD Upgrade Project, Coordinate NOV survey
Mcmullen, Kyle	Engineering Discipline Manager	20461	Mcmullen, Kyle:Engineering Discipline Manager	2017-12-12	Hibernia Platform	:Hibernia Platform	TSR-01576-HIBP	Top Drive Maintenance Platform	Regular Pay	N		1	0	revise drawings  revise calculations
Mcmullen, Kyle	Engineering Discipline Manager	20461	Mcmullen, Kyle:Engineering Discipline Manager	2017-12-13	Hibernia Platform	:Hibernia Platform	TSR-01576-HIBP	Top Drive Maintenance Platform	Regular Pay	N		0.5	0	revise drawings  revise calculations
Osten, Greg	Project Manager	23110	Osten, Greg:Project Manager	2017-12-11	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP.	(Non-Billable): PM Review Change Order 5	Regular Pay	N		4	0	On 12/13, bi-weekly conf call.  On 12/11 and 12/13, review TDS6 pm plan revisions.
Osten, Greg	Project Manager	23110	Osten, Greg:Project Manager	2017-12-12	Hibernia Platform	:Hibernia Platform	TSR-01583-HIBP.	(Non-Billable): Top Drive & Control System Upgrade	Regular Pay	N		4	0	On 12/12, review revised estimate, MH TD specs, Hibernia electrical system capacity.
Osten, Greg	Project Manager	23110	Osten, Greg:Project Manager	2017-12-13	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP.	(Non-Billable): PM Review Change Order 5	Regular Pay	N		5	0	On 12/13, bi-weekly conf call.  On 12/11 and 12/13, review TDS6 pm plan revisions.
Rouse, Roger	Maintenance Supervisor	ROGERROUSE	Rouse, Roger:Maintenance Supervisor	2017-12-11	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP	PM Review Change Order 5	Regular Pay	N		1	0	Review and identify duplicates in TDS-6S mechanical tasks and standardizing those operations.
Rouse, Roger	Maintenance Supervisor	ROGERROUSE	Rouse, Roger:Maintenance Supervisor	2017-12-12	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP.	(Non-Billable): PM Review Change Order 5	Regular Pay	N		1	0	Meetings each day for Hibernia PM review status.
Rouse, Roger	Maintenance Supervisor	ROGERROUSE	Rouse, Roger:Maintenance Supervisor	2017-12-13	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP.	(Non-Billable): PM Review Change Order 5	Regular Pay	N		1	0	Meetings each day for Hibernia PM review status.
Rouse, Roger	Maintenance Supervisor	ROGERROUSE	Rouse, Roger:Maintenance Supervisor	2017-12-14	Hibernia Platform	:Hibernia Platform	TSR-01606-HIBP.	(Non-Billable): PM Review Change Order 5	Regular Pay	N		0.5	0	Meetings each day for Hibernia PM review status.