Name Billing Class Employee No. Item Line Class Transaction Date Job No. Customer Service Item Notes Payroll Item Billable Employee Paid Day Rate Duration Days Remarks Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2018-02-12 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 1 0 Weekly meeting, revise docs for easier management. Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2018-02-13 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 1 0 Weekly meeting, revise docs for easier management. Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2018-02-14 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 4 0 Went through C101-17-10A and began cleaning up procedures and populating the Task List Long Text Upload templates, in preparation for loading into SAP Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2018-02-15 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 4 0 Went through C101-17-10A and began cleaning up procedures and populating the Task List Long Text Upload templates, in preparation for loading into SAP Anatra, Mike Site Manager MIKEANATRA Anatra, Mike:Site Manager 2018-02-16 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 1 0 Went through C101-17-10A and began cleaning up procedures and populating the Task List Long Text Upload templates, in preparation for loading into SAP Carmichael, Steve Manager/Staff Consultant Carmichael, Steve:Manager/Staff Consultant 2018-02-12 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 1 0 Review and update PM task – Reduce PM task procedures to 132 characters or less per line item Carmichael, Steve Manager/Staff Consultant Carmichael, Steve:Manager/Staff Consultant 2018-02-13 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 2 0 Review and update PM task – Reduce PM task procedures to 132 characters or less per line item Carmichael, Steve Manager/Staff Consultant Carmichael, Steve:Manager/Staff Consultant 2018-02-14 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 3 0 Review and update PM task – Reduce PM task procedures to 132 characters or less per line item Carmichael, Steve Manager/Staff Consultant Carmichael, Steve:Manager/Staff Consultant 2018-02-15 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 2 0 Review and update PM task – Reduce PM task procedures to 132 characters or less per line item Carmichael, Steve Manager/Staff Consultant Carmichael, Steve:Manager/Staff Consultant 2018-02-16 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 2 0 Review and update PM task – Reduce PM task procedures to 132 characters or less per line item Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-12 2M Tek :2M Tek TSR-01621-2M-TEK Torque Sub Calibration Machine Regular Pay N 1 0 review plan, adjust work load, create meeting for Friday, review design with Dan, book hotel for Monday, make travel plans, communicate with 2mtek, review travel with Dan and review final design pictures and make list of questions for 2mtek, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-12 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.75 0 board meeting, TSR meeting, 4th quarter earnings meeting, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-12 OH-006 :OH-006 Overhead All Activities Regular Pay N 1.5 0 Problem with Outlook, helpdesk ticket with IT, 13 updates had to be installed, closed, reviewed BOP test issue from Hibernia with Mike Kyle and Rob, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-12 OH-009 :OH-009 OH-009-019 Iraq Regular Pay N 1.5 0 Add API information to a table for Crescent tender Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-12 Rig 270L-TSR :Rig 270L-TSR TSR-01622-270L Rig Layout Options 2018 Regular Pay N 2 0 review drawings with Dan, create closeout, submit to Kyle Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-12 Rig 272L-TSR :Rig 272L-TSR TSR-01608-272L Colville River Ice Bridge Crossing Regular Pay N 2 0 final review of Genesis report, mark up report and discuss with Tecky Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-13 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 0.5 0 Angola travel info, schedule clinic visit for offshore medical Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-13 Rig 270L-TSR :Rig 270L-TSR TSR-01622-270L Rig Layout Options 2018 Regular Pay N 4.5 0 review drawings with Dan, create closeout, submit to Kyle Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-13 Rig 272L-TSR :Rig 272L-TSR TSR-01608-272L Colville River Ice Bridge Crossing Regular Pay N 3 0 final review of Genesis report, mark up report and discuss with Tecky Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-14 2M Tek :2M Tek TSR-01621-2M-TEK Torque Sub Calibration Machine Regular Pay N 1 0 review plan, adjust work load, create meeting for Friday, review design with Dan, book hotel for Monday, make travel plans, communicate with 2mtek, review travel with Dan and review final design pictures and make list of questions for 2mtek, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-14 Rig 077B-TSR :Rig 077B-TSR TSR-01603-077B SEMS Package Regular Pay N 4 0 flow calcs Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-14 Rig 270L-TSR :Rig 270L-TSR TSR-01622-270L Rig Layout Options 2018 Regular Pay N 1 0 review drawings with Dan, create closeout, submit to Kyle Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-14 Rig 272L-TSR :Rig 272L-TSR TSR-01608-272L Colville River Ice Bridge Crossing Regular Pay N 2 0 final review of Genesis report, mark up report and discuss with Tecky Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-15 2M Tek :2M Tek TSR-01621-2M-TEK Torque Sub Calibration Machine Regular Pay N 2.5 0 review plan, adjust work load, create meeting for Friday, review design with Dan, book hotel for Monday, make travel plans, communicate with 2mtek, review travel with Dan and review final design pictures and make list of questions for 2mtek, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-15 OH-004 :OH-004 Overhead All Activities Regular Pay N 2.5 0 board meeting, TSR meeting, 4th quarter earnings meeting, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-15 OH-006 :OH-006 Overhead All Activities Regular Pay N 1.5 0 Problem with Outlook, helpdesk ticket with IT, 13 updates had to be installed, closed, reviewed BOP test issue from Hibernia with Mike Kyle and Rob, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-15 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 0.25 0 Angola travel info, schedule clinic visit for offshore medical Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-15 Rig 077B-TSR :Rig 077B-TSR TSR-01603-077B SEMS Package Regular Pay N 4.25 0 flow calcs Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-16 2M Tek :2M Tek TSR-01621-2M-TEK Torque Sub Calibration Machine Regular Pay N 1.5 0 review plan, adjust work load, create meeting for Friday, review design with Dan, book hotel for Monday, make travel plans, communicate with 2mtek, review travel with Dan and review final design pictures and make list of questions for 2mtek, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-16 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Problem with Outlook, helpdesk ticket with IT, 13 updates had to be installed, closed, reviewed BOP test issue from Hibernia with Mike Kyle and Rob, Elenburg, Tyler Engineer II 34119 Elenburg, Tyler:Engineer II 2018-02-16 Rig 077B-TSR :Rig 077B-TSR TSR-01603-077B SEMS Package Regular Pay N 3 0 flow calcs Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2018-02-12 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.5 0 (02/12/18) Team meeting. Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2018-02-12 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 8 0 (02/12/18) Reviewed comments from BP. Started drawing updates - 257B BOP stacks. (02/16/18) Created new BOP drawings with customer wellhead info - 257B Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2018-02-13 OH-001 :OH-001 Overhead All Activities Regular Pay N 8 0 Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2018-02-14 OH-001 :OH-001 Overhead All Activities Regular Pay N 8 0 Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2018-02-15 OH-001 :OH-001 Overhead All Activities Regular Pay N 8 0 Gasper, James Supervising Designer/Checker 23139 Gasper, James:Supervising Designer/Checker 2018-02-16 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 7.5 0 (02/12/18) Reviewed comments from BP. Started drawing updates - 257B BOP stacks. (02/16/18) Created new BOP drawings with customer wellhead info - 257B Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2018-02-12 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 2 0 Hibernia TD comparison Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2018-02-12 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Kan ban meetin TSR meeting Earnings call Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2018-02-12 TSR-01629 :TSR-01629 TSR-01629-004 Screening Phase - Non-Billable (PKD Only) Regular Pay N 4 0 Initial IT set up GE PO and MR Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2018-02-13 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 2 0 Hibernia TD comparison Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2018-02-13 TSR-01629 :TSR-01629 TSR-01629-002 Screening Phase - Parker Drilling Regular Pay N 2 0 BoD document Genesis kickoff meeting Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2018-02-13 TSR-01629 :TSR-01629 TSR-01629-004 Screening Phase - Non-Billable (PKD Only) Regular Pay N 5 0 Initial IT set up GE PO and MR Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2018-02-14 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 2 0 Hibernia TD comparison Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2018-02-14 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Kan ban meetin TSR meeting Earnings call Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2018-02-14 OH-013 :OH-013 Overhead All Activities Regular Pay N 1 0 worksheet update Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2018-02-14 TSR-01629 :TSR-01629 TSR-01629-004 Screening Phase - Non-Billable (PKD Only) Regular Pay N 5 0 Initial IT set up GE PO and MR Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2018-02-15 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 2 0 Hibernia TD comparison Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2018-02-15 OH-004 :OH-004 Overhead All Activities Regular Pay N 3 0 Kan ban meetin TSR meeting Earnings call Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2018-02-15 TSR-01629 :TSR-01629 TSR-01629-002 Screening Phase - Parker Drilling Regular Pay N 4 0 BoD document Genesis kickoff meeting Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2018-02-16 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 2 0 Hibernia TD comparison Ghadge, Sachin Senior Engineer 34418 Ghadge, Sachin:Senior Engineer 2018-02-16 TSR-01629 :TSR-01629 TSR-01629-002 Screening Phase - Parker Drilling Regular Pay N 4 0 BoD document Genesis kickoff meeting Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2018-02-12 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 4 0 Updating SAP Functional Equipment Maintenance Procedures to ensure the maximum 132 characters per line. Updating the review tracker on SharePoint. Reviewing documentation that MA sent me from the rig in proposed changes in existing maintenance procedures. Attending conference call meetings. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2018-02-12 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 2 0 Reviewing documentation from the Holly Platform and visiting with Allen Henley on the phone regarding same. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2018-02-13 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 2 0 Reviewing MH Wirth TD & Traveling Block information & Drawings. Reviewing the information that Billy Arnold with NOV sent. Attending NOV - Survey Report Review conference meeting call. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2018-02-13 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 4 0 Updating SAP Functional Equipment Maintenance Procedures to ensure the maximum 132 characters per line. Updating the review tracker on SharePoint. Reviewing documentation that MA sent me from the rig in proposed changes in existing maintenance procedures. Attending conference call meetings. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2018-02-13 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 2 0 Reviewing documentation from the Holly Platform and visiting with Allen Henley on the phone regarding same. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2018-02-14 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 2 0 Reviewing MH Wirth TD & Traveling Block information & Drawings. Reviewing the information that Billy Arnold with NOV sent. Attending NOV - Survey Report Review conference meeting call. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2018-02-14 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 4 0 Updating SAP Functional Equipment Maintenance Procedures to ensure the maximum 132 characters per line. Updating the review tracker on SharePoint. Reviewing documentation that MA sent me from the rig in proposed changes in existing maintenance procedures. Attending conference call meetings. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2018-02-14 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 2 0 Reviewing documentation from the Holly Platform and visiting with Allen Henley on the phone regarding same. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2018-02-15 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 3 0 Reviewing MH Wirth TD & Traveling Block information & Drawings. Reviewing the information that Billy Arnold with NOV sent. Attending NOV - Survey Report Review conference meeting call. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2018-02-15 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 2 0 Updating SAP Functional Equipment Maintenance Procedures to ensure the maximum 132 characters per line. Updating the review tracker on SharePoint. Reviewing documentation that MA sent me from the rig in proposed changes in existing maintenance procedures. Attending conference call meetings. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2018-02-15 OH-009 :OH-009 OH-009-024 MinKit Offshore Platform Regular Pay N 3 0 Reviewing documentation regarding fuel consumption verses submarine cable option. Reviewing documentation of the BOD located on Q;Drive, attending conference calls Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2018-02-15 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 2 0 Reviewing documentation from the Holly Platform and visiting with Allen Henley on the phone regarding same. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2018-02-16 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 4 0 Updating SAP Functional Equipment Maintenance Procedures to ensure the maximum 132 characters per line. Updating the review tracker on SharePoint. Reviewing documentation that MA sent me from the rig in proposed changes in existing maintenance procedures. Attending conference call meetings. Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2018-02-16 OH-009 :OH-009 OH-009-024 MinKit Offshore Platform Regular Pay N 2 0 Reviewing documentation regarding fuel consumption verses submarine cable option. Reviewing documentation of the BOD located on Q;Drive, attending conference calls Gorrell, Chuck Sr Site Mgr 10154 Gorrell, Chuck:Sr Site Mgr 2018-02-16 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 2 0 Reviewing documentation from the Holly Platform and visiting with Allen Henley on the phone regarding same. Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2018-02-12 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 02/12/2018 - Weekly Operations Conference Call; 02/15/2018 - Tech Services Weekly Meeting; PKD 4th QTR Earnings Meeting Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2018-02-12 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.5 0 MK Timesheet Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2018-02-12 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 9.5 0 Angola Due Diligence Report; Angola Due Diligence Opportunity Assessment Meeting; Angola Risk Spider Graph; Trip notes from Angola DD ; Argentina Due Diligence Entity Update Meeting; Argentina Due Diligence Closeout Report (Chase Signatures); Internal Corporate Project Activities Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2018-02-13 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 11 0 Angola Due Diligence Report; Angola Due Diligence Opportunity Assessment Meeting; Angola Risk Spider Graph; Trip notes from Angola DD ; Argentina Due Diligence Entity Update Meeting; Argentina Due Diligence Closeout Report (Chase Signatures); Internal Corporate Project Activities Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2018-02-14 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 11 0 Angola Due Diligence Report; Angola Due Diligence Opportunity Assessment Meeting; Angola Risk Spider Graph; Trip notes from Angola DD ; Argentina Due Diligence Entity Update Meeting; Argentina Due Diligence Closeout Report (Chase Signatures); Internal Corporate Project Activities Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2018-02-15 OH-004 :OH-004 Overhead All Activities Regular Pay N 3 0 02/12/2018 - Weekly Operations Conference Call; 02/15/2018 - Tech Services Weekly Meeting; PKD 4th QTR Earnings Meeting Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2018-02-15 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 6 0 Angola Due Diligence Report; Angola Due Diligence Opportunity Assessment Meeting; Angola Risk Spider Graph; Trip notes from Angola DD ; Argentina Due Diligence Entity Update Meeting; Argentina Due Diligence Closeout Report (Chase Signatures); Internal Corporate Project Activities Kuehn, Matt Project Manager 22143 Kuehn, Matt:Project Manager 2018-02-16 OH-009 :OH-009 OH-009-007 General Business Development Support Regular Pay N 9 0 Angola Due Diligence Report; Angola Due Diligence Opportunity Assessment Meeting; Angola Risk Spider Graph; Trip notes from Angola DD ; Argentina Due Diligence Entity Update Meeting; Argentina Due Diligence Closeout Report (Chase Signatures); Internal Corporate Project Activities Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2018-02-12 2M Tek :2M Tek TSR-01621-2M-TEK Torque Sub Calibration Machine Regular Pay N 1 0 Design review Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2018-02-12 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 1 0 MHWirth technical clarifications and analysis, NOV survey review meeting Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2018-02-12 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 1 0 Discussion with david, NOV, survey review meeting, discussion with MHWirth Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2018-02-12 TSR-01629 :TSR-01629 TSR-01629-002 Screening Phase - Parker Drilling Regular Pay N 1 0 Coordinate with team to align on weekly priorities, BoD presentation, Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2018-02-12 TSR-01629 :TSR-01629 TSR-01629-004 Screening Phase - Non-Billable (PKD Only) Regular Pay N 5 0 CTR for KV, Project setup in Oracle, PO issuance to GE, Weekly meeting with KV, SP setup, Genesis access for PKD office, Deliverable list and CTR development with Genesis, Email approval for Genesis subcontractor, Lead Genesis kick-off meeting, Project setup Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2018-02-13 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 0.5 0 MHWirth technical clarifications and analysis, NOV survey review meeting Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2018-02-13 TSR-01629 :TSR-01629 TSR-01629-004 Screening Phase - Non-Billable (PKD Only) Regular Pay N 9 0 CTR for KV, Project setup in Oracle, PO issuance to GE, Weekly meeting with KV, SP setup, Genesis access for PKD office, Deliverable list and CTR development with Genesis, Email approval for Genesis subcontractor, Lead Genesis kick-off meeting, Project setup Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2018-02-14 Hibernia Platform :Hibernia Platform TSR-01583-HIBP Top Drive & Control System Upgrade Regular Pay N 1.5 0 MHWirth technical clarifications and analysis, NOV survey review meeting Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2018-02-14 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 1 0 Discussion with david, NOV, survey review meeting, discussion with MHWirth Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2018-02-14 TSR-01629 :TSR-01629 TSR-01629-002 Screening Phase - Parker Drilling Regular Pay N 2 0 Coordinate with team to align on weekly priorities, BoD presentation, Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2018-02-14 TSR-01629 :TSR-01629 TSR-01629-004 Screening Phase - Non-Billable (PKD Only) Regular Pay N 5.5 0 CTR for KV, Project setup in Oracle, PO issuance to GE, Weekly meeting with KV, SP setup, Genesis access for PKD office, Deliverable list and CTR development with Genesis, Email approval for Genesis subcontractor, Lead Genesis kick-off meeting, Project setup Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2018-02-15 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 0.5 0 Discussion with david, NOV, survey review meeting, discussion with MHWirth Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2018-02-15 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Weekly TS meeting, Timesheet, SCM entro address update Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2018-02-15 TSR-01629 :TSR-01629 TSR-01629-004 Screening Phase - Non-Billable (PKD Only) Regular Pay N 8.5 0 CTR for KV, Project setup in Oracle, PO issuance to GE, Weekly meeting with KV, SP setup, Genesis access for PKD office, Deliverable list and CTR development with Genesis, Email approval for Genesis subcontractor, Lead Genesis kick-off meeting, Project setup Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2018-02-16 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 0.5 0 Update percent complete in template Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2018-02-16 OH-006 :OH-006 Overhead All Activities Regular Pay N 0.5 0 Weekly TS meeting, Timesheet, SCM entro address update Lambert, Joshua Asst PM JOSHLAMBERT Lambert, Joshua:Asst PM 2018-02-16 TSR-01629 :TSR-01629 TSR-01629-004 Screening Phase - Non-Billable (PKD Only) Regular Pay N 7 0 CTR for KV, Project setup in Oracle, PO issuance to GE, Weekly meeting with KV, SP setup, Genesis access for PKD office, Deliverable list and CTR development with Genesis, Email approval for Genesis subcontractor, Lead Genesis kick-off meeting, Project setup Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-12 OH-004 :OH-004 Overhead All Activities Regular Pay N 2.5 0 Weekly Operations Phone Conference Weekly TS Mgmt. Meeting Daily TSR board meeting Weekly TSR meeting (earning conf call) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-12 OH-006 :OH-006 Overhead All Activities Regular Pay N 2 0 timesheet and timesheet approvals IHS invoice ECAD Performance Appraisal Meeting with Rob Earnings Update Luncheon Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-12 OH-034 :OH-034 OH-034-010 Gulf of Mexico (includes compliance documentation – USCG) Regular Pay N 1 0 update compliance tracker Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-12 Rig 270L-TSR :Rig 270L-TSR TSR-01622-270L Rig Layout Options 2018 Regular Pay N 0.5 0 CO review and approval Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-12 Rig 272L-TSR :Rig 272L-TSR TSR-01591-272L NOVOS System Installation Regular Pay N 1 0 reviewing report Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-12 Rig 272L-TSR :Rig 272L-TSR TSR-01608-272L Colville River Ice Bridge Crossing Regular Pay N 1.5 0 Review Genesis report / meeting with MDQ Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-12 TSR-01629 :TSR-01629 TSR-01629-004 Screening Phase - Non-Billable (PKD Only) Regular Pay N 1 0 Board meetings Setting up timekeeping system Genesis on boarding Weekly Exxon Meeting Genesis PO SharePoint Meeting Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-13 2M Tek :2M Tek TSR-01621-2M-TEK Torque Sub Calibration Machine Regular Pay N 0.5 0 Design review Meetings with Tyler and Dan Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-13 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.5 0 Weekly Operations Phone Conference Weekly TS Mgmt. Meeting Daily TSR board meeting Weekly TSR meeting (earning conf call) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-13 OH-006 :OH-006 Overhead All Activities Regular Pay N 3 0 timesheet and timesheet approvals IHS invoice ECAD Performance Appraisal Meeting with Rob Earnings Update Luncheon Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-13 ORLAN-TSR :ORLAN-TSR TSR-01623-ORLP Orlan Service Beam CRI HP Pump Regular Pay N 1 0 Drawing review and hand calculations Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-13 Rig 209L-TSR :Rig 209L-TSR TSR-01615-209L DM External Stairs Regular Pay N 1 0 CO review and approval Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-13 Rig 272L-TSR :Rig 272L-TSR TSR-01608-272L Colville River Ice Bridge Crossing Regular Pay N 1 0 Review Genesis report / meeting with MDQ Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-13 TSR-01629 :TSR-01629 TSR-01629-004 Screening Phase - Non-Billable (PKD Only) Regular Pay N 2.5 0 Board meetings Setting up timekeeping system Genesis on boarding Weekly Exxon Meeting Genesis PO SharePoint Meeting Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-14 2M Tek :2M Tek TSR-01621-2M-TEK Torque Sub Calibration Machine Regular Pay N 0.5 0 Design review Meetings with Tyler and Dan Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-14 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.5 0 Weekly Operations Phone Conference Weekly TS Mgmt. Meeting Daily TSR board meeting Weekly TSR meeting (earning conf call) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-14 OH-006 :OH-006 Overhead All Activities Regular Pay N 2 0 timesheet and timesheet approvals IHS invoice ECAD Performance Appraisal Meeting with Rob Earnings Update Luncheon Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-14 OH-034 :OH-034 OH-034-005 Kazakhstan Regular Pay N 1 0 257B BOP stack-up drawings Quote for Rig Saver for EMD gensets (257) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-14 OH-034 :OH-034 OH-034-007 Indonesia Regular Pay N 1.5 0 comparison sketch between 264L and 1500 HP rig (Starr Energy) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-14 ORLAN-TSR :ORLAN-TSR TSR-01619-ORLP Choke Manifold Pressure Gauge Regular Pay N 1 0 CO review / approval Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-14 ORLAN-TSR :ORLAN-TSR TSR-01623-ORLP Orlan Service Beam CRI HP Pump Regular Pay N 0.5 0 Drawing review and hand calculations Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-14 Rig 209L-TSR :Rig 209L-TSR TSR-01626-209L Rig Access Relocation from PBM to DM-DSM Regular Pay N 0.5 0 CTR review and approval Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-14 Rig 270L-TSR :Rig 270L-TSR TSR-01622-270L Rig Layout Options 2018 Regular Pay N 1 0 CO review and approval Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-14 Rig 272L-TSR :Rig 272L-TSR TSR-01591-272L NOVOS System Installation Regular Pay N 0.5 0 reviewing report Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-14 TSR-01629 :TSR-01629 TSR-01629-004 Screening Phase - Non-Billable (PKD Only) Regular Pay N 0.5 0 Board meetings Setting up timekeeping system Genesis on boarding Weekly Exxon Meeting Genesis PO SharePoint Meeting Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-15 2M Tek :2M Tek TSR-01621-2M-TEK Torque Sub Calibration Machine Regular Pay N 0.5 0 Design review Meetings with Tyler and Dan Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-15 OH-004 :OH-004 Overhead All Activities Regular Pay N 1.5 0 Weekly Operations Phone Conference Weekly TS Mgmt. Meeting Daily TSR board meeting Weekly TSR meeting (earning conf call) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-15 OH-006 :OH-006 Overhead All Activities Regular Pay N 3 0 timesheet and timesheet approvals IHS invoice ECAD Performance Appraisal Meeting with Rob Earnings Update Luncheon Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-15 OH-034 :OH-034 OH-034-004 Aksai Regular Pay N 1.5 0 Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-15 OH-034 :OH-034 OH-034-005 Kazakhstan Regular Pay N 1 0 257B BOP stack-up drawings Quote for Rig Saver for EMD gensets (257) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-15 ORLAN-TSR :ORLAN-TSR TSR-01623-ORLP Orlan Service Beam CRI HP Pump Regular Pay N 0.5 0 Drawing review and hand calculations Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-15 TSR-01629 :TSR-01629 TSR-01629-004 Screening Phase - Non-Billable (PKD Only) Regular Pay N 1 0 Board meetings Setting up timekeeping system Genesis on boarding Weekly Exxon Meeting Genesis PO SharePoint Meeting Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-16 OH-006 :OH-006 Overhead All Activities Regular Pay N 2 0 timesheet and timesheet approvals IHS invoice ECAD Performance Appraisal Meeting with Rob Earnings Update Luncheon Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-16 OH-034 :OH-034 OH-034-005 Kazakhstan Regular Pay N 1 0 257B BOP stack-up drawings Quote for Rig Saver for EMD gensets (257) Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-16 TSR-01629 :TSR-01629 TSR-01629-002 Screening Phase - Parker Drilling Regular Pay N 2 0 Basis of Design Kick-Off Meeting Review of BOD / provide comments Mcmullen, Kyle Engineering Discipline Manager 20461 Mcmullen, Kyle:Engineering Discipline Manager 2018-02-16 TSR-01629 :TSR-01629 TSR-01629-004 Screening Phase - Non-Billable (PKD Only) Regular Pay N 1 0 Board meetings Setting up timekeeping system Genesis on boarding Weekly Exxon Meeting Genesis PO SharePoint Meeting Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2018-02-12 Hibernia Platform :Hibernia Platform TSR-01583-HIBP. (Non-Billable): Top Drive & Control System Upgrade Regular Pay N 1.5 0 compiled CAD drawings from NOV and MHWirth to check for pipe handling clearance. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2018-02-12 OH-004 :OH-004 Overhead All Activities Regular Pay N 1.5 0 daily: TSR board meeting update (30 mins) 02/12: online time sheets and time sheets to payroll 02/15: weekly TSR meeting/quarterly earning update meeting Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2018-02-12 OH-006 :OH-006 Overhead All Activities Regular Pay N 1.25 0 02/12: update Projectsense to include Genesis for time keeping 02/14: install/update AutoCAD standard for all users in HTSG Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2018-02-12 OH-013 :OH-013 Overhead All Activities Regular Pay N 1.25 0 02/12: transmit TSR-01615-DWG 02/13: transmit TSR-01615-CO; TSR-01619-CO 02/14: transmit TSR-01626-CTR; TSR-01622-CO Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2018-02-12 OH-019 :OH-019 Overhead All Activities Regular Pay N 1 0 weekly meeting with Sakhalin regarding ongoing TSR's Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2018-02-12 Rig 209L-TSR :Rig 209L-TSR TSR-01626-209L Rig Access Relocation from PBM to DM-DSM Regular Pay N 1.5 0 model concept for site review of door relocation in PB and access stair and platform. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2018-02-13 OH-013 :OH-013 Overhead All Activities Regular Pay N 1 0 02/12: transmit TSR-01615-DWG 02/13: transmit TSR-01615-CO; TSR-01619-CO 02/14: transmit TSR-01626-CTR; TSR-01622-CO Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2018-02-13 Rig 209L-TSR :Rig 209L-TSR TSR-01626-209L Rig Access Relocation from PBM to DM-DSM Regular Pay N 7 0 model concept for site review of door relocation in PB and access stair and platform. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2018-02-14 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.5 0 daily: TSR board meeting update (30 mins) 02/12: online time sheets and time sheets to payroll 02/15: weekly TSR meeting/quarterly earning update meeting Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2018-02-14 OH-006 :OH-006 Overhead All Activities Regular Pay N 4 0 02/12: update Projectsense to include Genesis for time keeping 02/14: install/update AutoCAD standard for all users in HTSG Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2018-02-14 Rig 209L-TSR :Rig 209L-TSR TSR-01626-209L Rig Access Relocation from PBM to DM-DSM Regular Pay N 2 0 model concept for site review of door relocation in PB and access stair and platform. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2018-02-14 TSR-01629 :TSR-01629 TSR-01629-002 Screening Phase - Parker Drilling Regular Pay N 1.5 0 updated Option 1: Krechet on GBS build Maersk CJ70 model and integrate with GBS and created 3D PDF file Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2018-02-15 OH-001 :OH-001 Overhead All Activities Regular Pay N 4 0 Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2018-02-15 OH-004 :OH-004 Overhead All Activities Regular Pay N 2 0 daily: TSR board meeting update (30 mins) 02/12: online time sheets and time sheets to payroll 02/15: weekly TSR meeting/quarterly earning update meeting Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2018-02-15 OH-009 :OH-009 OH-009-018 Kazakhstan Regular Pay N 2 0 convert PDF files to CAD drawing for BOP clearance on 257 Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2018-02-16 Rig 209L-TSR :Rig 209L-TSR TSR-01626-209L Rig Access Relocation from PBM to DM-DSM Regular Pay N 3 0 model concept for site review of door relocation in PB and access stair and platform. Nguyen, Lam Designer II 27172 Nguyen, Lam:Designer II 2018-02-16 TSR-01629 :TSR-01629 TSR-01629-002 Screening Phase - Parker Drilling Regular Pay N 5 0 updated Option 1: Krechet on GBS build Maersk CJ70 model and integrate with GBS and created 3D PDF file Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2018-02-12 OH-006 :OH-006 Overhead All Activities Regular Pay N 3 0 On 2/12, timesheets, weekly mtg and ops conf call. On 2/15, weekly mtg. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2018-02-12 TSR-01629 :TSR-01629 TSR-01629-002 Screening Phase - Parker Drilling Regular Pay N 1 0 On 2/12-2/16, continue BOD template and entries into BOD. Guide Minkit team formation. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2018-02-12 TSR-01629 :TSR-01629 TSR-01629-004 Screening Phase - Non-Billable (PKD Only) Regular Pay N 5 0 On 2/12-2/16, continue BOD template and entries into BOD. On 2/13, XOM conf call update. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2018-02-13 TSR-01629 :TSR-01629 TSR-01629-002 Screening Phase - Parker Drilling Regular Pay N 1 0 On 2/12-2/16, continue BOD template and entries into BOD. Guide Minkit team formation. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2018-02-13 TSR-01629 :TSR-01629 TSR-01629-004 Screening Phase - Non-Billable (PKD Only) Regular Pay N 7 0 On 2/12-2/16, continue BOD template and entries into BOD. On 2/13, XOM conf call update. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2018-02-14 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 1 0 On 2/14-2/16, PM review mtg, bi-weekly report. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2018-02-14 TSR-01629 :TSR-01629 TSR-01629-002 Screening Phase - Parker Drilling Regular Pay N 1 0 On 2/12-2/16, continue BOD template and entries into BOD. Guide Minkit team formation. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2018-02-14 TSR-01629 :TSR-01629 TSR-01629-004 Screening Phase - Non-Billable (PKD Only) Regular Pay N 7 0 On 2/12-2/16, continue BOD template and entries into BOD. On 2/13, XOM conf call update. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2018-02-15 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 2 0 On 2/14-2/16, PM review mtg, bi-weekly report. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2018-02-15 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 On 2/12, timesheets, weekly mtg and ops conf call. On 2/15, weekly mtg. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2018-02-15 TSR-01629 :TSR-01629 TSR-01629-002 Screening Phase - Parker Drilling Regular Pay N 1 0 On 2/12-2/16, continue BOD template and entries into BOD. Guide Minkit team formation. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2018-02-15 TSR-01629 :TSR-01629 TSR-01629-004 Screening Phase - Non-Billable (PKD Only) Regular Pay N 7 0 On 2/12-2/16, continue BOD template and entries into BOD. On 2/13, XOM conf call update. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2018-02-16 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 2 0 On 2/14-2/16, PM review mtg, bi-weekly report. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2018-02-16 TSR-01629 :TSR-01629 TSR-01629-002 Screening Phase - Parker Drilling Regular Pay N 1 0 On 2/12-2/16, continue BOD template and entries into BOD. Guide Minkit team formation. Osten, Greg Project Manager 23110 Osten, Greg:Project Manager 2018-02-16 TSR-01629 :TSR-01629 TSR-01629-004 Screening Phase - Non-Billable (PKD Only) Regular Pay N 4 0 On 2/12-2/16, continue BOD template and entries into BOD. On 2/13, XOM conf call update. Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-12 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Earnings call and earnings meeting, Board meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-12 OH-019 :OH-019 Overhead All Activities Regular Pay N 1 0 weekly meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-12 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 1 0 pipe inspection pipe rotator fabrication questions, base oil fittings questions, drains under rotary review Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-12 OH-034 :OH-034 OH-034-005 Kazakhstan Regular Pay N 1 0 10" diverter valve and line clarifications, quote check, gaps Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-12 ORLAN-TSR :ORLAN-TSR TSR-01572-ORLP Choke Manifold Replacement Regular Pay N 3 0 HPPS PO status, center line review, WOM shipments coordination, fittings clarifications Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-12 Rig 209L-TSR :Rig 209L-TSR TSR-01620-209L Active Tank Premix Piping Modification Regular Pay N 0.5 0 concept check, piping spec Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-12 Rig 209L-TSR :Rig 209L-TSR TSR-01626-209L Rig Access Relocation from PBM to DM-DSM Regular Pay N 1 0 concept development, 3D review, piping spec Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-13 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.5 0 Earnings call and earnings meeting, Board meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-13 OH-034 :OH-034 OH-034-005 Kazakhstan Regular Pay N 0.5 0 10" diverter valve and line clarifications, quote check, gaps Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-13 ORLAN-TSR :ORLAN-TSR TSR-01572-ORLP Choke Manifold Replacement Regular Pay N 2.5 0 HPPS PO status, center line review, WOM shipments coordination, fittings clarifications Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-13 ORLAN-TSR :ORLAN-TSR TSR-01619-ORLP Choke Manifold Pressure Gauge Regular Pay N 0.5 0 quote recommendation Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-13 Rig 209L-TSR :Rig 209L-TSR TSR-01620-209L Active Tank Premix Piping Modification Regular Pay N 1.5 0 concept check, piping spec Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-13 Rig 209L-TSR :Rig 209L-TSR TSR-01626-209L Rig Access Relocation from PBM to DM-DSM Regular Pay N 3 0 concept development, 3D review, piping spec Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-14 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.5 0 Earnings call and earnings meeting, Board meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-14 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 2 0 pipe inspection pipe rotator fabrication questions, base oil fittings questions, drains under rotary review Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-14 OH-034 :OH-034 OH-034-005 Kazakhstan Regular Pay N 1 0 10" diverter valve and line clarifications, quote check, gaps Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-14 ORLAN-TSR :ORLAN-TSR TSR-01572-ORLP Choke Manifold Replacement Regular Pay N 1 0 HPPS PO status, center line review, WOM shipments coordination, fittings clarifications Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-14 ORLAN-TSR :ORLAN-TSR TSR-01619-ORLP Choke Manifold Pressure Gauge Regular Pay N 0.5 0 quote recommendation Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-14 ORLAN-TSR :ORLAN-TSR TSR-01623-ORLP Orlan Service Beam CRI HP Pump Regular Pay N 1.5 0 drawing review, calculations review, FEA analysis Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-14 Rig 209L-TSR :Rig 209L-TSR TSR-01626-209L Rig Access Relocation from PBM to DM-DSM Regular Pay N 2 0 concept development, 3D review, piping spec Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-15 OH-004 :OH-004 Overhead All Activities Regular Pay N 2.5 0 Earnings call and earnings meeting, Board meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-15 OH-034 :OH-034 OH-034-001 Sakhalin Regular Pay N 2.5 0 pipe inspection pipe rotator fabrication questions, base oil fittings questions, drains under rotary review Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-15 OH-034 :OH-034 OH-034-005 Kazakhstan Regular Pay N 2 0 10" diverter valve and line clarifications, quote check, gaps Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-15 ORLAN-TSR :ORLAN-TSR TSR-01572-ORLP Choke Manifold Replacement Regular Pay N 0.5 0 HPPS PO status, center line review, WOM shipments coordination, fittings clarifications Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-15 ORLAN-TSR :ORLAN-TSR TSR-01623-ORLP Orlan Service Beam CRI HP Pump Regular Pay N 1 0 drawing review, calculations review, FEA analysis Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-16 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.5 0 Earnings call and earnings meeting, Board meeting Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-16 ORLAN-TSR :ORLAN-TSR TSR-01572-ORLP Choke Manifold Replacement Regular Pay N 1 0 HPPS PO status, center line review, WOM shipments coordination, fittings clarifications Reck, John Engineer I 29656 Reck, John:Engineer I 2018-02-16 ORLAN-TSR :ORLAN-TSR TSR-01623-ORLP Orlan Service Beam CRI HP Pump Regular Pay N 4.5 0 drawing review, calculations review, FEA analysis Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2018-02-13 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 2 0 Research O&M manuals for LTV Energy FC-1600 Mud Pumps Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2018-02-15 Hibernia Platform :Hibernia Platform TSR-01606-HIBP. (Non-Billable): PM Review Change Order 5 Regular Pay N 3 0 Research O&M manuals for LTV Energy FC-1600 Mud Pumps Rouse, Roger Maintenance Supervisor ROGERROUSE Rouse, Roger:Maintenance Supervisor 2018-02-16 Hibernia Platform :Hibernia Platform TSR-01606-HIBP PM Review Change Order 5 Regular Pay N 3 0 Revising maintenance plans 10080279, 10080294, & 10080309 on the FC-1600 Mud Pumps. Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2018-02-12 OH-004 :OH-004 Overhead All Activities Regular Pay N 3 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2018-02-12 OH-006 :OH-006 Overhead All Activities Regular Pay N 5 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2018-02-12 OH-009 :OH-009 OH-009-024 MinKit Offshore Platform Regular Pay N 1 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2018-02-13 OH-004 :OH-004 Overhead All Activities Regular Pay N 3 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2018-02-13 OH-006 :OH-006 Overhead All Activities Regular Pay N 3 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2018-02-13 OH-009 :OH-009 OH-009-024 MinKit Offshore Platform Regular Pay N 3 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2018-02-14 OH-004 :OH-004 Overhead All Activities Regular Pay N 3 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2018-02-14 OH-011 :OH-011 Overhead All Activities Regular Pay N 5 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2018-02-15 OH-004 :OH-004 Overhead All Activities Regular Pay N 2 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2018-02-15 OH-006 :OH-006 Overhead All Activities Regular Pay N 5 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2018-02-15 OH-009 :OH-009 OH-009-024 MinKit Offshore Platform Regular Pay N 2 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2018-02-16 OH-004 :OH-004 Overhead All Activities Regular Pay N 2 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2018-02-16 OH-006 :OH-006 Overhead All Activities Regular Pay N 1 0 Shank, Rob Manager/Staff Consultant 35358 Shank, Rob:Manager/Staff Consultant 2018-02-16 OH-009 :OH-009 OH-009-024 MinKit Offshore Platform Regular Pay N 2 0 Slack, Dan Senior Designer 30809 Slack, Dan:Senior Designer 2018-02-12 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.25 0 Daily meeting, TSR Update Meeting, Timesheets. Slack, Dan Senior Designer 30809 Slack, Dan:Senior Designer 2018-02-12 Rig 270L-TSR :Rig 270L-TSR TSR-01622-270L Rig Layout Options 2018 Regular Pay N 7.75 0 Options for walking 1A, 1B & 2 with matting layouts. 270L-01-SK-026-RA-Chayvo-water-well-plot-plan-north-south-well-rows, 270L-01-SK-028-RA-Chayvo-water-well-walking-path-layout-north-south-well-rows, 270L-01-SK-029-RA-Chayvo-water-well-walking-path-layout-east-west-well-rows, 270L-01-SK-024-RA-Chayvo-water-well-plot-plan, 270L-01-SK-027-RA-Chayvo-water-well-plot-plan-east-west-well-rows. Slack, Dan Senior Designer 30809 Slack, Dan:Senior Designer 2018-02-13 Rig 270L-TSR :Rig 270L-TSR TSR-01622-270L Rig Layout Options 2018 Regular Pay N 8 0 Options for walking 1A, 1B & 2 with matting layouts. 270L-01-SK-026-RA-Chayvo-water-well-plot-plan-north-south-well-rows, 270L-01-SK-028-RA-Chayvo-water-well-walking-path-layout-north-south-well-rows, 270L-01-SK-029-RA-Chayvo-water-well-walking-path-layout-east-west-well-rows, 270L-01-SK-024-RA-Chayvo-water-well-plot-plan, 270L-01-SK-027-RA-Chayvo-water-well-plot-plan-east-west-well-rows. Slack, Dan Senior Designer 30809 Slack, Dan:Senior Designer 2018-02-14 2M Tek :2M Tek TSR-01621-2M-TEK Torque Sub Calibration Machine Regular Pay N 5.75 0 Discuss design layout options Advantages vs. Disadvantages, Options for designs 1-4, create 3 model display modes for long sub, short sub & torque position for design option 4 Slack, Dan Senior Designer 30809 Slack, Dan:Senior Designer 2018-02-14 OH-004 :OH-004 Overhead All Activities Regular Pay N 0.25 0 Daily meeting, TSR Update Meeting, Timesheets. Slack, Dan Senior Designer 30809 Slack, Dan:Senior Designer 2018-02-14 Rig 270L-TSR :Rig 270L-TSR TSR-01622-270L Rig Layout Options 2018 Regular Pay N 2 0 Options for walking 1A, 1B & 2 with matting layouts. 270L-01-SK-026-RA-Chayvo-water-well-plot-plan-north-south-well-rows, 270L-01-SK-028-RA-Chayvo-water-well-walking-path-layout-north-south-well-rows, 270L-01-SK-029-RA-Chayvo-water-well-walking-path-layout-east-west-well-rows, 270L-01-SK-024-RA-Chayvo-water-well-plot-plan, 270L-01-SK-027-RA-Chayvo-water-well-plot-plan-east-west-well-rows. Slack, Dan Senior Designer 30809 Slack, Dan:Senior Designer 2018-02-15 2M Tek :2M Tek TSR-01621-2M-TEK Torque Sub Calibration Machine Regular Pay N 7 0 Discuss design layout options Advantages vs. Disadvantages, Options for designs 1-4, create 3 model display modes for long sub, short sub & torque position for design option 4 Slack, Dan Senior Designer 30809 Slack, Dan:Senior Designer 2018-02-15 OH-004 :OH-004 Overhead All Activities Regular Pay N 1 0 Daily meeting, TSR Update Meeting, Timesheets. Slack, Dan Senior Designer 30809 Slack, Dan:Senior Designer 2018-02-16 OH-008 :OH-008 Overhead All Activities Regular Pay N 8 0 Floating Holiday